HIE-ISOLDE Project Status Report: Planning of Phase II 74th ISOLDE Collaboration Committee meeting November 10th 2015 Y. Kadi.

Slides:



Advertisements
Similar presentations
Costing Meeting Ajit Kurup 13 th June Page 2 Costing Meeting 13 th June 2011 Ajit Kurup Summary of CERN costing workshop. Proposed Level 3 breakdown.
Advertisements

RF Unit Test Facility at NML & CM1 Test Plan Bob Kephart Fermilab IWLC-10 October 20, 2010.
LHC Crab Cavities - Phase 1 - Schedule 2008 Mini Workshop - reminder Activities & Planning Planning Remarks 1 LHC-CC09, 3rd Crab Cavity Workshop - Session.
Special Linac WG meeting: Assembly of the ISOLDE Cryomodules – HIE-ISOLDE Survey and Alignment – March 19 th 2014 Jean-Christophe GaydeEN/MEF-SU Guillaume.
HIE-ISOLDE (High Intensity and Energy) project Protection of superconducting solenoids MPE work shop – December 14, 2010 G.J. Coelingh TE-MPE-CP.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
HIE-ISOLDE Design Study and the CATHI Project Richard Catherall EN-STI ISOLDE Technical Coordinator HIE-EBIS Workshop 16 th -17 th October CERN.
HIE-ISOLDE contribution packages M. Pasini BE/RF.
HIE-ISOLDE Project Status Report Y. Kadi for the HIE-ISOLDE Project Team 49th INTC Meeting CERN, 11 February 2015.
Status and Highlights of the Pulsed Magnet Program as of summer 2010, mid-point in current award period Delivered 350 th science pulse > 70T in 75T magnets.
Workshop on cryogenic and vacuum sectorisations of the SPL CERN, 9 th -10 th November 2009 Workshop Organisation and Goals Vittorio Parma TE-MSC.
CLIC QD0 R&D Status 1 Michele Modena, CERN TE-MSC IWLC10, WG5, 21October 2010.
WP3 Required interfaces for cryostat design / integration Patxi DUTHIL SPL 3 rd Collaboration Meeting, CERN, Geneva November 12 th 2009.
CRYOMODULES High Beta Low Beta Approved by CERN Research Board in December 2009.
Status of REX and Commissioning with Beam Dr. Jose Alberto Rodriguez, BE-OP-PSB (167538)
SM18 INFRASTRUCTURE Crab Cavity CryoModule – Conceptual Design Meeting
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
Harry Carter – LCFOA Meeting 5/1/06 1 LCFOA Technical Briefings: Cryomodules H. Carter Fermilab Technical Division.
Workshop Objectives & Highlights from Daresbury Meeting Erk Jensen, CERN.
HIE-ISOLDE Project Status Report
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
HIE-ISOLDE Project Status Report Y. Kadi for the HIE-ISOLDE Project Team HIE-ISOLDE Physics Coordination WG Meeting CERN, 16 February 2015.
Report from HIE-ISOLDE HEBT WG J.Bauche‎, P.Farantatos‎, M.Fraser‎, B.Goddard, Y.Kadi‎, D.Lanaia‎, D.Nisbet‎, E.Siesling‎, G.Vandoni‎, D.Voulot‎, E.Zografos.
PIP Update June 18 th Agenda Summary Update – Current Activities/Updates – Reid, Slabaugh.
Maria J. G. Borge Beam Lines for HIE-ISOLDE. Status of HIE-ISOLDE 2 May 2010: 34 LoI submitted 1 Nov 2012: INTC endorsed the increase of 2 GeV-proton.
Commissioning of REX Jose Alberto Rodriguez, BE-OP-PSB (167538) on behalf of the ISOLDE operations team.
Floor plans, Infrastructure & Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling.
Plans and schedule for the Long Shutdown LS1 SGUI CERN, 2 February 2012 Hie-Isolde Erwin Siesling.
HIE-ISOLDE Project: Planning & Resources Y. Kadi (EN-HDO) and the HIE-ISOLDE Project team.
HIE-ISOLDE Project Status Report 52nd ISOLDE & nTOF Technical Committee meeting February 3rd 2016 Y. Kadi On behalf of the HIE-ISOLDE Project Team.
Final Report – Injector Re- Commissioning Working Group (IRWG) Working group to find strategy for more efficient start-up of injectors and associated facilities.
High power RF tests places at CERN O. Brunner, CERN 4th SPL Collaboration Meeting jointly with ESS.
HIE-ISOLDE Project Status Report 50th ISOLDE & nTOF Technical Committee meeting July 1st 2015 Y. Kadi.
Krzysztof Radwan, PJAS, TE/VSC/ICM Interlocks, Controls and Monitoring Section HIE-ISOLDE Vacuum Controls INSTALLATION.
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
SM18 Vertical & Horizontal Test 110/12/2013Mathieu Therasse CERN BE/RF A. Benoit, O. Brunner, E. Jensen, A. Macpherson, P. Maesen, K. Schirm, W. Venturini.
HIE ISOLDE commissioning of the cryogenic control system installation at CERN. LNL-INFN 22/07/2015 Dr. Marco Pezzetti (CERN )
Booster Status, September 4, 2003 – E. Prebys 1 Frantic Shutdown Preparations Continue…
HIE-ISOLDE Project 3 rd beam line + HELIOS June 16th 2015 (updated on June 18th) Y. Kadi, S. Maridor.
HIE-ISOLDE Status Report Yacine Kadi on behalf of HIE-ISOLDE project team ISOLDE Annual Workshop, 5 December 2011.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Programme for the Physics Start-up Stable and radioactive beams Jose Alberto Rodriguez, BE-OP-PSB (167538)
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
Status and Future Perspective of the HIE-ISOLDE Project CERN, November 19-20, 2012
ESS Program Plan and Schedule Update
WP-46 XFEL 3rd harmonic system XFEL Project Progress Report (1-2010)
HIE-ISOLDE Report Jose Alberto Rodriguez on behalf of Yacine Kadi and the HIE-ISOLDE project team.
Update on HW commissioning
The ISOLDE Solenoidal Spectrometer project
Ralph Aßmann (DESY) 2nd collaboration week November 24th, 2017, Lisbon
HIE-ISOLDE Status Report
HIE-ISOLDE Project Status Report
HIE-ISOLDE Project: Planning & Resources
HIE-ISOLDE Status & Summary of HIE-ISOLDE SC
Injector Performance Requirements Conventional Facilities Update
HIE-LINAC status report
IHEP Cryomodule Status
Report on HIE-ISOLDE Status
CERN’s MidTermPlan and the consequences for HIE-ISOLDE
66th ISOLDE Collaboration Committee meeting
HIE-ISOLDE contribution packages
IR Upgrade Possibilities for PEP-II
Cooler e-source Magnetized Beam LDRD Progress Report
Overall time schedule of SRF activities
LCLS Injector System Overview D. H
Ideas for REX/HIE-ISOLDE Upgrade
Accelerator Installation Schedule
Cooler e-source Magnetized Beam LDRD Progress Report
Presentation transcript:

HIE-ISOLDE Project Status Report: Planning of Phase II 74th ISOLDE Collaboration Committee meeting November 10th 2015 Y. Kadi

F. Formenti WK16/2015 WK35/2015 HIE-ISOLDE physics 2015 On Oct. 22nd  Enormous progress since April 2015  Physics with RI as planned  Re-engineering of the RF coupler => Need to work out coherent planning for CM1, CM2 and CM3

Preparation for running w/ CM1 + CM2 (get new couplers, complete CM2, fix CM1) Move CM1 to SM18 Fix CM1 & re- install Resume CM2 & install Beam commissioning 16 wks physics w/ CM1 + CM2 Today Prepare 5 cavities & 10 new couplers Stop assembly CM2 Cryogenic services of CM2 + CM1 CM1 + CM2 h/w commissioning CM1 CM2 CM1+CM2 Fix all jumper boxes Prepare parts for CM3 + CM4 EDMS:

Forecast for HIE-ISOLDE Phase 2 (years ) Today CM3 + CM4 part procurement XT00 modification CM3 assembly C.R. free (scenario 3) Waiting for C.R. free (CM2 being assembled) CM3 test in M9 bunker CM4 assembly CM3 install General remarks:  Test in M9 bunker is now mandatory for CM3 and CM4 because the HIE-ISOLDE facility is running  XT00 modification for PHASE 2: push forward the quadruplet and move 1 doublet to XT03 EDMS:

HEBT installation status (XT00 in Linac tunnel, B170)

HEBT installation status (XT00 / XT01 / XT02, B170)

Forecast for HIE-ISOLDE Phase 2 (years ) CM4 assembly CM3 commissioning & beam commissioning Window for XT02 extension, XT03 installation & commissioning Run PHASE 2a with CM1+CM2+CM3 & XT01+XT02+XT03 CM4 test in M9 bunker, then put on hold (adj. window) Beam commissio ning Run PHASE 2b CM4 installation, commissioning General remarks:  NEW: PHASE 2 run is split into PHASE 2a (2017) and PHASE 2b (2018)  NEW: beam optics with 3 CMs: CM4 replaced by one doublet & replace first doublet XT03 with drift tube EDMS:

Overall Summary Radioactive beam delivered to Miniball experiment on Oct. 22 nd 2015 as initially planned. The results of the hardware tests highlighted that CM1 is not fully qualified for sustained operation (problem on RF couplers): De-install CM1 and re-work during winter shutdown; Re-engineer RF couplers; Improve thermalisations of the RF power line. New coherent planning is proposed for CM1, CM2 and CM3 Agree with Collaboration on a common scope for Physics run 2 & 3 ( ) Procurement for the 3 rd beam line and extension of XT02 for HELIOS has been launched: HELIOS solenoid magnet => TE/MSC & Isolde Coll.

Acknowledgments 9

Thank you for your attention