Activities of 2008) Jinsook Kim, Yongwook Baek 1
Activities of TOF 2008) SM16: Completed – LV cables installation – HV cables tested – VME 4 crates test & mounted – FEA cards & record ID – Amphenol cables done (both) – FEAC cards & cables installation – Gluing done for both sides – Pulser test : done 2
Activities of TOF 2008) 3 SM17& SM18 : 100 % done – Cooling pipe – Aluminum frame done – gas leak test – Put mylar to protect interface cards – FEA cards & recode ID – LV cables installation – HV cables tested – VME 4 crates test & mounted – FEA cards & record ID – Amphenol cables done – FEAC cards & cables installation – Gluing done for both sides – Pulser test : done – Move to P2
Activities of 2008) 4 Check using test program : Control cable connections DRM connection Fix & test : Slow control cables TTC signal cables Installation : Grounding cables LV power cables Optic fiber links
Summary & Milestone Summary (1 post doc. & 1 students) The assembly of TOFs has been completed in time. All SMs have been Milestone – Commissioning – Cosmic run (magnet on) Period: 2 nd & 3 rd week of June 5