Director’s Review July 15, 2004 1 Installation and Technical Commissioning of D0 RunIIb L0 Silicon and Trigger Upgrades Schedule & Costs R.P. Smith for.

Slides:



Advertisements
Similar presentations
Kondo GNANVO Florida Institute of Technology, Melbourne FL.
Advertisements

Bagby L0 Workshop L0 Infrastructure  Mapping  Installations u Horseshoe Area s Adapter Card u Cathedral s Low Voltage Fuse Panel u Platform s.
DoE Review June 6-7, 2000 Current Detector Configuration June 6, 2000  Solenoid, Central Preshower installed in central bore  A-layer MDTs installed.
DZero RunIIb Director’s Review February 3, Run IIb Project Status Vivian O’Dell.
September 16, 2002 ID Groups Physics Coordinator B. Klima Software and Computing A. Boehnlein, J. Qian Physics Groups Spokesmen G. Blazey J. Womersley.
MINER A NuMI MINER A DAQ Review 12 September 2005 D. Casper UC Irvine WBS7: Electronics and Data Acquisition  Overview (this talk): D. Casper  Front-end.
Brenna Flaugher Oct. 31 th CDF Meeting1 RunIIb Silicon Project Successful Lehman Review Sept Workshop at LBL 10/23-10/25: Wednesday-Thursday  hybrids.
WP2: Detector development Summary G. Pugliese INFN - Politecnico of Bari.
13 January All Experimenters’ MeetingAlan L. Stone - Louisiana Tech University1 Data Taking Statistics Week of 2003 January 6-12 We had to sacrifice.
W. Freeman, D0 PMG 25-Feb-03 1 Run IIb Schedule Status u Schedule Status u Update on near-term equipment expenditures u Budgeting Update u Summary.
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
D0 Run IIb Review 15-Jul-2004 Run IIb DAQ / Online status Stu Fuess Fermilab.
Jon S Kapustinsky 11/17/2010 Jon S Kapustinsky FVTX Commissioning Plan 1.71 Jon S Kapustinsky 1.
The MINER A Operations Report All Experimenters Meeting Howard Budd, University of Rochester July 8, 2013.
M. Gilchriese ATLAS Upgrade Introduction January 2008.
Aug 2005 Working Groups Physics J. Hobbs V.Buescher (deputy) Physics Groups Spokespersons G. Blazey T. Wyatt Trigger Silicon Layer O Online L3/DAQ Trigger.
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
Project Overview How to get here…. Half Way to the Test Run October 18, 2012HPS Project Overview2 …starting from here? John Jaros HPS Collaboration Meeting.
Silicon RunIIb Workshop, Dec , A. Bean, M. Demarteau Slide 1 Workshop  Workshop is to “Move beyond the Technical Design Proposal”  Many.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
M&O status and program for ATLAS LAr calorimeter R Stroynowski (on vacations)
September 19,2006 TeV Working Groups Physics J. Hobbs R. Van Kooten Physics Groups Spokespersons T. Wyatt D. Denisov Trigger Silicon Layer O Online L3/DAQ.
17 February All Experimenters’ MeetingAlan L. Stone - Louisiana Tech University1 Data Taking Statistics Week of 2003 February Dedicated some.
Director’s Review 5/5/03 Spalding DRAFT RLS 1 Project Planning  Documentation to DOE June 1  DOE Review ~July 22 Documents Summary Project Overview,
DZero RunIIb PMG June 7, Run IIb Project Status Vivian O’Dell.
Ronald Lipton Layer 0 Status PMG Sep Status of the Layer 0 Project – emphasis on hardware status, preproduction, and preparations for shutdown work.
DZero Run IIb PMG February 25, Run IIb DZero PMG  Status overview, issues (Kotcher)  Schedule, project status (Freeman)  AOB Jon Kotcher Fermilab.
L0 Technical Readiness Review-Electronics Installation Linda Bagby L0 Electronics Installation  System Electronics Overview u Low Voltage s Filter.
DZero Run IIb PMG January 28, Agenda Run IIb D-Zero PMG January 28, 2003  Overview, issues (Kotcher)  Project status (O’Dell)  Trigger technical.
Rev of Run IIb, Nov 4-8, 2002, A. Bean 1 Silicon Management  Organization and Management  Schedule  Resources  Conclusions Alice Bean Univ. of Kansas.
All Experimenters MeetingDmitri Denisov Week of July 7 to July 15 Summary  Delivered luminosity and operating efficiency u Delivered: 1.4pb -1 u Recorded:
FNAL PMG Feb 5, DØ RunIIb Trigger Upgrade WBS 1.2 Paul Padley, Rice University for the DØ Trigger Upgrade Group.
Director’s Review Feb 3-4, Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.
D0 PMG 6/15/00 PMG Agenda June 15, 2000  Overview (Tuts) u Detector status u Reportable milestones u Financial status u Summary  Response to DOE review.
Director’s Review of RunIIb Dzero Upgrade Installation Linda Bagby L0 Electronics Installation  System Electronics Overview u Low Voltage u High.
V. O’Dell, D0 RunIIb PMG 4-Feb Dzero Run IIb PMG  Agenda u Overview & Management News: V. O’Dell u Trigger Upgrade Status:P. Padley u Silicon closeout.
DoE Review June 6, 2000 Cost Estimate  New Cost Estimate u Manpower Costs (Op. SWF) u Equipment Costs (Eq. M&S) u Contingency  Conclusions Mike Tuts.
Tevatron BPM Upgrade Stephen Wolbers CD Accelerator Coordination Meeting August 3, 2004.
1 EIR Nov 4-8, 2002 DAQ and Online WBS 1.3 S. Fuess, Fermilab P. Slattery, U. of Rochester.
Muon Tracking Meeting SOR issue First priority Diagnostic: MCH DetectorScriptError Arriving at the initialization stage: the whole or part.
DZero Run IIb Rev Nov 05 ‘03 1 Kotcher Agenda (from Rebaselining Review)  Introduction (Kotcher – 10’)  Trigger & DAQ/Online (Wood – 30’) u AFE II/TriP.
Tevatron BPM Upgrade Stephen Wolbers CD Accelerator Coordination Meeting September 21, 2004.
Brenna Flaugher Sept. 24 th Lehman Review1 Run IIB Silicon Upgrade: Cost and Schedule Lehman Review Sept. 24, 2002 Brenna Flaugher Run IIB Silicon Project.
R. Boyd 1 February  Dr. M. Saleem  D. Jana  M. R. Meera Labbai  R. Boyd.
1 DØ RunIIb Trigger Upgrade: Status Darien Wood for the DØ Trigger Upgrade Group.
FPD STATUS Carlos Avila Uniandes/UTA 1. FPD overview 2. Roman pot and detector status 3. FPD readout integration status 4. Software status 5. Stand-alone.
March 15,2005 Working Groups Physics J. Hobbs V.Buescher (deputy) Physics Groups Spokespersons T. Wyatt D.Denisov Trigger Silicon Layer O Online L3/DAQ.
1 FY05 Shutdown at CDF Rob Roser for the CDF Operations Group January 18, 2004.
9/17/2008TWEPP 2008, R. Stringer - UC Riverside 1 CMS Tracker Services: present status and potential for upgrade Robert Stringer University of California,
February 3, 2005DZero Run IIb Director's Review1 Standing Committee on Upgrade Installation to Physics Commissioning  Charge: u Convened by spokespersons.
D0 PMG February 15, 2001 PMG Agenda February 15, 2001  Overview (Weerts) u Detector status u Reportable milestones u Summary  Operations Organization.
DZero Run IIb PMG December 10, Agenda Run IIb D-Zero PMG December 10, 2002  ESAAB news (Lab, Project, DOE)  Project status, overview (Kotcher)
DON LYNCH NOVEMBER 6, AGENDA November 4, BABAR Magnet Update Global Design Concept – Update Outer HCal Structural Analysis (2 nd pass) sPHENIX.
D0 PMG, 07Jun05 1 D. Wood, Trigger Upgrade Status Trigger Upgrade Status  The DØ Trigger Upgrade consists of u Complete replacement of Level 1 calorimeter.
Collaboration Mtg April 14, 2000 DO Timeline J F M A M J J A S O N D J F M D Install silicon front-end ICD FPS Lum (L0) CFT install/hookup 1/2.
SPHENIX MECHANICAL D. Lynch September 11, AGENDA Global Design Concept – Updated Global Assembly Concept – Updated Inner HCal Installation concept.
Linac2 and Linac3 D. Küchler for the linac team. Planning first preparative meeting for the start-up of Linac2 in June 2013 –this early kick-off useful.
SPHENIX MECHANICAL D. Lynch & R. Ruggiero July 31, /29/2014sPHENIX Mechanical Design.
SPHENIX MECHANICAL D. Lynch August 21, /15/2014sPHENIX Mechanical Design.
Fernanda G. Garcia, Steve Dixon, Andy Stefanik, Justin Tillman, John Voirin SBN Far Detector Installation & Integration.
What do we want to achieve in this running period? Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory MICO.
Arnd Meyer (RWTH Aachen) Sep 8, 2003Page 1 Integrated Luminosity Total data sample on tape with complete detector > 200pb -1.
The MINER A Operations Report All Experimenters Meeting Howard Budd, University of Rochester June 3, 2013.
WBS 1-7 System Assembly & Installation John Voirin August 10-11, 2011.
HF Test station at P5 A.Mestvirishvili.
EMU Slice Test Run Plan a working document.
Hall A Compton Electron detector overview
Pierluigi Paolucci & Giovanni Polese
Presentation transcript:

Director’s Review July 15, Installation and Technical Commissioning of D0 RunIIb L0 Silicon and Trigger Upgrades Schedule & Costs R.P. Smith for the D0 Collaboration

Director’s Review July 15, AFE/TriPChiP A. Bross Run IIb Project V. O’Dell, Project Manager, R. Lipton, Deputy M. Johnson,Technical Coordinator T.J. Sarlina, Asst Project Manager, D. Knapp, Budget Officer T. Erickson, Adminstration Trigger Installation D. Edmunds Silicon Installation Mechanical: W. Cooper Electrical: L. Bagby L1 Cal Upgrade M. Abolins H. Evans Readout A. Nomerotski R. Sidwell Sensors M. Demarteau R. McCarthy Mechanical Design & Fabrication W. Cooper Detector Modules & Integration L. Bagby Installation R. Smith DAQ/Online S. Fuess Trigger P. Padley D. Wood Silicon Layer 0 A. Bean (R. Lipton) L1 Track Trigger M. Narain D. Lincoln L1 Cal/Track Match K. Johns L2  upgrade R. Hirosky Silicon Track Trigger U. Heintz Simulation E. Barberis, M. Hildreth Administration (A. Bean) Administration (D. Wood) L3 Systems D. Chapin G. Watts Network & Host Systems J. Fitzmaurice S. Krzywdzinski Control Systems F. Bartlett G. Savage V. Sirotenko DAQ/Online Management (S. Fuess) Run IIb Upgrade Organization Installation /commissioning not formally part of the project, however formal installation management in place

Director’s Review July 15, Shutdown Activities Related to Installation  Upgrade Installation “Infrastructure” tasks planned for 2004 Shutdown (in CH or MCH) u L1 Cal – None u L1 CalTrack – begin mods of Muon PDT and Scintillator FEB’s, terminate L1CTT transition and MTCxx cables u L1CTT - install parallel “slice”: crate, controller, few DFEA’s, cables for CTOC, CTT u L2 Beta – None u STT – None u L0 Silicon – possible H-disk refurbish (incl. clearance survey), 4-Hybrid SVX4 string, study cooling silicon to lower temp, reroute 3 H-disk cables, mini fuse panel, adapter cards, new Wiener PS, Interlock chassis u Online – Move Online (DAQ, Oracle, NFS) to new host cluster

Director’s Review July 15, General 2005 Installation Overview  Hardware Ready Milestones (from Upgrade Project Schedules): u L2 Beta Production & Testing Complete 1/24/05 u L2 STT Production & Testing Complete 3/30/05 u L1 Cal Track Match Production & Testing Complete 5/16/05 u L1 Cal Trigger Production & Testing Complete 5/26/05 u L1 CTT Production & Testing Complete 7/5/05 u Layer Zero Silicon Ready to ship to DAB 7/21/05  D0 Prefers Tevatron shutdown to be paced by L0 completion date, or later; Beam off at least ~ 7 weeks  Configure Installation Schedule to Mesh with Hardware Project Schedules u Minimize Lost Beam Time “Physics stops to Physics resumes”

Director’s Review July 15, Beam-Off Time Paced by Silicon  Installation Schedule shows Tevatron Shutdown Time driven by Layer 0 Silicon Installation u Detector Not Removed From Collision Hall u L0 Silicon Schedule Predicts Silicon Ready 7/21/2005 u Installation Schedule Predicts Tevatron Shutdown 6/30/05 – 8/17/05 => ~ 7 weeks beam off u Silicon Installation dominates CH access time. Trigger Elements require lesser amounts of CH access “in shadow of” silicon. u Personnel Leave Collision Hall as soon as electronic commissioning of silicon is complete – finish Technical Commissioning after Tevatron resumes operation u Detector Closed up for Physics Commissioning ~3 weeks later (provides for short accesses to detector if required, until full functionality of new silicon is demonstrated)

Director’s Review July 15, Install Trigger during Beam-Off Period?  Installation Schedule shows most invasive trigger hardware Upgrade - L1 Cal – will be installed while beam is off for L0 Installation u Trigger Framework off < 1 week; DAQ available thereafter u Uncable BLS, remove old Cal Trigger Racks from MCH1 u Reconfigure BLS cables to new patch panels in MCH1 u Move fully operational L1 Cal Racks from Sidewalk test area to MCH1 u Reconnect BLS cables from patch panels u Expect to begin Technical Commissioning ~1 week before beam comes back  CTT requires 2 weeks of CH access (< 1/3 of what silicon requires); balance of Trigger installation, none.

Director’s Review July 15, Layer 0 Silicon Installation Principal Elements  Highlights from WBS Installation Schedule -- Silicon  “Infrastructure” tasks: refurbish dry gas system, prepare new L0 adapter cards for horseshoe, installation fixturing, etc. prior to shutdown  Run IIa Silcon warmed only to Collision Hall dewpoint  H-disks removed u L0 Silicon (mounted on new beryllium beampipe) uses old beampipe as installation fixture u Reinstall inner H-disks u Cable plant, readout system, power supplies re-used u Reclosing of Be Beampipe determines resumption of beam Includes time for full checkout of electrical integrity of all new and existing silicon channels  Installation Schedule Predicts Tevatron Shutdown should occur ~ 3 weeks before L0 Silicon is ready to transport

Director’s Review July 15, Silicon Installation Milestone Overview IDWBSTASK NAMESTART-DATEFINISH-DATEDURATION Silicon Infrastructure Prepared5/3/05 0 w Shutdown for Installation Begins6/30/05 0 w Detector Open and Ready for Access7/11/05 0 w RunIIa Be Beampipe and H-disks Removed7/18/05 0 w Silicon Ready to Move to DAB7/21/05 0 w L0 Silicon Installed in RunIIa Silicon7/29/05 0 w L0 Silicon Cable-up Complete8/10/05 0 w RunIIb Beam Pipe Closed8/17/05 0 w Silicon Ready for Resumption of Tevatron Operation8/17/05 0 w Silicon System Ready for Physics Commissioning9/7/05 0 w Installation Schedule predicts time advance needed (~ 3 weeks) to prepare detector for arrival of L0 Tevatron Downtime ~ 7 weeks

Director’s Review July 15, Milestones for Completion of Technical Commissioning IDWBSTASK NAMESTART- DATE FINISH- DATE DURATION Tevatron Operation Resumes8/17/05 0 w Silicon Installed and Technically Commissioned9/07/05 0 w L1 Cal Trigger Installed & Commissioned9/07/05 0 w L1 Cal Track Match Installed & Commisioned10/13/05 0 w L2 CTT Installed and Commissioned9/27/05 0 w L2 Beta Installed and Commissioned7/21/05 0 w L2 STT Technical Commissioning Complete11/10/05 0 w

Director’s Review July 15, Installation Effort Schedule Workweek = Standard 5 days per week, except a few two-shifts days (e.g. open detector)

Director’s Review July 15, Installation Effort Schedule Workweek = Standard 5 days per week

Director’s Review July 15, Installation Effort Schedule

Director’s Review July 15, Detector Occupancy Schedule Two Shift Gap Limit: 8, Cathedral Limit: ~12

Director’s Review July 15, Installation Costs  Burdened FY05 Installation Costs u G&A Labor 30.35% M&S 16.05% u esc. Labor 12.49% M&S 1.08% BaseContingencyTotal Effort1428K614K2043K M&S94K 188K Total1522K708K2231K If all installation done in FY06, total cost would be: M&S $193k, Labor $2124k, Total = $2317k, Delta = $86k

Director’s Review July 15, Physics Commissioning Not part of Installation: SC-IPC  In order to ensure time “From Physics to Physics” is minimum, it is important to develop mature view of schedule for Physics Commissioning  D0 Spokes have convened the Standing Committee on Upgrade Installation-to-Physics-Commissioning  SC-IPC is to generate a detailed plan which quantifies the time and effort required to return the detector to physics data taking u SC-IPC Co-Chairs: C. Gerber, R.P. Smith u 14 SC-IPC members organized into 5 working groups which analyze commission-to-physics needs of upgrade elements

Director’s Review July 15, SC-IPC Structure  SC-IPC divided into five Working Groups, each member of SC- IPC serves on at least two WG u WG1: L1 Cal trig (K. Johns + Barberis, Buescher, Hirosky) u WG2: L1 Cal trackmatch & CTT (S. Gruenendahl + Johns, Watts, Quinn) u WG3: L2 Beta, STT expansion (B. Hirosky + Jesik, Watts, Yasuda) u WG4: Trigsim (J. Hays + Shabalina, Buescher, Jesik, Kajfasz, vonToerne) u WG5: Layer 0 (B. Quinn + Barberis, Cooper, Kajfasz, Shabalina, Yasuda, von Toerne) u WG6: AFEII not yet convened (wait until tests of prototype) u Online covered by Committee as a whole  Preliminary findings from SC-IPC: many (e.g. TrigSim) software tasks must start now

Director’s Review July 15, Conclusions  WBS Installation & Technical Commissioning Schedule In Place u Tasks detailed to fourth sublevel u Resources (Effort, M&S) loaded u WBS Dictionary and BOE in place  Installation Management Team in place  SC-IPC up and running to create and monitor physics commissioning planning: timeline, effort cost, and task list  D0 prefersTevatron shutdown schedule to align with completion of silicon, or later