MG - IEFC Workshop 20121 MTE status and outlook for 2012 M. Giovannozzi Introduction Recap of 2011 activities Activities before LS1 Milestones Acknowledgements:

Slides:



Advertisements
Similar presentations
Accelerator Complex Status P. Collier. Linac2, Booster and PS Startup on-time, according to the schedule. Only minor problems Rapidly set-up the major.
Advertisements

ERDs for the CT extraction in the PS Proposal for a new correction scheme ERDs for the CT extraction in the PS Proposal for a new correction scheme Andrea.
Multi-Turn Extraction / L.Ducimetière / Kicker options for MTE Prepared by L.Ducimetière, L.Sermeus Outline: Reminder : Present MTE dedicated.
SESAME – TAC 2012: M. Attal Maher Attal SESAME Booster Characterization.
AGS pp Status Feb. 6, 2015 RSC Meeting Haixin Huang.
Massimo GiovannozziCOULOMB' September Resonant multi-turn extraction: principle and experiments M. Giovannozzi and S. Gilardoni, M. Martini,
Longitudinal motion: The basic synchrotron equations. What is Transition ? RF systems. Motion of low & high energy particles. Acceleration. What are Adiabatic.
Massimo GiovannozziPAC05, May 16th FINAL RESULTS FROM THE NOVEL MULTI-TURN EXTRACTION STUDIES AT CERN PROTON SYNCHROTRON M. Giovannozzi and R. Cappi,
Massimo GiovannozziFermilab - July 3rd Resonant multi-turn extraction project: principle and experiments at the CERN Proton Synchrotron M. Giovannozzi.
Introduction Status of SC simulations at CERN
Loss maps of RHIC Guillaume Robert-Demolaize, BNL CERN-GSI Meeting on Collective Effects, 2-3 October 2007 Beam losses, halo generation, and Collimation.
STRIPLINE KICKER STATUS. PRESENTATION OUTLINE 1.Design of a stripline kicker for beam injection in DAFNE storage rings. 2.HV tests and RF measurements.
MG - MTE Workshop 24/09/20101 Measurements’ analysis S. Gilardoni, M. Giovannozzi, M. Newman Introduction Techniques, tools Results (selected) Outlook.
Proton beams for the East Area The beams and their slow extraction By : Rende Steerenberg PS/OP.
AGS Polarized Proton Development toward Run-9 Oct. 3, 2008 Haixin Huang.
March 2, 2007ELC Experience with clearing voltages and solenoids at SPS damper pick-ups W. Hofle Acknowledgements PS-OP, SL-OP, SL-BI LHC-VAC, SL-HRF.
Tools for loss analysis and studies PS2/PS2+ Meeting 23 rd of May of 2007 Javier Barranco AB/ABP.
LHC beams in the SPS in 2014 H. Bartosik, G. Rumolo, G. Iadarola With the help from K. Kornelis, V. Kain and SPS OP crew.
H. Bartosik, K. Cornelis, A. Guerrero, B. Mikulek, G. Rumolo, Y. Papaphilippou, B. Salvant, E. Shaposhnikova June 16 th, 2011.
Fk. Bordry AB/PO Ability of the converter s to follow the reference function (static, dynamics) I1 I2 I3 Static part is covered by the static definition.
1 Status of EMMA Shinji Machida CCLRC/RAL/ASTeC 23 April, ffag/machida_ ppt & pdf.
October 4-5, Electron Lens Beam Physics Overview Yun Luo for RHIC e-lens team October 4-5, 2010 Electron Lens.
MG - IEFC meeting 22/01/20101 Linac 3 shielding S. Gilardoni, M. Giovannozzi, S. Baird, R. Brown, S. Damjanovic, T. Otto, M. Widorski, Acknowledgements:
C. Fischer – LHC Instrumentation Review – 19-20/11/2001 Gas Monitors for Transverse Distribution Studies in the LHC LHC Instrumentation Review Workshop.
Simulations and measurements of the injection oscillations and the MTE A. Huschauer Supervisor: S. Gilardoni Acknowledgements: H. Bartosik, H. Damerau,
Extraction from the Delivery Ring November 19, 2013 J. Morgan.
1 FFAG Role as Muon Accelerators Shinji Machida ASTeC/STFC/RAL 15 November, /machida/doc/othertalks/machida_ pdf/machida/doc/othertalks/machida_ pdf.
1 st September 2005LHC-LUMI 05 - G.Arduini – CERN/AB Optical requirements for the magnetic lattice of the high energy injectors (SSPS in the SPS tunnel)
Part III Commissioning. Proof of Principle FFAG (POP) study The world first proton FFAG –Commissioned in March –From 50 keV to 500 keV in 1ms. –Proof.
Design of the Turnaround Loops for the Drive Beam Decelerators R. Apsimon, J. Esberg CERN, Switzerland.
MTE vs CT D.Manglunki for BE/OP - pictures from M.Giovannozzi - details in “Fifty years of the CERN Proton Synchrotron (Vol I)” CERN
Chromaticity dependence of the vertical effective impedance in the PS Chromaticity dependence of the vertical effective impedance in the PS S. Persichelli.
PS losses during CT extraction, a history about 30 year long... J. Barranco, S. Gilardoni CERN - AB/ABP.
4 th Order Resonance at the PS R. WASEF, S. Gilardoni, S. Machida Acknowledgements: A. Huschauer, G. Sterbini SC meeting, 05/03/15.
Andreas Jansson, "Quadrupole Pick-ups", LHC BI-Review, November 19-20, Quadrupole Pick-ups  What is a quadrupole pick-up?  PS pick-ups and experimental.
Primary beam production: progress - Extraction from LSS2 - Switching from TT20 at 100 GeV B.Goddard F.Velotti, A.Parfenova, R.Steerenberg, K.Cornelis,
SPS proton beam for AWAKE E. Shaposhnikova 13 th AWAKE PEB Meeting With contributions from T. Argyropoulos, T. Bohl, H. Bartosik, S. Cettour.
The Introduction to CSNS Accelerators Oct. 5, 2010 Sheng Wang AP group, Accelerator Centre,IHEP, CAS.
MG - APC meeting 29/02/20081 MTE commissioning strategy and requirements M. Giovannozzi What is needed to implement MTE ScheduleCommissioning Acknowledgements:
Principals of fast injection and extraction R. Apsimon.
PSB H- injection concept J.Borburgh, C.Bracco, C.Carli, B.Goddard, M.Hourican, B.Mikulec, W.Weterings,
LHC beam dump, injection system and other kickers B.Goddard, with input from L.Ducimetière, W.Bartmann, V.Mertens, J.Borburgh, M.Barnes, C.Bracco, V.Senaj,
Optimization of beam envelop at the injection point of PS Chenghui Yu Jan. 30, 2012.
14/01/2005M. Giovannozzi - PS-SPS Days1 When can we have a clean Multiturn Extraction from the PS? M. Giovannozzi M. GiovannozziContentIntroduction Summary.
Beam loss and radiation in the SPS for higher intensities and injection energy G. Arduini 20 th November 2007 Acknowledgments: E. Shaposhnikova and all.
Beam absorbers for Machine Protection at LHC and SPS
Pushing the space charge limit in the CERN LHC injectors H. Bartosik for the CERN space charge team with contributions from S. Gilardoni, A. Huschauer,
High Intensity Beams in Existing Accelerators for CN2PY: SPS studies, PS issues E. Shaposhnikova Laguna-LBNO General Meeting CERN, Acknowledgments:
MTE commissioning status S. Gilardoni, BE/ABP With C. Hernalsteens and M. Giovannozzi.
Summary of ions measurements in 2015 and priorities for 2016 studies E. Shaposhnikova 3/02/2016 Based on input from H. Bartosik, T. Bohl, B. Goddard, V.
LEIR re-commissioning and other operational aspects First ideas for new tools and organization First draft re-commisisoning plan H. Bartosik, A. Huschauer,
PS2 WG Injection and extraction systems Basics and assumptions
Beam test of slow extraction from the ESR
Summaries and conclusions of the MTE Workshop
LINAC4 ADVISORY COMMITTEE
(Beam) Impact of MTE on the PS septa
A. Franchi, N. Carmignani - ESRF
LEIR IMPEDANCE AND INSTABILITY MEASUREMENTS
Multi-Turn Extraction studies and PTC
Emittance growth AT PS injection
Impact of remanent fields on SPS chromaticity
Proposal for a Transparent Off-Axis Injection Scheme for BESSY II
Elena Wildner CERN CA15139 Meeting, Sofia 15/
Update on the PSB Transfer Lines
Multiturn extraction for PS2
FCC-hh injection group 7
UPDATE ON DYNAMIC APERTURE SIMULATIONS
Multi-Turn Extraction for PS2 Preliminary considerations
Beam dynamics requirements after LS2
Triplet corrector layout and strength specifications
Presentation transcript:

MG - IEFC Workshop MTE status and outlook for 2012 M. Giovannozzi Introduction Recap of 2011 activities Activities before LS1 Milestones Acknowledgements: G. Arduini, H. Bartosik, J. Borburgh, R. Brown, M. Buzio, S. Damjanovic, S. Gilardoni, C. Hernalsteens, M. Hourican, A. Lachaize, Y. Papaphilippou, R. Steerenberg, and many colleagues in BI, OP, RF, DGS- RP, and TE-ABT, TE-MSC… 8/3/2012

MG - IEFC Workshop Introduction - I The three fronts that are being investigated Activation of septum 16 Generated by longitudinal bunch structure Impact on cool down time for intervention in septum area Fluctuation of trapping efficiency in the PS Long campaign of beam measurements to find source (not yet identified) Huge amount of beam data analysed. Injection trajectories fluctuations in SPS 8/3/2012

MG - IEFC Workshop Introduction - II Mitigation measures proposed Activation of septum 16 Dummy septum in SS15 Hybrid MTE extraction (re-using electrostatic septum for CT) Fluctuation of trapping efficiency in the PS Injection trajectories fluctuations in SPS Different strategy for beam measurements in Possibly same source for both issues (magnetic reproducibility of PS main field). Original proposal by Brennan 8/3/2012

MG - IEFC Workshop Dummy septum solution 8/3/2012 Current layout of SS15 Items under study Extraction trajectories (TOF should be optimised) and tested with beam. Relocation of elements currently in SS15 is completed. Additional elements installed during last TS: Additional DHZ in SS03 Additional gamma-jump quadrupole in SS99. Everything is ready for beam tests. Hardware design Optimisation and finalisation of the design. Activation and energy deposition studies (including particle tracking). Shielding optimisation. Impedance. Simulation of setting-up with beam.

Dummy septum: beam studies - I To make transverse space for the blade of the dummy septum in SS15 Move outwards the MTE beam (light blue) Move inwards the TOF beam (green) 8/3/20125MG - IEFC Workshop 2012 Isl. Slow bump Nominal TOF Modified fast bump Courtesy C. Hernalsteens

Dummy septum: beam studies - II Strategy to reduce amplitude at SS15 Reduce slow bump in SS15 Optimise strength of extraction kicker KFA71 It turned out that KFA4 (used for MTE – extraction of fifth turn) was useful in gaining transverse space in SS15 while reducing amplitude in SS09 (where losses were observed with protons). 8/3/20126MG - IEFC Workshop 2012 SS09 SS15 With KFA4 Without KFA4 Courtesy C. Hernalsteens

Dummy septum: beam studies - IV Main results: Space gained ≈ 7 mm Measurements to be repeated with protons to increase statistics and check losses 8/3/20127MG - IEFC Workshop 2012 Dummy septum Improved TOF Modified fast bump for MTE Courtesy C. Hernalsteens

8/3/2012MG - IEFC Workshop Courtesy M. Hourican Dummy septum: hardware design - I Downstream side Blade material: copper or tungsten. Comparable performance in terms of absorption. Choice: mechanical or impedance.

Dummy septum: hardware design - II 8/3/2012MG - IEFC Workshop Courtesy M. Hourican Shielding material: concrete and marble. Shielding dimensions: to be optimised.

Dummy septum: energy deposition - I 1D projection along the blade length, averaged over ±1σ x in x and over the blade thickness (3mm). Maximum value E max = (21.0±0.1) J/cm 3 /s 8/3/2012MG - IEFC Workshop E [GeV/cm 3 /s] MMU15 SS15 E [GeV/cm 3 /s] Courtesy S. Damjanovic

Rate for beam loss intensity of p/s 8/3/2012MG - IEFC Workshop E max rate [J/cm 3 /s] Dummy septum blade 21.0±0.1 Dummy septum tank (8.0±0.1)×10 -3 Vacuum chambers and beam screen(1.84±0.02)×10 -2 Dummy septum: energy deposition - II vacuum chambers and beam screen E max = (1.15±0.005)×10 -3 GeV/cm 3 /primary Courtesy S. Damjanovic

Extraction with SEH31: recap of CT Two slow bumps (SS16, SS31) One fast bump (pedestal and staircase, between SS21 and SS9) QKE (in SS5/25 and SS25/73) Two septa (SMH16, SEH31) Two kickers in TT2 to correct the turn-by-turn trajectory differences 8/3/201212MG - IEFC Workshop 2012

Hybrid MTE - I Phase of KFA13 is not suitable for a closed bump between 21 and 13. Kicker in 9 will always work at high strength, with KFA13 providing a small correction. QKEs are needed to “help” the kicker in 9 and provide extra kick to the beam deflected by SEH31. All this forces to go towards a nearly “carbon copy” of the CT optics. Guidelines for new solution: Minimise the strength of QKEs Close the combined SS16+SS31 slow bump Close the fast bump 8/3/201213MG - IEFC Workshop 2012

Hybrid MTE - II Tests performed: Slow bump: combine bumps in SS16 and SS31 8/3/201214MG - IEFC Workshop 2012 Original bump 31: not closed due to magnets in series New bump perfectly closed (also from measurements) Courtesy C. Hernalsteens

Hybrid MTE - III Tests performed: Tune control during rise of slow bump and QKEs 8/3/201215MG - IEFC Workshop 2012 Huge tune variation. Difficult to measure (too fast for standard tools). Partial correction using F8L. Potential issues: Tune change in vertical plane. Correct response of the circuit.

Hybrid MTE - III Tests performed: Kicked beam into island Fast tune change induces fast islands’ movement. The beam kicked inside does not follow and filaments 8/3/201216MG - IEFC Workshop 2012 No tune correction Best tune correction Accurate measurement (special analysis tool) and correction of fast tune change are the top priority for 2012 tests.

Fluctuations - I 8/3/2012MG - IEFC Workshop Different strategy to measure PS reproducibility. Instead of measuring trapping fluctuations, the position of the islands is measured: Orbit system can be used Accurate measurement, easier to interpret, and it provides similar information on reproducibility. Measurement of tune vs. Dp/p

Tune vs  p/p Small but systematic tune difference as a function of preceding magnetic cycle. Curve shape is also different. Courtesy A. Lachaize 8/3/2012MG - IEFC Workshop

Islands’ stability 8/3/201219MG - IEFC Workshop 2012 Island 1 Pickup 80 Average position (mm) Peak to peak (mm) After ZERO cycle (POPS) After EASTB cycle (rotating machine) After TOF cycle (rotating machine) After TOF cycle (POPS) Flat-top Programmed tune ramp Huge spread for the same preceding cycle Huge dependence of island’s position on preceding magnetic cycle Reduced variation of island’s position Reduced variation of island’s position Tests with special supercycles 1.13 BPs with 1 MTE (and ZEROs) 2.13 BPs with 2 consecutive MTE (and ZEROs ) 3.26 BPs with 2 MTE (and ZEROs). This case is equivalent to two supercycles of type BPs with 13 MTE Courtesy A. Lachaize

Statistics over five days - I Test reproducibility over long period Test with fixed preceding magnetic cycle Different ways to change the tune 8/3/201220MG - IEFC Workshop 2012 Injectors schedule In red measurement’s slots Huge tune variation requiring constant correction! Courtesy A. Lachaize

Statistics over five days - II October 25 th (before injectors’ MD) 8/3/201221MG - IEFC Workshop 2012 LHC as preceding cycle seems to improve stability.

Statistics over five days - III October 28 th (after injectors’ MD) 8/3/201222MG - IEFC Workshop 2012 LHC as preceding cycle does not seems to improve stability. Stability seems already better than before MD.

Highlights of Mini-Workshop on PS Main Magnet Field Issues - I Observations from the OP side – O. Hans Observations from the MTE side – A. Lachaize B-field regulation and PFW current regulation – F. Boattini PS main magnet model and simulations – M. Juchno Past and recent main magnet measurements and B-train – M. Buzio Discussion to draw up an action plan 8/3/201223MG - IEFC Workshop 2012

Highlights of Mini-Workshop on PS Main Magnet Field Issues - II Highlights from the mini-Workshop: Magnetic model is mature for predictive use. Magnetic measurements (dipole and quadrupole components) are provide interesting data! 8/3/2012MG - IEFC Workshop 2012 I(t) (zoom-in) I* 2 (t) (quadrupole) I* 1 (t) (dipole) quadrupole relative field error  5    100 ms Courtesy M. Buzio B = G 2010 measurement campaign by B. Vandorpe Qualitative agreement! No decay of dipole component Sizeable decay of quadrupolar component 24

Highlights of Mini-Workshop on PS Main Magnet Field Issues - III Wrap-up session last Tuesday to define actions. Points relevant for MTE activities: System for measuring dipole and quadrupole components will be available for measurements in two weeks. Higher-order (up to decapole) components could be measured in a month. Possible strategies for improving reproducibility (not necessarily operational…): Use n (1<n<6) 26 GeV/c before the MTE cycle. Pre-cycle the main magnets at low current (up-down between 0 A and 50 A) with several mini-cycles (should be fast). 8/3/2012MG - IEFC Workshop

Milestones - I Complete by mid-2012 studies for dummy septum: Paper studies: Assessing principle Finalise the hardware design Beam studies: Set up new slow bump (no DHZ15) and new extraction trajectory for TOF beam -> parallel MD Test new gamma-jump scheme (needs high-intensity beams operational) -> dedicated MD Perform by mid-2012 tests with new magnetic measurement system (together with beam measurements): Reproducibility of quadrupolar component for operational and special super-cycles. Effect of measures for magnetic reproducibility. 8/3/2012MG - IEFC Workshop Parallel MD

Milestones - II Depending on the success of the mitigation measures (to be completed by end-2012): Resume trapping to confirm improved reproducibility -> parallel MD Transfer to SPS to confirm improved reproducibility -> parallel MD Complete by end-2012 studies for hybrid MTE: Paper studies: Assessing principle Beam studies: Improve tools for tune correction during extraction. Tests of jumping the electrostatic septum (with CT settings) -> parallel MD Additional tests with special settings of CT elements -> dedicated MD 8/3/2012MG - IEFC Workshop