DEPARTMENT OF PUBLIC WORKS Presentation to Portfolio Committee on SAPS PROVISION OF INFRASTRUCTURE AT LEBOMBO LAND PORT OF ENTRY 17 June 2015 1.

Slides:



Advertisements
Similar presentations
On the Customs front, massive changes have taken place under the Customs Modernisation Programme which was launched two years ago. As with Revenue, Customs.
Advertisements

1 DEPARTMENT OF PUBLIC WORKS PROGRESS REPORT ROAD MAINTENANCE, JOB CREATION AND POTHOLES by ACTING DDG: PROJECTS (OBED MOLOTSI) 01 November 2011.
Public Border Operators Association Border Infrastructure Project Updates Canada – United States Transportation Border Working Group Meeting April 19 –
PRESENTATION TO THE SELECT COMMITTEE ON APPROPRIATION 19 OCTOBER 2010.
1 Presentation to Presentation to the Portfolio Committee of Home Affairs on the pending immigration strike Presenter: Ronald Oppelt 30 August 2006.
Transportation Border Working Group Montreal October 22 and 23, 2013 CBSA Project Update.
1 PRESENTATION TO THE PORTFOLIO COMMITTEE ON HOME AFFAIRS STATUS OF THE AMENDMENTS TO THE REFUGEE ACT AND RELOCATION OF REFUGEE RECEPTION OFFICES CLOSER.
What is a master plan? Creates the long-term vision for the University’s land and physical resources. Lays foundation for development plan, but is not.
DEPARTMENT OF PUBLIC WORKS Presentation to Joint meeting of Portfolio Committees on Home Affairs and Public Works on INFRASTRUCTURE EXPANSION FOR DHA 19.
INPUTS INTO THE DRAFT DISASTER MANAGEMENT AMENDMENT BILL Portfolio Committee on Cooperative Governance and Traditional Affairs 22 APRIL.
MTF Rail Development Forum
Lecture(3) Instructor : Dr. Abed Al-Majed Nassar
Texas Department of Transportation Corpus Christi District Harbor Bridge Project U.S. 181 (Harbor Bridge)/SH 286 (Crosstown Expressway) Agency Scoping.
1 1 OPERATIONAL RESPONSE SERVICES: BORDER POLICING INFRA STRUCTURE/ OFFICE AND RESIDENTIAL ACCOMODATION: PORTS OF ENTRY Briefing by SAPS to the Portfolio.
State Information Technology Agency Presentation to Portfolio Committee on Home Affairs.
Intersection Control Evaluation (ICE). Outline  Background  ICE Process  Impacts  Current Status.
MYTON SCHOOL Local Plan Update – Dec WDC Local Plan - Background The Warwick District Council (“WDC”) Local Plan sets out Council’s policies and.
Team Tech meeting May 22, 2006 State Traffic Commission & DEP Storm Water Permitting State Traffic Commission Permitting & Storm Water Permitting State.
Presented by Themba P Wakashe Director-General REPORT ON THE UNSPENT BUDGET 2009/10 TO STANDING COMMITTEE ON APPROPRIATIONS.
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
1 Community-Based Care Readiness Assessment and Peer Review Team Procedures Overview Guide Department of Children and Families And Florida Mental Health.
YOUNG PROFESSIONALS SEMINAR CIVIL ENGINEERING CHALLENGES Venue: CSIR International Convention Centre Gauteng Date: 22 November 2013 Presenter: Vikash.
IT Governance Purpose: Information technology is a catalyst for productivity, creativity and community that enhances learning opportunities in an environment.
1 Portfolio Committees on Correctional Services and Public Works Kimberley Correctional Centre 18 August 2010.
AUDITOR-GENERAL Presentation to the Public Service and Administration Portfolio Committee on the appointment and utilisation of consultants Report of the.
TMEA One Stop Border Posts (OSBP) Tanzania Country Programme Development Partners Dar es Salaam, 15 May 2013.
1 DPW Presentation to the Portfolio Committees on Correctional Services and Public Works Kimberley Correctional Centre 24 November 2010.
Limpopo - Health1 Report to the Select Committee on Finance on the Provincial Budgets and Expenditure Review 2001/ /08 and Conditional Grants and.
Report on the Challenges in the Planning and Procurement of Services for the Ceres and van Rhynsdorp Correctional Facilities Portfolio Committee on Correctional.
COMPLIANCE WITH THE SIGNING AND FILING OF PERFORMANCE AGREEMENTS BY HEADS OF DEPARTMENT BRIEFING TO THE PORTFOLIO COMMITTEE ON PUBLIC SERVICE AND ADMINISTRATION.
PRESENTATION TO THE PORTFOLIO COMMITTEE ON THE FORENSIC AUDIT THAT WAS CONDUCTED DURING May 2006.
CIVILIAN SECRETARIAT FOR POLICE STATUS REPORT ON IMPLEMENTATION OF THE CIVILIAN SECRETARIAT FOR POLICE SERVICE ACT 2 OF 2011 PORTFOLIO COMMITTEE ON POLICE.
{ Phases of Project & life cycle Prepared by: Syed ShahRukh Haider.
1 Re Kgabisa Tshwane Programme. 2 Background October 1997 Cabinet decision that Departments headquarters must locate in the inner city of Tshwane June.
NATIONAL RECTIFICATION PROGRAMME SELECT COMMITTEE ON APPROPRIATIONS 11 SEPTEMBER 2012 NATIONAL RECTIFICATION PROGRAMME SELECT COMMITTEE ON APPROPRIATIONS.
Presentation to Portfolio Committee on Police on SAPS Communication Projects By: Mr Sithembiso Freeman Nomvalo
Framework for the Closure Process in respect of Thubelisha Homes and Servcon Housing Solutions (PTY) Ltd Presentation to: Portfolio Committee on Housing.
Department of Correctional PRESENTATION ON THE DEVELOPMENT OF THE “NEW GENERATION” CORRECTIONAL FACILITY PROTOTYPES DEPARTMENT OF CORRECTIONAL SERVICES.
BUILDING OF NEW PRISONS NEW PRISONS PRESENTATION BY THE DEPARTMENT OF CORRECTIONAL SERVICES 2 September 2003.
Development through partnership Infrastructure Delivery Management Toolkit: 2010 Edition Delivery Process 2: Project Management 1.
1 DEPARTMENT OF PUBLIC WORKS P ROGRESS REPORT ON THE LEBOMBO PORT OF ENTRY 22 FEBRUARY 2011.
11 PUBLIC HEARINGS ON CONDITIONAL GRANTS AND CAPITAL EXPENDITURE 2008/2009 PARLIAMENT 27 AUGUST 2008.
DPW PRESENTATION TO PORTFOLIO COMMITTEE ON CORRECTIONAL SERVICES 09 FEBRUARY 2010.
INFRASTRUCTURE EXPANSION IN RELATION TO THE DEPARTMENT OF HOME AFFAIRS (DHA) Presentation to Portfolio Committees of Home Affairs and Public Works 19 September.
PAN AFRICAN PARLIAMENT CONSTRUCTION PROJECT Status report presented to International Relations Portfolio Committee 17 June 2015.
Office of the Director-General a DoT response to PCOT PCOT budget review and recommendations report (BRRR) 17 March 2015.
Department of Water Affairs and Forestry Department of Water Affairs and Forestry Department of Water Affairs and Forestry Department of Water Affairs.
1 Hospital Revitalization Grant Performance Report: Free State.
National Department of Public Works Republic of South Africa National Department of Public Works Republic of South Africa 25 MAY 2004 JAMES MASEKO DIRECTOR-GENERAL.
Train Station Project Update Report from Ad Hoc Committee December 11, 2007.
NATIONAL MACRO ORGANIZATION OF STATE PROJECT (NMOS) 2014 DEPARTMENT OF COMMUNICATIONS NATIONAL MACRO ORGANIZATION OF STATE PROJECT (NMOS) 2014 DEPARTMENT.
Transportation Border Working Group - Vancouver October 21 and 22, 2014 CBSA Infrastructure Project Update.
EFFECTIVE & SUSTAINABLE PROCUREMENT SYSTEM IN LAGOS STATE Partnering for Development Onafowote, Fatai Idowu Acting General Manager (PPA) Presentation made.
MENTAL HEALTH CLINIC Siting Process and Analysis.
ROAD ACCIDENT FUND COMPULSORY BRIEFING SESSION RAF/2015/00010 & RAF/2015/00011 Date: 18 June 2015 Time: 11:00.
OVERVIEW OF DEPARTMENT OF ARTS AND CULTURE SERVICES INFRASTRUCTURE PORTFOLIO DATE: 06 SEPTEMBER 2016.
Briefing on the oversight role of the DPW over IDT
Eagle P3 Project Update RTD Board of Directors Sept. 2, 2014.
BUDGET PRESENTATION TO THE SELECT COMMITTEE ON SOCIAL SERVICES
Building DHA as a Security Department
PRESENTATION TO THE PORTFOLIO COMMITTEE ON HOME AFFAIRS
DMV Accounting Officer/ SITA DCEO 24 May 2017
Report to portfolio committee
Presidential Permits Implementing EO 13337
PORTFOLIO COMMITTEE ON SOCIAL DEVELOPMENT 13 MARCH 2019
MPUMALANGA 4TH QUARTER EIG PERFOMANCE
Presented by Magdeline Tshabalala
Contract Award for the Colorado Street Bridge Suicide Mitigation Enhancements Project City Council May 20, 2019 Item # 7.
RIBA Plan Tom Robinson sir david Swindells Vii
HOME AFFAIRS IDENTIFICATION SYSTEM (hanis)
Presentation transcript:

DEPARTMENT OF PUBLIC WORKS Presentation to Portfolio Committee on SAPS PROVISION OF INFRASTRUCTURE AT LEBOMBO LAND PORT OF ENTRY 17 June

Table of Contents Lebombo Background Scope of work Future developments 2

CONTEXT OF DEVELOPMENT OF PORT OF ENTRIES The strategic management of Border Environment remains with BCOCC It is acknowledged that in 2007 SARS assumed the leadership of BCOCC The recently redeveloped commercial port of entries are; Lebombo, Skilpadhek, Vioolsdrift and Golela 3

BACKGROUND OF LEBOMBO 1.The project to redevelop Lebombo was initiated to develop a One Stop Port of Entry Facility to be shared by both South Africa & Mozambique. 2.The scheme or master plan received concurrence as the preferred model by BCOCC, led by SARS on the advise of the International Consultants under SARS. 3.The structure was designed to be positioned on the border line of the two countries based on multi-level floors to cater for passenger cars, pedestrians and buses. 4.The freight path was to cut across the high slope to lead to the Freight Clearing Facility on the Mozambican side 5.These main features formed the original scope of work for the One Stop Border Post. 6.DPW as the infrastructure Department developed the design further to the stage of contract documentation and costing. 4

LEBOMBO PORT OF ENTRY 1.The estimate costs of the structure above including the Freight Path, Freight Facility, Railway Station added to R 1,473,059,160 in The Department could not receive funding commitment from National Treasury to continue with the One Stop Border Post development. 3.As a result DPW opted to consult all stakeholders to address the need for a freight bypass road, and covert the temporary unit structures into a permanent pedestrian facility – this work was to form part of Phase 1 of the development. 5

BYPASS ROAD The Bypass Road development was completed and handed over in April The government of Mozambique equally completed their part of the bypass road. In discussions with BCOCC stakeholders four Inspection Canopies were built to enable inspection of trucks on a routine basis. These canopies were not fitted with any ablution facilities, and the requirements for ablution became evident when Police used the canopies as permanent stations for searching vehicles. The development of ablution facilities and supporting infrastructure remains in the scope of the next development phases. 6

FREIGHT PROCESSING AREA View of the Freight Processing Building Driveway to Freight Inspection Canopy The Freight Processing Building supports the bypass road. Occupation by User Department has been confirmed. The trucks volume has increased and this further warrants the extension of the parking area which will form part of the next phases of construction. 7

PEDESTRIAN FACILITY The building now known as the Pedestrian Facility was originally conceptualised a temporary structure for operations when the Construction of the One Stop Building Facility commenced. When it was confirmed that the amount required would not be secured, the facility was converted to process pedestrians on the basis of joint operations between SA/Mozambique. The layout and specification was well work-shopped with Stakeholders and completed as such. An official request by the Accounting Officer of DHA to reconfigure the internal layout was received by the Department in July 31st Entrance/ Exit to Mozambique Entrance/ Exit to South Africa Existing Queuing System

Pedestrian Path to Mozambique Elevation of Pedestrian Facility PEDESTRIAN FACILITY

FUTURE DEVELOPMENT – PHASE 2 SCOPE OF WORKS FOR LEBOMBO The following are the requests received from BCOCC to address inadequacies: a)Houses Converted to Offices b)Pedestrian Facilities – Rearrangement of existing balustrates, additional search tables for SAPS, counters, grid enhancement and windows for SAPS, refurbishment of holding facilities for SAPS. c)External works – 20 parking bays for SAPS, d)At Three Canopies – Ablution facilities for SAPS, e)Further Additional Works – Renovate 3 houses to accommodate SAPS, extension of road shoulder to provide search area for SAPS. 10

FUTURE DEVELOPMENT – PHASE 2 (cont.) FINANCIAL IMPLICATIONS The proposed scope of works is estimated at R 16,382, including fees, contingency and VAT. However the actual cost will be determined upon approval of the project by the user department (BCOCC). 11

DELAYING FACTORS & CORRECTIVE MEASURES Project was delayed and affected by the dispute between the department and professional team appointed to provide professional service and manage implementation of the project by the contractor. It must be noted that we motivated for re-appointment of the consortium of consulting firms which was involved in the design and implementation pedestrian facility and halted one stop border post as they are acquainted with site conditions, services installed in the facility and have corporate memory of the entire complex. Unfortunately the dispute referred herein relate to the previous projects managed by the consortium. We confirm that the project planning phase will be concluded and advertised by end of July

STATUS OF PROJECT The professional team is finalizing the designs and consultation with user departments to ensure that the project is advertised by end of July

PROJECT EXECUTION PLAN Item Project Stage StartFinish 1Design Stage (4A) Tender stage (4B) Tender Adjudication (5) Tender Award (5A) Site Handover Construction Stage (5B) Practical completion (6A) Final delivery (7)

LPOE on Planning for Redevelopment As reported in the previous committee meeting. The department in consultation with BCOCC has embarked on feasibility study to develop one stop border post master plans for Maseru Border Post, Beit Bridge Border Post and Kosi Bay. We can confirm that preliminary master plan reports for Maseru and Beit Bridge Border Posts are available. That gives us hope to conclude the proposed master plan within the current financial year (2015/16) as planned 15

Newly Constructed LPOE In every new construction or redevelopment of land port of entry provisions are made for office accommodations based on the needs of the six (06) User Departments actively operational at the Land Ports of Entry that including SAPS. Accommodation needs include office accommodation and holding cells in the operational area. Same applies to recently redeveloped border post such as Skilpadshek LPOE, Golela LPOE and Vioolsdrift LPOE. The department is guided by number of officials deployed at the land port of entry to determine the quantum of the space required each user department. 16

Shortage of Office Space and holding Cells User Departments present their approved needs to the Border Control Operation Coordinating Committee (BCOCC) Infrastructure Committee Chaired by SARS BCOCC/ Border Management Agency (BMA). If supported, User Departments then present to the Director-Generals Technical Oversight Committee. If supported, User Departments submit their approved needs to DPW. DPW then conducts a feasibility study/ site clearance through its Town Planning unit. The Site Clearance report will identify a suitable location within the port of entry and give an assessment report on the impact on bulk infrastructure with recommendations. 17

Scanners at border posts User Departments submits their approved needs to DPW after obtaining support from BMA/ BCOCC Infrastructure Committee and the Director Generals Technical Oversight Committee. DPW then conducts a feasibility study/ site clearance report. Once the report is finalized, it is presented to the User Departments for the User Departments to confirm the best option suited to their approved needs. DPW then constructs platforms, scanner power points and wire-ways for related services. The User Departments thereafter source, mount and connect the scanners to the newly constructed platforms and power point. In other words DPW will only provide scanner platforms and power points to the scanner. 18