OVERVIEW Review of completed projects Update on large construction projects Update on other miscellaneous projects
COMPLETED PROJECTS Athletic Complexes $12M Mat-Su Day School $12.4M Valley Pathways $22.5M Big Lake ES Reno Ph I $2.2M Houston/Palmer Jr MS Lockers $335K Flooring Replacements Ph I $2M Palmer HS Mechanical Upgrades $5.5M Trapper Creek ES Roof $1M Swanson ES Ext Upgrades $200K Willow ES Roof $1.3M Joe Redington Sr MS/HS $65M CTHS Addition $16M Houston HS Exterior Siding $600K ADA Upgrades District Wide $1.5M Washroom Upgrade District Wide $800K Palmer HS, Palmer Jr MS, Cottonwood Creek ES, Pioneer Peak ES Roofs $3.8M
DENA’INA ES $26.5M Design: Bettisworth North Construction: FE Const. 44,224 SF K through 5 school Work started April 2015 Approx. 65% complete On schedule to occupy 2016
DENA’INA ES Exterior Interior Common Area
IDITAROD ES $25.2M Design: MCG Construction: Collins 50,605 SF replacement school. Pre-K thru 5 Work started May 2015 Approx. 70% complete On schedule to occupy 2016
IDITAROD ES Common Area Classroom
FRONTERAS CHARTER SCHOOL $6.9M Contractor: Howdie Const. Funded by USDA loan and $500K from MSB Construction 45% complete Access road from Seward Meridian is in place Construction schedule is to occupy 2016
FRONTERAS CHARTER SCHOOL Framing Near Completion
ATHLETIC FIELD IMPROVEMENTS $6.4M Play court upgrades at Finger Lake, Snowshoe, Larson, Glacier View and Houston High completed in 2014 All summer 2015 work completed with the exception of the Iditarod softball/baseball turf in-fields which are on weather hold until spring 2016
ADDITIONAL PROJECTS Back-Up Generators, District Wide $2.6M - Design: AMC Engineering, 1oo% design - Project bidding closed Jan 2016, with Wolverine Supply the low bidder - Sufficient funds to award base bid; Wasilla MS, Wasilla HS, Palmer HS -- Sufficient funds to award alternates; Big Lake ES, Butte ES, Snowshoe ES, Willow ES and the Operations & Maintenance Building - Contract award is on the March 1 agenda for assembly approval Big Lake ES Renovation Ph II $800K, and ADA Parking Upgrades $200K - Flooring, washroom partitions, and parking lot are complete - Corridor contract approved by the assembly Jan 12 with work to start spring/summer 2016 District Wide HVAC Upgrades $7.1M - Design: PDC Engineers, Contractor: Wirtanen Construction - Scope includes upgrading building controls from pneumatic to direct digital controls and is approximately 60% complete - Work will continue into the 2017 school year
ADDITIONAL PROJECTS cont. District Wide Energy Upgrades $3.1M (Gym Lighting and Windows) - New LED Gym lighting: Wasilla HS, Burchell, Houston MS, Cottonwood Creek, Pioneer Peak, Larsen, Shaw, Snowshoe, Big Lake, Willow, Swanson, Sherrod, Goose Bay, and Palmer JMS are complete - Partial window replacements at 18 schools will be advertised Feb/Mar for summer 2016 construction Flooring Replacements $200K (funded by flooring bond balance) - Scope includes new poured rubber gym flooring at three schools - Sherrod and Swanson were installed over Christmas break - Pioneer Peak Elementary will be installed over spring break Roof Bond Balance $800K - Sutton ES reroof and Tanaina ES roof modifications closed Jan EP Roofing was low bid and are on the Feb 16 assembly agenda
QUESTIONS