PARTNER / MAJOR CONTRACT Swales Aerospace MISSION MANAGER Frank Snow PRINCIPAL INVESTIGATOR Vassilis Angelopolos (UCB) UPN: Time History of Events and Macroscale Interactions during Substorms (THEMIS) PROJECT MANAGER Peter Harvey INSTRUMENT MANAGER William Davis LRD October 2006 PHASE C/D GSFC PROJECT SCIENTIST David Sibeck
THEMIS Probe 2 at Swales 11/03/05
LEGEND GOOD SHAPE MINOR PROBLEM MAJOR PROBLEM R Y THEMIS PROJECT SUMMARY LAUNCH VEHICLE LAUNCH SITE BUSINESS R & D BUDGET MPS BUDGET MANPOWER PROCUREMENT SCHEDULE MASS RESERVES POWER COST SUMMARY COST TECHNICAL SCHEDULE OVERALL Y YY MISSION ANALYSIS PROJECT MGT SYSTEMS ENGR EXT INTERFACES SR&QA GENERAL FGM IDPU EFI SST ESA INSTRUMENTS SCM MECHANICAL THERMAL PROPULSION ELECTRICAL AUG GN&C SEP SPACECRAFT COMMUNICATIONS SOFTWARE GSE SYSTEMS MOC SODA GROUND SYSTEMS GBO ANTENNA Y 4 Y OCT AUG SEP OCT AUG SEPOCT AUG SEPOCT AUGSEPOCT AUGSEPOCT AUG SEPOCT AUGSEPOCT Y Y Y Y Y R Y Y
LIKELIHOODLIKELIHOOD CONSEQUENCES Approach M – Mitigate W – Watch A – Accept R - Research * Criticality TrendID Diplexer Multipaction Testing Risk TitleAppr.Rank Decreasing (Improving) Increasing (Worsening) Unchanged New since last month L x C Trend 10/28/05 Med High Low THEMIS Top Risks THEMIS 3 6 M 1 M M 5 Orbit Debris Analysis 6 M Insufficient Schedule Reserves for October 2006 Launch Probe Dry Mass Reserves Insufficient support during Mission I & T 2 4 Transponder lost of lock M 2 M 4 5
Risk Focus THEMIS 10/28/05 CommentsApproach & PlanRisk StatementRank, Title, Criticality 6 3. Probe Dry Mass Reserves <15% Criticality If: The Probe dry mass reserve is below the recommended margin of 15%, Then: Fuel propellant and delta-V capability is reduced and secondary science will be impacted. Med Mitigate: All mass changes approved at THEMIS Project level. 90% of Probe 1 mass has been weighed. Mass budget reserves is 7.7%. No changes to mass reserves 1.Insufficient Schedule Reserves Criticality If: The project cannot develop a robust resource loaded schedule for the production mode of delivering 5 spacecraft buses and 25 instruments, Then: The project schedule reserves will quickly erode. Mitigate: Organize schedule reviews with AETD Status and review project schedules on weekly basis Project schedule reserves is 22 days (1.1 mo/yr). First Probe bus will be delivered to UCB in mid November. Med Code 500 and APL are reviewing multipaction test margins. Mitigate: Work with Code 560 to develop appropriate diplexer acceptance tests. If: Diplexer is not properly tested for multipaction Then: Diplexer performance maybe compromised. 2. Diplexer Multipaction Testing Criticality Med
Risk Focus THEMIS 10/28/05 CommentsApproach & PlanRisk StatementRank, Title, Criticality 7 GSE modified so this anomaly can be isolated to either the GSE or transponder. Transponder #3 and #4 have completed ATP without repeating the failure Transponder #5 has initiated ATP Mitigate: Monitor transponders 2-5 for repeat of failure. Code 500 performing a system of communication system If: Transponder is the cause of the anomoly Then: Project schedule will be impacted 4. Lost of lock during ATP (non repeatable) believed to be a GSE anamoly Criticality Med If: The reliability for S/C post-mission disposal being less than.99 is deemed unacceptable, Then: Significant cost, schedule, and mission impact can result. Mitigate: Obtain early approval from NASA/HQ for the current reliability value. Swales incorporating Boeing/KSC launch vehicle data for final report. ODA rev B will be submitted 11/30. Low 5. Orbit Debris Analysis (spacecraft) Criticality Low 6. Insufficient support during Mission I & T Criticality If: UCB SSL has inadequate spacecraft bus support during mission I & T Then: Problem and failures during testing will impact project schedule reserve Mitigate: Develop a detailed resource (personnel, facility, GSE) loaded schedule for mission I &T. Obtain needed commitments from support groups (i.e. Swales, JPL, SSL etc.) Code 300 will provide additional QA and Safety support at both UCB and JPL. Code 500 is reviewing Mission I&T plan and will provide recommendations
THEMIS RFA’s 8
CY 2005 MILESTONES CY 2004 THEMIS INSTRUMENT TOP LEVEL SCHEDULE STATUS AS 11/01/05 MISSION MGR. : FRANK SNOW 1 MAJOR REVIEWS IDPU DEVELOPMENT IDPU ETU DESIGN, FAB, I&T IDPU FLIGHT FABRICATION & I&T 2 EFI SPB / AXB DEVELOPMENT EFI SPB DESIGN, FAB, I&T (ETU & FLT) EFI AXB DESIGN, FAB, I&T (ETU & FLT) 3 ESA DEVELOPMENT ESA ETU DESIGN, FAB, I&T ESA FLIGHT FABRICATION & I&T 4 SST DEVELOPMENT SST ETU DESIGN, FAB, I&T SST FLIGHT FABRICATION & I&T 5 FGM DEVELOPMENT FGM ETU DESIGN, FAB, I&T FGM FLIGHT FABRICATION & I&T 6 SCM DEVELOPMENT SCM EM DESIGN, FAB, I&T SCM FLIGHT FABRICATION & I&T 8 INSTRUMENT I&T INSTRUMENT INTEGRATION & TEST MAGBOOM FLIGHT FAB & I&T FLT 1 BD FAB/ASSY COMPL BOARD I&T COMPL. IDPU ETU I &T COMPL 1/14 11/19 10/06 4/07 6/20 10/ INSTRU. CDR 4/19-20 MISSION CDR 6/ /22 CR A S O N S J ON DJ 6 9/21 1 ETU INSTRU. I &T COMPL 12/10 START FLT INSTRU I&T w/ IDPU, ESA, SST ETU 7 MISSION MGR. : FRANK SNOW PROJECT MGR. : PETER HARVEY F M /22 11/10 PCB/FGE ETU I &T COMPL 3/18 12/ FLT TO IDPU FGE FLT 1-2 DEL to GER. 11/01 SC/EM I &T COMPL 3/21 1/05 PA /11 6/14 8/ FLT I&T COMPL FAB FLT HINGES 12/07 ETU I &T COMPL 12/06 11/15 5/05 8/19 ETU COMPL 8/14 9/10 2/044/18 5/06 7/ FLT I&T COMPL 11/11 FLT FAB/ASSY 2/07 4/13 5/ FLT 1-6 BD FAB/ASSY COMPL BOARD I&T COMPL. ESA ETU I &T COMPL 3/30 1/07 12/22 FLT I&T COMPL 2/ SST ETU I &T COMPL 9/17 3/29 7/07 7/ FLT 1 BD FAB/ASSY COMPL 12/06 A M 8/30 12/10 FGE FLT 3-5 DEL to GER. 2/ J 5/ /30 7/1310/26 11/ FLT IDPU FLT ESA 2/09 SC /25 5/06 6 FLT I&T COMPL 10/24 6 8/14 7/29 4 FLT I&T COMPL 5 8/ /13 5 7/21 FLT I&T COMPL 10/17 11/ FLT I&T COMPL
CY 2005 MILESTONES CY 2004 THEMIS Bus, Instrument & Mission I&T Schedule STATUS AS OF: 11/01/05 MISSION MGR. : FRANK SNOW MAJOR REVIEWS CY P1 INTEGRATION & TEST BUS/INSTRU MECH & ELEC I&T & C/O (UCB) BUS MECH & AVIONICS BUILD UP (Swales) NDJFMA PROBE SUBSYSTEM HARDWARE 2 P2 INTEGRATION & TEST 3 P3 INTEGRATION & TEST 4 P4 INTEGRATION & TEST 5 P5 INTEGRATION & TEST 11/21 MECH BUILDUP 7 SETUP / PROBE VIB / PCA INTEGR. (JPL) 8 PCA VIB / ACOUSTICS / THERMAL (JPL) 9 11 LAUNCH PROCESSING/LAUNCH INSTRUMENT CDR 4/19-20 MISSION CDR 6/14-18 CRR 2/04 4/06-08 HQ FGM/SCM CDR 4/22 INSTRU P1 PSR COMPL INSTRU COMPL 9/21 11/10 11/22 PROJECT MGR. : PETER HARVEY 5/02 INSTRU COMPL 11/22 ENVIRONMENTAL TEST & CLOSEOUTS (JPL) 5/04 P2-P5 PER 7/10/11 PSR 10 MECH H/W -- Critical Path H/W -- Project Reserve -- Instrument Slack LEGEND -- Intermediate Slack 12 DAYS 10/19 10 DAYS 8/11 5/31 8/10 FLT 1 BAU 1/12 6 P2- P5 SHIP TO JPL PROBE SUBSYSTEM HARDWARE MJ JANDJFMA MJ J A SOSO 6/09 MECH BUILDUP INSTRU COMPL 11/10 MECH BUILDUP 12/01 MECH H/W MECH BUILDUP 2/03 4/11 MECH BUILDUP 1/10 SHIP to JPL PROBE SUBSYSTEM HARDWARE 5/009 MISSION RESERVE MAG & MASS PROP (JPL) / SHIP 6/05 PCA INTEGR PROBE VIB 6/14 6/30 PROBE THERMAL PCA VIB/ACOUSTICS 7/07 MAG / SPIN BAL./ P1-5 PACK 7/12 FLT 5 BAU 12/23 FLT 2 BAU FLT 4 BAU MECH H/W 2/20 AVIONICS B/U Swap out 7/18 9/23 10/20 11/07 IRU BAU EDU#1 FLT 3 BAU SHIP to UCB AVIONICS B/U P1 Test Review BUS/INSTRU MECH & ELEC I&T & C/O (UCB) BUS MECH & AVIONICS BUILD UP (Swales) BUS/INSTRU MECH & ELEC I&T & C/O (UCB) BUS MECH & AVIONICS BUILD UP (Swales) BUS/INSTRU MECH & ELEC I&T & C/O (UCB) BUS MECH & AVIONICS BUILD UP (Swales) BUS/INSTRU MECH & ELEC I&T & C/O (UCB) BUS MECH & AVIONICS BUILD UP (Swales) BAU EDU#2 AEB IRU P1 Test Review 3/21 4/03-14 PROBE I&T 4/06 SHIP to UCB AVIONICS B/U Swap out AEB SHIP to UCB 2/21 AEB & IRU MISSION CONTINGENCYIIRT CONTINGENCY AVIONICS B/U PROBE I&T & C/O SHIP to UCB ASTROTECH C/O 3/20 2/21 3/17 ENVIRONMENTALS P1 PER 11/11 SHIP to JPL 4/14 4/02 1/ /06 1/06 4/03 PROBE I&T & C/O 11/16 SHIP to UCB BAU EDU#2 1/10 1/30 3/21 BAU EDU#1 Swap out 3/16 1/31 4/0 4 Probe1 PSR 1/03 C/O 11/20 1/30 4/03 AVIONICS B/U 4/25 5/0 3 Swap out 10
Apr Sept 2005 THEMIS CRITICAL MILESTONE CHART Critical Milestone Explanation of Missed Milestones May DecJan Feb JunJul AugSeptOctNov Bus Avionics Unit EDU #1 to Probe 2 All Flight 1 Instrument’s Complete Instrument Milestones Spacecraft Milestones Flight 1 Instrument Integration & Test Compl. P1 Reaction Control System (RCS) Compl. 4/08 P1 BAU Delivery to I&T Flight 2 Instrument Integration & Test Compl. Flight 3 Instrument Integration & Test Compl. Flight 4 Instrument Integration & Test Compl. Flight 5 Instrument Integration & Test Compl. 5/02 Bus Avionics Unit EDU #2 to FSW 4/25 P1 Transponder Compl. 6/ ) Completing action items from Instrument Suite 1 Pre-Ship Review. (Instru. Suites 2-5 have 2 to 5 months reserve) 11) Power Electronics Unit (PEU) had to changed out resistors during Thermal Characterization. 10) Power Module was used for test set verification & BAU was shared with flatsat Mar P1 Probe Ship to UCB ) Antenna, transponder harness rework. 9/ / / / / /20 11
THEMIS Missed Milestones 11/01/05 Missed Milestones Milestone DateExpected DateNeed Date P4 Instrument Suite Integr. P5 Instrument Suite Integr. P5 Instrument Suite PER 3) 5) 6) 7) P1 Mount S/A & Closeouts P2 Solar Arrays to I&T 8) 9) 10) P2 IRU to I&T 11) 12) 10/05/05 10/07/05 08/05/05 09/30/05 09/07/05 10/01/05 11/08/05 11/10/05 02/15/06 03/01/06 03/03/06 01/11/06 01/30/06 03/16/06 12/01/05 13) 01/03/06 01/30/06 12/19/05 11/24/05 P4 Instrument Suite PER 4) 10/07/0511/10/05 02/17/06 14) P2 Instrument Suite PSR 1) 09/29/0511/10/0501/05/06 P3 Instrument Suite PSR 2) 10/10/0511/10/05 02/20/06 15) P1 CPT, Closeout, Pack & Ship P1 BAU Swap Out P1 Flight BAU 09/21/05 09/28/05 01/12/06 01/13/06 01/12/06 01/13/06 Slack (in work days) P3 Transponder to I&T 08/16/0511/14/05 01/10/06 P3 Antenna to I&T 10/07/0511/25/05 01/10/06 P2 Avionics Build up 10/07/0512/13/0512/20/05 71 days 81 days 6 days 0 days 63 days 5 days 71 days 40 days 72 days 0 days 41 days 32 days 5 days
THEMIS Missed Milestones 11/01/05 Missed Milestones Milestone DateExpected DateNeed Date P3 IRU to I&T P3 AEB to I&T P3 Mechanical Build up 18) 20) 21) 22) P4 Mechanical Build up P5 Separation System P5 Transponder to I&T 23) 24) 25) 26) 27) 10/01/05 09/02/05 10/07/05 10/14/05 11/24/05 11/15/05 11/23/05 01/10/06 02/03/06 12/23/05 02/21/06 28) 12/16/05 11/04/05 11/28/05 19) 16) 17) P4 Antenna to I&T P4 IRU to I&T P4 AEB to I&T 10/14/05 12/06/05 11/30/06 11/28/05 02/03/06 P4 Transponder to I&T 10/01/0511/16/05 02/03/06 P1 Bus/Instru Test (Funct, CPT) 10/13/0512/16/05 01/06/06 P1 Bus/Instrument Integr. 10/04/0512/02/05 12/23/05 P1 Closeout Activities 10/17/0501/04/06 01/25/06 34 days 43 days 47 days 49 days 61 days 15 days 57 days 33 days 40 days 35 days 15 days Slack (in work days)
Status ?Instrument Status Charts
Probe Status ?Probe Status Charts
Probe Status ?Probe Status Charts
Schedule Recovery Plan Code 560 Schedule Recovery Review (J. Shue, C. Kellenbenz, R. Schnurr) Review schedule for completeness Provide recommendation to maintain or accelerate schedule Provide additional resources including civil servants or contractors UCB Provide FOT for testing support Provide engineers and technicians as needed Code 568 MI&T review Review UCB Mission Integration Plan Identify ways to accelerate schedule Provide resources Payload Processing at Astrotech MIWG/GOWG (11/2-11/4) identified ways to increase schedule reserves 5-10 days Astrotech/UCB/Boeing will develop a detailed integrated schedule by January 17