HIE-ISOLDE Project Status Report 52nd ISOLDE & nTOF Technical Committee meeting February 3rd 2016 Y. Kadi On behalf of the HIE-ISOLDE Project Team.

Slides:



Advertisements
Similar presentations
Status of Cryogenics at point 4 following the power cut L. Tavian 20 August 2011.
Advertisements

Status of the SPL cavities at CERN I.Aviles & N. Valverde on behalf of SPL team 1I. Aviles & N. ValverdeLund, 11 December 2013.
ANL HWR Cryomodule Status Update 27 January 2015 Zachary Conway On behalf of the ANL Linac Development Group Argonne National Laboratory Physics Division.
HIE-ISOLDE Project: Status Report EXTRA COSTS AND ADDITIONAL RESOURCES CERN, 29 January 2013 Yacine Kadi.
HIE-ISOLDE contribution packages M. Pasini BE/RF.
Cavity status; recent KEK activities : Hayano (1) STF CM-1 cavities are; MHI-014: 3-rd VT:36MV/m (finished) MHI-015: 3-rd VT: > 18.4MV/m.
HIE-ISOLDE Project Status Report Y. Kadi for the HIE-ISOLDE Project Team 49th INTC Meeting CERN, 11 February 2015.
Summary of WG 2 - cavities W. Weingarten 15th SPL Collaboration Meeting CERN - 25/26 Nov Cavity WG.
TTF-II Status & Prospectives Nick Walker DESY 5 th ITRP Meeting – CALTECH.
STF EP, VT commissioning by FNAL AES001 H. Hayano, KEK
1 Status of the CLIC two-beam module program A. Samochkine, G. Riddone Acknowledgements to the Module WG members 4 February 2014 CLIC Workshop 2014 (3-7.
HIE-ISOLDE Project Status Report
Mid Term Review Meeting, 26 September 2012N. SURNAME1 * The research project has been supported by a Marie Curie Early Initial Training Network Fellowship.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
Test plan for SPL short cryomodule O. Brunner, W. Weingarten WW 1SPL cryo-module meeting 19 October 2010.
HIE-ISOLDE Project Status Report
E. KAKO (KEK) 2009' Oct. 26 ILC KEK Global Design Effort 1 Cavity Preparation for S1-Global Eiji Kako (KEK, Japan)
Spoke test in vertical cryostat IPNO-UU Meeting on spoke test program, 2 nd -3 st October 2013 IPNO Team.
HIE-ISOLDE Project Status Report Y. Kadi for the HIE-ISOLDE Project Team HIE-ISOLDE Physics Coordination WG Meeting CERN, 16 February 2015.
Commissioning of REX Jose Alberto Rodriguez, BE-OP-PSB (167538) on behalf of the ISOLDE operations team.
Cryogenics for crab cavities – SPS/LHC 2 nd HiLumi LHC meeting – Frascati (Italy) 15 November 2012 K. Brodzinski and L. Tavian on behalf of cryogenic team.
Floor plans, Infrastructure & Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling.
Plans and schedule for the Long Shutdown LS1 SGUI CERN, 2 February 2012 Hie-Isolde Erwin Siesling.
HIE-ISOLDE Project: Planning & Resources Y. Kadi (EN-HDO) and the HIE-ISOLDE Project team.
HIE-ISOLDE Project Status Report: Planning of Phase II 74th ISOLDE Collaboration Committee meeting November 10th 2015 Y. Kadi.
High power RF tests places at CERN O. Brunner, CERN 4th SPL Collaboration Meeting jointly with ESS.
HIE-ISOLDE Project Status Report 50th ISOLDE & nTOF Technical Committee meeting July 1st 2015 Y. Kadi.
TE-CRG Activities D. Delikaris, TE-CRG.
Status of the Spanish contribution to CTF3 L. García-Tabarés, F. ToralCERN, 17/9/2006.
DTL prototype summary and production sequence F.Grespan LNL _06_22 CDR.
SM18 Vertical & Horizontal Test 110/12/2013Mathieu Therasse CERN BE/RF A. Benoit, O. Brunner, E. Jensen, A. Macpherson, P. Maesen, K. Schirm, W. Venturini.
HIE ISOLDE commissioning of the cryogenic control system installation at CERN. LNL-INFN 22/07/2015 Dr. Marco Pezzetti (CERN )
HIE-ISOLDE Status Report Yacine Kadi on behalf of HIE-ISOLDE project team ISOLDE Annual Workshop, 5 December 2011.
Programme for the Physics Start-up Stable and radioactive beams Jose Alberto Rodriguez, BE-OP-PSB (167538)
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
Infrastructure status and plans at CERN 1) W. Weingarten/CERN TTC Milano 28 February - 3 March W. Weingarten/CERN 1)Most of the slides are based.
WP1: Superconducting Cavity Developments and Tests Walter Venturini Delsolaro Mid Term Review Meeting, 26 September 2012 CATHI Marie Curie Initial Training.
HIE ISOLDE Linac Short Technical Description W. Venturini Delsolaro Material from: L. Alberty, J. Bauche, Y. Leclerq, R. Mompo, D. Valuch, D. Voulot, P.
ESS Program Plan and Schedule Update
WP High Beta Cavities Delivery
Resource Loaded Schedule and Budget Profile
CC LLRF SM18 test plan and BA6 infrastructure
Spoke section of the ESS linac: - Status of prototypes and CDS-SL
CSP 25th November 2010 Technical agreement number 3: overview
WP-46 XFEL 3rd harmonic system XFEL Project Progress Report (1-2010)
HIE-ISOLDE Report Jose Alberto Rodriguez on behalf of Yacine Kadi and the HIE-ISOLDE project team.
Complementary ISTC Projects #3888, 3889p
FCC R&D WP5 Cavity Fabrication Status May 2017 M
SPS cryogenic proximity equipment and SM18 validation
Infrastructure inventory and use
Update on HW commissioning
ESS RF Development at Uppsala University
Status of the cryogenic system for B180
The HIE—ISOLDE Cryogenic System, its Infrastructure and Considerations for Phase 3 O. Pirotte (TE/CRG)
HIE-ISOLDE Status Report
UK RFD Pre-Series cryomodule
SRF Section Cuvée 2014.
HIE-ISOLDE Project: Planning & Resources
Injector Performance Requirements Conventional Facilities Update
Operation experience of cryogenic system and cryomodules for the superconducting linear accelerator at IUAC, New Delhi. T S Datta ( On behalf of Cryogenics.
HIE-LINAC status report
HIE-ISOLDE Project: Status Report
IHEP Cryomodule Status
IHEP ILC Cavity Status Jiyuan Zhai (IHEP)
Report on HIE-ISOLDE Status
HIE-ISOLDE contribution packages
Prototype cryomodule development
Teleconference ACS – FREIA 19th June 2017
UPPSALA UNIVERSITY_GERSEMI PROJECT
SuRf Lab: (STFC) VTF Infrastructure and Process
Presentation transcript:

HIE-ISOLDE Project Status Report 52nd ISOLDE & nTOF Technical Committee meeting February 3rd 2016 Y. Kadi On behalf of the HIE-ISOLDE Project Team

OUTLINE Status of the Machine RF coupler issues CM2 assembly Shut-down works Schedule MeV/u Conclusions 2

Main Achievements The 2015 Commissioning campaign achieved its goals CM design choices validated SC cavities performance were confirmed with beam RF coupler problem identified, being addressed Physics run started on 19 th October, on schedule

RF Line/Coupler Issue 4 courtesy W. Venturini, black: SM18 60W off resonance blue: Cryolab 60W red: SM18 60W on resonance Cold tests at SM18

RF Line/Coupler Issue 5 courtesy W. Venturini,  Triggering phenomenon is pure RF heating  Key is cooling of the coupler antenna  New thermalization of copper and cable  Change antenna material (Cu OFE), weld antenna to cable  Crash program: Full validation in SM18 (critical path)

Validation tests in SM18 (December 2015) 6 new Cu antenna (before assembly) coupler additional thermalization courtesy W. Venturini,

Heat run with LLRF loops closed (Jan 2016) 7 4 days at 6 MV/m with amplitude and phase controlled, and ~ 90 W forward power courtesy W. Venturini,

Assembly of CM2 8 Courtesy Y. Leclerq,

Dismounting & Transport of CM1 9 Cryo Module 1 transport to SM18: for retrofitting of the couplers. Friday 8 January. To be received back end of March. courtesy E. Siesling,

Preparation for running w/ CM1 + CM2 Main HIE ISOLDE installation and start-up tasks: -Removal CM1: End-of-year 2015 / Wk Modifications and repair BI Dboxes: Jan 2015 – April Installation CM2: end Feb – end March Installation REX 9-Gap RF amplifier: end Feb – end March Re-installation CM1: end March – end April Cryo modifs & maintenance: Dec 2015 – end April HW & Beam commissioning CM1 & CM2: May – mid Aug 2016 courtesy E. Siesling,

OUTLINE Status of the Machine RF coupler issues CM2 assembly Shut-down works Schedule MeV/u Conclusions 11

Forecast for HIE-ISOLDE Phase 2 (years ) 12 Today CM3 + CM4 part procurement => 95% completed XT00 modif. CM3 assembly C.R. free (scenario 3) Waiting for C.R. free (CM1 being retrofitted) CM3 test in M9 bunker CM4 assembly CM3 install General remarks:  Test in M9 bunker are foreseen for CM3 and CM4 while the HIE-ISOLDE facility is in operation  XT00 modification for PHASE 2 EDMS: courtesy F. Formenti, Critical Issue with quality and availability of industry produced copper substrates for CM3

CM2/CM3 cavities status (2015) 13 Productio n process QS2QS5QS7QS8QS9QS10QS11QS12QS13QS Substrate reception xxxxxxxxWE34 Frequency pre-tuning NPxxxxx WE36 Annealing NP xx WE40 Surface treatment xxxxxWE35NPWE41 Nb coating xxxx Cut & inspection at CERN WE36 Process stopped due to substrate non-conformity WE42 RF vertical test at 4.5K WE36xxxWE40WE45 Storage /on hold CM2 CM3 Nb stripping

Performance of series cavities for CM2 (vertical test) 14 nameEacc (10W) [MV/m]Pc (6MV/m) [W] QS QS QS QS QS QS W  How to get better substrates for CM4 Change raw material specs? Weld parameters? thermal treatments? 3 pre-machined cavities not annealed at RI (QS21-23) High(er) beta cavity machined out of bulk w/o beam ports => New design & production process

Status: CM3 & CM4 15

Overall Summary Radioactive beam delivered to Miniball experiment on Oct. 22 nd 2015 as initially planned. The results of the hardware tests highlighted that CM1 is not fully qualified for sustained operation (problem on RF couplers): CM1 has been de-installed and will be re-worked during this shutdown; New RF couplers with improved thermalisation of the RF power line tested on QS12 and installed on CM2. New coherent planning is proposed for Phase 2 Agree with Collaboration on a common scope for Physics run 2 & 3 ( ) Preparation of CM3/CM4 components on-going Issue with cavity substrates being addressed Procurement for the 3 rd beam line and extension of XT02 for HELIOS has been launched

Thank you for your attention

HIE ISOLDE Cu QWR series production Order for 15 (+5) pieces placed Production planning: first cavity due by November 2013 QS1 delivered in… June 2014 QS1 non conformities: weld projections, geometry QS2 delivered in July 2014 QS2 non conformities: traces of foreign material, geometry QS3 delivered in August 2014 QS3: defects close to the weld HAZ seen for the first time Constant delays during production, and recurrent defect issues Several interventions at the company: weld parameters retuned, magnetic steering in EB machine fixed, weld preparation reviewed: each time problem seemed solved… But is was not: by QS11, 40% of the production was badly affected In July 2015 shrink fitting and welding at RI were put on hold We decided to start systematic investigations at CERN In December green light was given to RI to finalize QS14 and QS15 Severe delays and uncertainties on the planning persisting in courtesy W. Venturini,

How to get usable substrates (degraded mode option for CM3) QS14  at RI for final machining QS15  at RI for shrink fit and weld QS13 is under reparation at CERN with EBW. Can it be finalized at CERN? QS6 was laser “repaired” by RI: we could try to use it but would require tumbling + heavy SUBU, or EP QS11 is on hold at CERN, it has cracks but the geometry is finalized: repairing it here is the quickest way to restart coating! 19 courtesy W. Venturini,

Heat load inventory for 4 CM HIE-ISOLDE Cost & Schedule review - 22 Nov Heat load typeQuantity [-] Individual load [W] or [g/s] K [W] 50K-75 K [W] Liquefaction [g/s] Low-β 4.5K (RF)070 High-β 4.5K (RF) RF power supply cable K41352 Cryostat K Transfer 4.5 K Trans. line K Dewar 2’ K133 Flexi. line with 4.5 K24496 Cryogenic 4.5 K30390 Cryogenic K16348 Current leads for 4 solenoids TOTAL latest measures

Heat load vs existing cold box cooling power ► Summary table: ► Remark: «ALEPH» and «Hall 180» cold boxes require the same cycle flow of 155 g/s (provided by the compressors), but « ALEPH » cold box has only 2 turbines whereas « Hall 180 » has 3 turbines. HIE-ISOLDE Cost & Schedule review - 22 Nov K level [W] 50 K - 75 K level [W] Liquefaction [g/s] Client’s heat load inventory with 2 cryo-mod Client’s heat load inventory with 4 cryo-mod Client’s heat load inventory with 6 cryo-mod « ALEPH » cold box cooling power (measured)630Not measured1.7 « Hall 180 » cold box cooling power (measured)1050Not measured

Forecast for HIE-ISOLDE Phase 2 (years ) 22 CM4 assembly CM3 commissioning & beam commissioning Window for XT02 extension, XT03 installation & commissioning Run PHASE 2a with CM1+CM2+CM3 & XT01+XT02+XT03 CM4 test in M9 bunker, ………. then put on hold (adj. window) Beam commiss. Run PHASE 2b CM4 installation, commissioning General remarks:  PHASE 2 run could be split into PHASE 2a (2017) and PHASE 2b (2018)  HIE-ISOLDE Physics workshop in February 1 st 2016  Regain RF performance with high-beta cavities of CM4 EDMS: courtesy F. Formenti,

3D view of HELIOS on XT02