LHC Inner Triplet Status J. Kerby For…Ranko Ostojic, Cedric Garion, Tom Page, Thierry Renaglia, Herve Prin, Bob Wands, Frederic Gicquel, Ingrid Fang, Juan.

Slides:



Advertisements
Similar presentations
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Advertisements

Hydraulic Cylinders and Cushioning Devices
Improved anchoring of SSS with vacuum barrier to avoid displacement Ofelia Capatina (speaker), Katy Foraz (coordinates all the activities), Antonio Foreste,
MICE- AFC Unit Mechanical Design of the Cold Mass Support System Oxford University Rohan Senanayake.
N. Dhanaraj, Y. Orlov, R. Wands Thermal-Stress Analysis of CC1 Space Frame.
Vacuum Vessel Production Readiness Review
D. Passarelli, M. Merio, L. Ristori, B. Wands March 29, 2012
AMS-02 Cryosystem Phase III Flight Safety Review January 12, 2010 Phil Mott.
Slide HALLD TAGGER MAGNET STRUCTURAL ANALYSIS Presented by William Crahen 6/10/09 Pole Plate analysis Vacuum chamber analysis Vacuum chamber tie rods and.
Tracker Solenoid Module Design Update Steve VirostekStephanie Yang Mike GreenWing Lau Lawrence Berkeley National LabOxford Physics MICE Collaboration Meeting.
Progress on the MICE 201 MHz Cavity Design Steve Virostek Lawrence Berkeley National Lab RF Working Group Fermilab August 22, 2007  automatic.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 14, 2009.
Identified Company (CompositeX) to manufacture Custom Composite Pressure Vessel ● Working pressure 1000psi ● Holds 8 kg Nitrous Oxide ● 700 cubic inch.
1 Presented at ColUSM by D. Ramos on behalf of the Cold Collimator Feasibility Study Working Group Longitudinal.
Cryomodule Concept for the ODU RF Dipole Crab Cavity Tom Nicol* - Fermilab December 10, 2013 * With lots of help from HyeKyoung, Tom J, Shrikant, Ofelia,
LARP QXF 150mm Structure Mike Anerella / John Cozzolino / Jesse Schmalzle November 15, nd Joint HiLumi LHC-LARP Annual Meeting.
ALIGNMENT OF Q2 LOW BETA QUADRUPOLES D. Missiaen, On behalf of the EN-MEF-SU/MTI team 1.
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
DFBX Thermo-Mechanical Review
ZTF Cryostat Finite Element Analysis Andrew Lambert ZTF Technical Meeting 1.
H. Felice - P. Ferracin – D. Cheng 09/19/2013 Update on structure CAD model.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
FNAL Meeting, July 2006 Basti, Bedeschi, Raffaelli, INFN-Pisa 1 ILC cryomodule mechanical work at INFN-Pisa  Ongoing work  Near term future  Manpower.
RFCC Module Design Update  automatic tuners  cavity suspension  cavity installation Steve Virostek Lawrence Berkeley National Lab MICE Collaboration.
1 LHC-DFBX DFBX Production Readiness Review Project Overview Joseph Rasson LBNL October 2002, LBNL Brookhaven - Fermilab - Berkeley US LHC ACCELERATOR.
1 MME3360b Assignment 04 10% of final mark 6 problems, each worth 16.7% of assignment mark Due April 9 th, 2012.
1 LHC-DFBX Shipping Specification Steve Virostek LBNL Presented at the DFBX RFP Review October 2002, LBNL Brookhaven - Fermilab - Berkeley US LHC.
Work toward Stainless Steel SRF Helium Vessels at Fermilab Tom Peterson (presenter), Information from Jeff Brandt, Serena Barbanotti, Harry Carter, Sergei.
JLAB CLAS12 Torus Structure The cold mass is composed of 6 coils, each inside a coil case, joined together at the inner radius by a hub and at the outer.
Cavity support scheme options Thomas Jones 25/06/15 to 06/07/15 1.
Key Design Issues and Recent Reviews Tom Peterson, Fermilab DFBX PRR, October 23, 2002 US LHC ACCELERATOR PROJECT brookhaven - fermilab - berkeley.
NCSX VACUUM VESSEL PL Goranson Status Report Sept 5, 2006 Support Rod Revision NCSX.
M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve.
Brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Inner Triplet Review Q1, Q2, and Q3 Mechanics T. Nicol April 24-25, 2007.
An alternative spectrograph mount Bruce C. Bigelow University of Michigan Department of Physics 5/14/04.
R. Ostojic CERN, AT Department. 2 LHC Insertions Experimental insertions in points 1, 2, 5, 8 contain low-beta triplets. In total, eight triplets are.
56 MHz SRF Cavity Cryostat support system and Shielding C. Pai
C.Hauviller/TS-IC 27 avril April 2007 Summary C. Hauviller Review of the inner triplet.
MPP Meeting Sandor Feher Inner Triplet Powering Should include the IR quads and the DFBX especially the power leads. DFBX commissioning doc was.
SCH Controls Readiness Review- Cryostat Nov 4-5, 2015 Kurt Cantrell.
56 MHz SRF Cavity and Helium vessel Design
C. Garion Presentation Outline  Overview of the inner triplet interconnections  Q1/Q2, Q2/Q3 interconnections  General view  Working conditions  Compensation.
Cavity support scheme options Thomas Jones 25/06/15 1.
The integration of 420 m detectors into the LHC
Mike Struik / LHC-CRI INSTRUMENTATION FEEDTHROUGH SYSTEM FOR LHC MACHINE ARC QUADRUPOLE MAGNETS. 123rd LHC Vacuum Design Meeting 19 April 1999.
MICE RFCC Module Update Steve Virostek Allan DeMello Lawrence Berkeley National Laboratory MICE CM27 at RAL, UK July 8, 2010.
CM2 Repair Status 8/13/2012 Tug Arkan 1. Latest Status After the warm end couplers were disassembled, it was decided to disassemble all the lower aluminum.
Adam Carreon July 19, 2012 Technical Division SRF Department Dressed SSR1 Cavities.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
Fixes J. Kerby For my many colleagues who have contributed to this effort (Ranko Ostojic, Cedric Garion, Tom Page, Thierry Renaglia, Herve Prin, Bob Wands,
3 rd ESAC Review, 27 th February to 1 st March 2013, CEA Saclay Fresca2 Dipole Structure Assembly J.C Perez on behalf of Fresca2 collaboration team.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
ILC : Type IV Cryomodule Design Meeting Main cryogenic issues, L. Tavian, AT-ACR C ryostat issues, V.Parma, AT-CRI CERN, January 2006.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
Teleconf ACS – FREIA 28th March 2017
SPL RF coupler: integration aspects
Status of the low-β triplets
Roadmap for triplet cryostats
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
Step IV - Engineering Jason Tarrant – Integration Engineering
Status of cryostat integration and conceptual design
Fredrik Fors Mechanical Engineering, JLab 09/29/2016
Cedric Garion, TE-VSC-DLM, WP12
LHC IRQ Tie Bar Redesign Using Sleeves – Preliminary
FRESCA2 Update on the dipole design and new calculations
The 11T cryo-assembly: summary of design and integration aspects
IR Beam Transport Status
SNS PPU Cryomodule Space Frame
Status of QQXF cryostat
Presentation transcript:

LHC Inner Triplet Status J. Kerby For…Ranko Ostojic, Cedric Garion, Tom Page, Thierry Renaglia, Herve Prin, Bob Wands, Frederic Gicquel, Ingrid Fang, Juan Carlos Perez, Tom Nicol, Sandor Feher, Tatsu Nakamoto, Peter Limon, Joseph Rasson, Steve Virostek, Paul Olderr, Tom Peterson, Jim Strait, Jim Rife, Vadim Kashikin…and anyone else I have inadvertently forgotten…

14 June  Review of 27 March sector 7-8 pressure test  Requirements for the fix  Cartridge for Q1 / Q3  Vacuum Loading  DFBX  Schedule

14 June 20073

4 Non IP end of Q1, looking toward IP The Xb, XBt, V EE and FF lines, and beam screen lines were not pressurized during the 27 Mar test

14 June  Tables for the full load case when all lines are pressurized to MAWP  27 March test the pumping and shield lines were not pressurized, and failure was at 20 bar Q1 load 115kN Q3 load 93kN

14 June Q1 115kN Q3 94kN

14 June Cold Mass Support  A ‘fixed’ and ‘free’ spider support  Invar rod connecting the two to share support

14 June Geometry was drawn directly from the CAD model. The bellows at the interconnections between cold masses were simulated with spring elements having a total stiffness of 5500 lbs/in at each interconnection. Moments due to the L line bellows were estimated, and are reacted w/ much longer lever arm of the spacing of the supports, so are a small effect in these analyses. Elements are second-order hexahedral and tetrahedral solids. A total of 500 thousand elements and nodes were used.

14 June Meshing of the supports was refined to include three elements through the half-inch thickness of the G11. The G11 was treated as orthotropic; in the plane of the support (the xy plane in the analysis) bending is resisted primarily by the tension or compression of the relatively stiff glass fibers; the Young's modulus is dominated by the glass, and was set to 3e6 psi in both the x and y directions. For the z-direction (through the thickness), loads are perpendicular to the glass fibers, and the stiffness is influenced more strongly by the epoxy matrix; a reduced modulus of 1e6 psi was used for this direction. Note that while this is technically "orthotropic", it really assumes isotropy in the xy plane.

14 June Q1- Q2 - full 20 bar load (all lines) sliding support lbs Q1 fixed support lbs IP bellows lbs lbs Q2 sliding support - 55 lbs fixed support lbs sliding support - 65 lbs IP bellows – 1920 lbs bellows lbs

14 June Q3 – full 20 bar load (all lines) fixed support lbs Q3 sliding support lbs IP bellows lbs lbs

14 June Pressure Test Summary  With Shield and Xb lines empty, actual loads 84% of 20 bar load in model…results linearly scaled for now: Q1 fixed support failed at 16,950lbs/75.4kN (7.5mm); then propagated to Q1 free support Q3 fixed support being checked at 14250lbs/63.3kN (6.4mm); Q3 free support shows no signs of damage Q2 unaffected  DFBX damage not from interaction with Q3

14 June Requirements for a Fix  In Situ  Does not move fixed point of the assemblies  React loads with sufficient stiffness to limit deflection – ~140kN design load (slide 4)  Acts at any temperature 300K to 2K  Focus on implementation in Q1—Q3 solution identical in length, IP end

14 June Fixed Points MQXAMQXBMQXAMQXB Q3Q2AQ1 DFBX Q2B MQXB LBX D1 External heat exchanger (HX) Fixed Point HX-Cold Mass FP Cold Mass- Vacuum Vessel Fixed Point Triplet- Tunnel Floor Tie Rods Linking Vacuum Vessels Jacks (longitudinal) Internal heat exchanger

14 June

14 June

14 June Q1

14 June Q1 MQXA Corrector Containment

14 June Q3

14 June Q3 MQXA Corrector Containment

14 June

14 June Allowable Deflection of Support  From failure analysis support fails at deflection of 7.5mm (6.4mm borderline)  System Analysis from Q1-Q2-Q3  Cooldown deflection ~1.0mm in Q2 free spiders (all tested, ok)  Analysis of test in fixture, test results, suggest 2.8mm

14 June Cooldown / 20 bar loads – Q1/Q2 Q2 sliding support lbs (2300 lbs) fixed support - 60 lbs (-86 lbs) sliding support lbs (2195 lbs) IP bellows – 7940 lbs (6000 lbs) bellows lbs (6115 lbs) sliding support lbs (-3190 lbs) Q1 fixed support lbs (-2840 lbs) IP bellows lbs (6000 lbs) lbs (0 lbs) 137kN (0kN) 35kN (27kN) 77kN (-13kN) 25kN (-14kN) 35kN (27kN) 10kN (10kN) 0kN (0kN) 35kN (27kN) 10kN (10kN)

14 June Cooldown / 20 bar loads – Q3 fixed support lbs (-2826 lbs) Q3 sliding support lbs (-3230 lbs) IP bellows lbs (6115 lbs) lbs (0 lbs)  Contraction of cold mass interconnect bellows Q1-Q2 and Q2-Q3 reacts portion of quench load  Further models move from full triplet to Q1 only w/ load of interconnect bellows included  W/ cooldown, free support pulled toward fixed support by Invar tie rod 35kN (27kN) 62kN (-13kN) 18kN (-14kN) 115kN (0kN)

14 June Allowable Deflection of Support  Testing / modeling to failure of individual supports The cold mass provides a rotational constraint on the support and lug which does not exist in the test fixture Test of single spider in fixture failed at 6900lbs, 17mm deflection Modeling used to translate results to spider / invar system, including gravity loads.  2.8mm bending of spider in installed configuration OK including safety factors  Removing front split ring on fixed support adds another 17.5mm of allowable motion

14 June Removing the front split ring is important as the cartridge is a much stronger spring than the support and would pull the cold mass 5.5mm if a large thermal mismatch existed Addition of 17.5mm of travel by removing this split ring, and using the cartridge to set the fix point of the assembly, greatly simplifies failure mode analysis.

14 June Cartouche / Cartridge  Affixed at Q1 non-IP end; Q3 IP end  Transfer load at all temperatures  Limits support deflections

14 June

14 June

14 June Q1 Cartridge Modeling  Cartridge applied to Q1 model including bellows for: Warm 25 bar pressure test load Cold Cold, 20 bar quench load Figure 1. Finite Element Model of Q1 with Cartridge

14 June Q1 Cartridge, 25 bar pressure test sliding support lbs Q1 fixed support lbs IP bellows lbs lbs cartridge lbs Figure 2. Forces on Components due to 25 Bar Warm Pressure Test Load 171kN 8kN18kN 144kN 2kN

14 June Q1 Cartridge, Cooldown sliding support lbs Q1 fixed support lbs IP bellows lbs 0 lbs cartridge lbs Figure 3. Forces on Components due to Cooldown 0kN 13kN 9kN 5kN 27kN

14 June Q1 Cartridge, cooldown + 20 bar sliding support lbs Q1 fixed support lbs IP bellows lbs lbs cartridge lbs Figure 4. Forces on Components due to Cooldown and 20 Bar Pressure Load 137kN 6kN5kN 109kN 28kN

14 June Q1 Cartridge, Deflections  Load per cartridge: 36kN (warm test, 25 bar evenly split)  Al tube stress (3300 psi / 8600 psi ASME allowable) (22.7MPa/59MPa allowable)  Invar peak cross section (16600 psi / psi) (114MPa / 148MPa) (Allowable – 3 to ultimate or 2 to yield of annealed Invar)

14 June Thermal Analysis

14 June Invar rod temperature

14 June Vacuum vessel flange temperature

14 June Cartridge Summary Cartridge design in production and testing  Worst case Q1 spider support longitudinal deflection < 2mm limit  Worst case Q1 spider load < ¼ load that caused failure during recent pressure test  Does not move magnet fix point In fact fixes Q1 / Q3 better than currently  Magnetic effect negligible  Additional load to 2K of a few Watts; Vacuum Oring OK.  Mechanical tests have been done on: Removal of split ring at fixed point Invar / Al tube connection Vacuum bracket to flange weld Full standalone cartridges  Test of 4 cartridges installed on a Q1 in process, actual test next week  Successful removal of split ring covers upset conditions Covers failure modes in thermalization of cartridge / cold mass  On track for sector 8-1….

14 June Q1

14 June Q1

14 June Vacuum Loads to Ground

14 June Vacuum vessel to ground  Apr Review noted issues to be resolved w/ alignment / jacks / tunnel ground under triplets  Safety factor of vacuum tie bars between vacuum vessels and DFBX also questioned

14 June V2V2 IPIP tot rod force = lbs bellows force = 500 lbs V3V3 IPIP lbs tot rod force = lbs tot rod force = 7100 lbs bellows force = 500 lbs bellows force = 100 lbs V1V1 IPIP tot rod force = lbs lbs bellows force = 500 lbs 25 bar load + Vacuum load (+bellows); no transverse load on jacks  Vacuum Vessel Deflections V1 4.3mm to IP V2 2.0mm to IP V3 0.4mm from IP  Vac Bellows makes ~5% change in deflections in 2 previous cases 100kN 171kN 100kN 1kN 2kN 100kN 2kN 100kN 135kN 32kN

14 June

14 June Vacuum Tie Bar Ass’y Outer nut omitted to prevent excessive load in the event of a cryogen spill inside the vacuum vessel

14 June Connection Details Nut to tighten sleeve against intermediate ear Nut to tighten assembly against vacuum vessel ear Spherical washers 2” OD, 1.25” ID sleeve Tie rod Tie rod, nuts, and spherical washers are the same as those in the current system

14 June Connections Details (2)

14 June DFBX

14 June DFBX-E 17 Feb 05

14 June Q3: 20 KN LD: 6.5 KN D1: 10.1 KN Bus Duct Assembly: Thrust Load Thrust Support Brackets

14 June MQX1 4 screws on each side Swivel support Fully adjustable support Feature allowing to loosen up the tolerances on the bore

14 June MBX1 Cut to loosen up the tolerances Handles to ease installation Cut to allow a full adjustment from the back with custom made tooling Fully adjustable leveling mount

14 June Summary  Production and Qualification tests of solutions in process Materials and parts arriving at CERN Initial hydraulic test in 181 next week on Q1 DFBX solution design complete On track for sector 8-1 and repairs in remaining sectors Great effort across labs

14 June

14 June