Apr 29, 2003SSWG - CDR Comments1 PFIS Critical Design Review Comments Detailed response available in document SALT- 3100BP0011 (PFIS web site) Responses.

Slides:



Advertisements
Similar presentations
Quantitative Techniques An Introduction
Advertisements

Seog Oh/ Duke University/June, 2003 TRT/ ATLAS week at CERN Duke Production Status.
6-7 July 20051B. C. Bigelow - UM Physics Finite element analysis of DECam May 11 C1 corrector lens – gravity and thermal load cases Bruce C. Bigelow, Physics.
Machine Elements in Mechanical Design. Introduction Mechanical Systems or Devices are designed to transmit power and accomplish specific patterns of motion.
1 Grating Mount Requirements Weight:< 75 Lbs including grating (43.1 Lbs) Size:Fit within structural envelope. 1.5” for cell behind grating. Alignment:Adjust.
Bridge Design Project Using SolidWorks and SolidWorks Simulation to design, test and build structures.
INDUSTRIAL & SYSTEMS ENGINEERING
GLAST LAT Project I&T Meeting – Jan 29,2004 E. Gawehn 1 GLAST Large Area Telescope: MGSE Status Report Eric Gawehn SU-SLAC I&T MGSE Engineer
1 Effect of missing/loose screws 03/01/04. 2 Moment Load about E-W Axis-1 S N 20 lbs +/-5% Result of 20 lbs load:.005 inch flexure at point of application.
Team Xerox Progress Report Mechanical Engineering Design Team Mechanical Engineering Design Team Jeff Carpenter Charlie Morris David Postel Jeremy Ryatt.
Oct 17, 2001SALT PFIS PDR - Structure1 Structure Interface/ constraints Loads Structure design rationale Truss Weight and CG Finite Element Analysis/ Image.
ISHELL Design Review Cryostat & Optics Bench Dan Kokubun 9/11/2013.
Oct 22, 2007SSWG #18 UKZN1 Robert Stobie Prime Focus Imaging Spectrograph Status Optics repair Schedule Status of other fix and improvement projects Budget.
1 IBL Integration Activities & Future plans  Overall FEA on Geneva (in convergence with Seattle)  News from IST Composite Design  Integration.
©Ian Sommerville 2000Software Engineering, 6th edition. Chapter 4 Slide 1 Concerned with activities involved in ensuring that software is delivered: on.
SALT Technology Development Lisa Crause India-South Africa Astronomy Workshop – SAAO 6 August 2012.
Magellan F/5 System Status A.Szentgyorgyi/SAO/30 Apr 2005.
So What? Operations Management EMBA Summer TARGET You are, aspire to be, or need to communicate with an executive that does not have direct responsibility.
Update on alignment kit and stave 250 frame M.Gibson (RAL) 1.
Oct 17, 2001SALT PFIS Preliminary Design Review Optical Integration and Test Plan 1 Southern African Large Telescope Prime Focus Imaging Spectrograph Optical.
PACS IIDR 01/02 Mar 2001 Instrument Interfaces1 PACS FPU Opto-mechanical Design Overview and Interfaces J. Schubert MPE.
MARS 2 Design Review-Optomechanical Review 07 Nov 2002 GLW1 MARS 2 Mechanical Design Review.
Reproduction interdite © ALMA EUROPEAN CONSORTIUM Reproduction forbidden Design, Manufacture, Transport and Integration in Chile of ALMA Antennas Page.
ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused.
Multiplexed High Res Spectroscopy at Keck – J. Cohen (PI), H. Epps (Optical Design), M. Rich (Project Scientist) Keck instruments for optical spectroscopy.
1 CERTIFIED SOLIDWORKS ASSOCIATE (CSWA) EXAM Nov 26, 20119:00-12:00 Dec 3, :00-12:00 SEB1015 NOTES We’ll take registrations in November but you’ll.
Design of a Lightweight Mounted Tip/Tilt Mirror
Oct 17, 2001SALT PFIS Preliminary Design Review1 PFIS/ IMPALAS Issues Outside Reviewer's Comments Post-PDR tasks Valuation Issues.
Spacecraft Interface/Handling Ring Robert Besuner 12 August 2004.
Oct 30, 2003PFIS - Student Wkshop1 The Prime Focus Imaging Spectrograph – Old Challenges and New Ones K. Nordsieck, Principal Investigator Jeff Percival,
January 25, 2005GRETINA 2004 Review1 GRETINA 2004 Annual Review Steve Virostek Lawrence Berkeley National Lab Mechanical System.
EXAMPLES OF GOOD VARIANCE ANALYSIS Cause –The $14k negative cost variance is due to reworking the upper housing design ($8.4k) and using a more expensive.
3.1.1 Optics, Optical Corrector, Mechanical Systems M. Johns, C. Claver.
Engineering Division 1 M321/M331 Mirror Switchyard Design Review Tom Miller
Structure Update Installation & Building Update Revisions Outlined Costs Revisited (since given to Gina) Jeff Nelson Fermilab.
Oct 17, 2001SALT PFIS Preliminary Design Review1 Southern African Large Telescope Prime Focus Imaging Spectrograph Mechanical Mechanism Design Michael.
Binospec - Next Generation Optical Spectrograph for the MMT
IRMOS Diffraction Grating Integral Tab Design  Performance of an optical system is highly sensitive to the surface distortion of the optics in the system.
Mount structure concept FM1 & FM2 Mount structure design 1) Aluminum structure. 2) Structure design for holding Newport mirror mount because of its compact.
Eastern USA University Academic Center Alexander AltemoseIStructural Option.
Apr 29, 2003SSWG1 Prime Focus Imaging Spectrograph Status Passed CDR- moving into fabrication phase Mechanism design complete: fabrication drawing packages.
Oct 10, 2002SSWG1 Prime Focus Imaging Spectrograph Status Engineering Status Optics Mechanical Control System Management Budget Schedule.
LAT Transport Container1 GLAST LAT Project8 September 2005 LAT Transport Container Design Review 8 September 2005 LAT Transport Container Design Review.
Lavs Issues Lav 12. Tube Planning future activities. Conclusions.
May 19, 2008SSWG #19 Göttingen1 Robert Stobie Prime Focus Imaging Spectrograph Status Optics repair positive progress: –UV efficiency –Some (repair-caused)
SRR and PDR Charter & Review Team Linda Pacini (GSFC) Review Chair.
Upgrade PO M. Tyndel, MIWG Review plans p1 Nov 1 st, CERN Module integration Review – Decision process  Information will be gathered for each concept.
Hunter Woron Spring 2012 Structural Professor Parfitt.
LARP Review, June 12-14, 2006 Prebys, Todesco, Zisman 1 Accelerator Systems Eric Prebys Ezio Todesco Mike Zisman.
Wire and Cathode Planes - Current Concept (work in progress) PPD Internal Review – 2 nd Part April 19 th, 2005 Rafael Silva FLARE Fermilab Liquid Argon.
Oct 17, 2001SALT PFIS Preliminary Design Review Management, Schedule, & Budget 1 Southern African Large Telescope Prime Focus Imaging Spectrograph Management,
Eric McDonald Drew Krutak Jeremy Hanneman. Our objective was to design and fabricate a High-Speed Treadmill that is capable of measuring the horizontal.
Edexcel BTEC Level 2 Diploma in Construction Members of the Construction Team Unit 1 Structure of the Construction Industry.
Andrei Nomerotski 1 Flex Status & AID A.Nomerotski, 18 June 2010.
13,14 July 2005 Feasibilty/Concept Study Mid Term Status Review CCAT Enclosure Nathan Loewen AMEC Dynamic Structures Ltd. 13 July 2005.
Prime Focus Imaging Spectrograph Status
Telescope Assembly, Integration and Verification (AIV) WBS 04C. 14 J
Prime Focus Imaging Spectrograph Status
Feasibilty/Concept Study Mid Term Status Review
Machine Elements in Mechanical Design
PFIS Camera & Collimator Conceptual Design
Budget Budget Contingency/ Cost Risks Descope Options
iSHELL Design Review Cryostat & Optics Bench
Bonneville Power Administration Aerial Line Cart Progress Report
Vibration Basics and Shaker Selection
Vibration Basics and Shaker Selection
Technical Updates Gábor László NSS Lead Instrument Engineer
Bunker Project Schedule/Budget
Construction Management Services April 16, 2018
Presentation transcript:

Apr 29, 2003SSWG - CDR Comments1 PFIS Critical Design Review Comments Detailed response available in document SALT- 3100BP0011 (PFIS web site) Responses tracked in 19 actions and 9 decisions David’s: major findings Time- critical decisions Other actions

Apr 29, 2003SSWG - CDR Comments2 Major Concerns Mechanism schedule is too tight and requires additional in- house Mechanical Engineers –We use a subcontractor to unload design and drawing tasks. Continues to be most efficient because firm already has a full I- DEAS model and is familiar with project –Additional personnel are available to monitor manufacturing steps No provision for spare optical blanks –A spare NaCl blank has been delivered –Two spare CaF 2 blanks (one for low-birefringence collimator elements, one for larger standard-grade camera elements) have been ordered: cost $32,800. –University has a mechanism for selling blanks if they are not required

Apr 29, 2003SSWG - CDR Comments3 Major Concerns- II Project should construct a test fixture with a rotator to verify flexure performance before delivery –existing plan: dolly/ holding fixture (“wedge”) that holds instrument at 37 deg, at one of 12 azimuths, to allow testing of mechanisms under gravity load. Est $7K, 1 wk ME. –add rotator to fixture for full verification of flexure model. Est $30K, 4 wk ME. –alternate: horizontal bearing which allows instrument to be tilted to 0 and +/- 37 deg. Est $12K, 2 wk ME. Prefer this one.

Apr 29, 2003SSWG - CDR Comments4 Major Concerns- III Concern that the flexure would not behave in a repeatable way due to stiction in the Z-pads –The current design couples the invar instrument structure to the steel rotator ring with an X-Y pin and a Y-slot, while support in Z is in 12 pads which are free in X-Y. –If there is stiction at these pads, the instrument will flex unpredictably as the temperature changes. –Analysis in progress: We have found a surface treatment that minimizes friction. Initial estimate shows < 5 micron stiction events. Pinned Foot Z-Pad (10 of)

Apr 29, 2003SSWG - CDR Comments5 Major Concerns- IV Transient thermal effects on optical performance should be modeled –will attempt evaluating an extreme case. Do not think it is important. The schedule is success-oriented. Schedule slip could be up to 1 year –the schedule is deliberately success-oriented. Schedule slips are allocated budget reserve as required. With the current budget reserve, up to 7 months of slip is covered. We consider 1 year unlikely.

Apr 29, 2003SSWG - CDR Comments6 Time-critical decisions The project should consider full mechanism spares –we estimate the cost of mechanism spares to be ~$30K/ major mechanism> Recommendation: No. –desired spares need to be identified as soon as possible to allow efficient ordering of parts –per the SOW, spares are not part of instrument cost- they are purchased separately by the SALT project The project should consider allowing a larger envelope for the NIR beam –We are studying pinning the curved I-beam on the NIR side, rather than welding it. Would allow up to ~120 mm additional envelope below NIR camera. –A larger redesign would invalidate the truss concept, and would require a schedule slip

Apr 29, 2003SSWG - CDR Comments7 NIR Beam Envelope

Apr 29, 2003SSWG - CDR Comments8 Time-critical decisions - II Panel advised compatibility testing of lens fluid and RTV –Recommend: no. We have experience in this combination; however, will investigate origin of this disagreement Panel advised looking at constructing a jig for testing off-axis images as test of alignment –We will look at whether there are any alignment issues that would not be apparent in off-axis images. Suspect not; test would be expensive ($10 - $45K).

Apr 29, 2003SSWG - CDR Comments9 Other Actions Analyze stray light, especially baffling necessary to capture grating zero-order. Do more formal FEA of lens mount gravity deflections. Investigate flexure of grating rotator stage. May be necessary to preload bearing. Investigate side load capacity of invar beams. All OK; radial top beams closest: will mark with warning and provide safe step.