National Grid Local System Plan Needs Assessment/Potential Solutions PAC Meeting September 21, 2010.

Slides:



Advertisements
Similar presentations
2004 NERC, NPCC & New England Compliance Programs John Norden Manager, Operations Training, Documentation & Compliance August 31, 2003 RC Meeting.
Advertisements

National Grid Local System Plan 2009 LSP Presentation Related Questions and Answers.
NERC TPL Standard Issues TSS Meeting #146 Seattle, WA August 15-17, 2007 Chifong Thomas.
Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore.
Houston Region Import Capacity Project Planning for Reliable Power.
March 26, 2014 Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting.
PER
Project Definition of Bulk Electric System & Bulk Electric System Rules of Procedure Development Presenter: Peter Heidrich, FRCC – BES Drafting.
Public Service Company of New Mexico
New Cost Estimate Template Issued: December 11, 2014 Effective: January 5, 2015.
New Template of Environmental Compliance Approval with Limited Operational Flexibility Environmental Approvals Branch Presented to Air Practitioners’ Group.
Federal Energy Regulatory Commission Proposed Rule on Small Generator Interconnection RM July 23, 2003.
1 FRCC Compliance Organization and Entity Registration 2008 FRCC Compliance Workshop.
Transmission planning in Vermont Past, present and future Docket 7081 workshop By Dean LaForest 9/19/05.
GOP and QSE Relationship Jeff Whitmer Manager, Compliance Assessments Talk with Texas RE June 25, 2012.
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 1 Network Operating Committee (NOC) June 12 th, 2014.
Determine Facility Ratings, SOLs and Transfer Capabilities Paul Johnson Chair of the Determine Facility Ratings Standard Drafting Team An Overview of the.
1 1 1 Central Maine Power Company Local System Plan Presentation Planning Advisory Committee Meeting October 21, 2010.
Applying the Distribution System in Grid Restoration/NERC CIP-014 Risk Assessment Srijib Mukherjee, Ph.D., P.E. UC Synergetic.
Entity Registration Under EPAct 2005 Public Power Council April 6, 2006 Louise McCarren Chief Executive Officer WECC.
2006 Reliability Study Scope Name Date. DRAFT 2 Purpose of Study Assess the PEC and Duke transmission systems’ reliability Develop a single reliability.
1 1 1 Central Maine Power Local System Plan Presentation Planning Advisory Committee Meeting December 16, 2009.
Integration of Variable Generation Task Force Preliminary Conclusions and Actions.
Reliable Power Reliable Markets Reliable People Performance Targets for the Customer Interconnection Process January, 2008.
2015 RTP – Study Scope of Short Circuit Analysis RPG Meeting May 19,
RPG Meeting Five Year Plan Extension Brad Schwarz.
OSC Meeting April 27, Transmission Cost Allocation Overview.
LAREDO PLANT RMR EXIT STRATEGY Presentation to Board of Directors March 16, 2004 Transmission Services Operations.
SPS policy – Information Presentation Presentation to ROS June 16, 2004.
Discussion of Market Participant Choice for Transmission Connections Stakeholder Session October 14, 2011.
ISO Outlook Summer 2005 and Beyond Senate Energy, Utilities and Communications Committee February 22, 2005 Jim Detmers Vice President of Grid Operations.
Enhancing Reliability of the North American Transmission Grid Enhancing Reliability of the North American Transmission Grid Presented By Dejan J Sobajic.
Transmission Planning Informational Workshop Montpelier, VT September 19, 2005 Allocating the Cost of New Transmission in New England Stephen J. Rourke.
Transmission Equivalence Richard V. Kowalski Manager, Transmission Planning ISO New England.
Regulatory Planning for Supply to GTA & Toronto Areas Presentation to Regulatory Affairs Standing Committee May 14, 2003.
ATC Planning Zone Meeting Teresa Mogensen Director, Transmission Planning & Service Scott Barnhart Manager, Transmission Planning.
2006 SPP RTO Expansion Plan Carl A. Monroe July 30, 2006.
NERC Project S ystem Protection Coordination - PRC-027​ Presentation to the NSRS Conference Call April 20, 2015 Sam Francis Oncor Electric Delivery.
1 1 1 Central Maine Power Local System Plan Presentation Planning Advisory Committee Meeting November 19, 2008.
Order 1000 Implementation in PJM – Challenges and Opportunities Jodi L. Moskowitz Senior Director – Transmission Development & Strategy October 13, 2015.
June 2008 Windsor-Essex Electrical Service Needs and Solutions.
ERS Update – DSWG Presentation September 21, 2012.
Distributed Generation Registration June 30, 2008.
Transmission Capital Project Updates. Transmission Expansion Plan Sigurd to Red Butte 345 kV line in-service May, 2015 Permitting activities continue.
October 29, 2012 RARF Workshop 2 Introduction to ERCOT Modeling Process Jay Teixeira Manager, Model Administration.
WECC-0100 Scope, Content & Status Update Rikin Shah, PAC Orlando Ciniglio, IPC WECC TSS Meeting, Salt Lake City, UT January ,
Coordinated Planning Concept (For Discussion Only) revised 11/30/04 07/01/04.
Capacity, Demand and Reserves Report Bill Bojorquez Board of Directors Meeting May 16, 2007.
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
Current Nodal OS Design 1.The NMMS database will have an OWNER and an OPERATOR designation for each piece of equipment in the model. The OWNER and OPERATOR.
2006 Reliability Study James Manning Bryan Guy May 12, 2006.
Dated: 17 February 2016 Instructor :Kashif Mehmood.
DRAFT – FOR DISCUSSION PURPOSES ONLY © 2013 New York Independent System Operator, Inc. All Rights Reserved. EIPC Roll-Up Powerflow Model Zach Smith Director,
PJM ©2007 NERC LTRA Workshop August 16, 2007 Paul McGlynn Manager, Transmission Planning Department.
4/16/2010 Regional Planning Group Meeting Long-Term Planning Study of the ERCOT Interconnection Warren Lasher Manager, System Assessment.
Orange County Government Adoption Public Hearing May 10, 2016 Board of County Commissioners School Impact Fee Update.
Current Nodal OS Design 1.The NMMS database will have an OWNER and an OPERATOR designation for each piece of equipment in the model. The OWNER and OPERATOR.
TAC Report to the ERCOT Board
NWA Suitability Criteria
I-5 Corridor Reinforcement Project
Massachusetts Electric Restructuring Roundtable
Reliability Assessment Committee Reliability Workshop Priorities
Presenter: Peter Heidrich, FRCC – BES Drafting Team Chair
New England Resource Adequacy
Reliability Assessment Committee Reliability Workshop Priorities
Annual Attachment O Stakeholder Meeting
Supplemental Project Planning Process Under Order 890 Within PJM
Annual Attachment O Stakeholder Meeting
Annual Attachment O Stakeholder Meeting
Presentation transcript:

National Grid Local System Plan Needs Assessment/Potential Solutions PAC Meeting September 21, 2010

Purpose of Local System Plan Per Attachment K – Local, the LSP is a report that:  Describes projected improvements to non-PTF that are needed to maintain system reliability  Reflects:  LSP Needs Assessments  Corresponding transmission system planning and expansion studies  Identifies:  Local Planning Process  Criteria, Data, and Assumptions

LSP Communication  PAC, Transmission Customers, and other Stakeholders have 30 days to provide any written comments for consideration by National Grid.  National Grid’s contact: Gabriel Gabremicael Mgr Transmission Planning, New England National Grid 40 Sylvan Road Waltham, MA  The ISO-NE RSP project list links to each individual TO’s LSP project list.  National Grid’s project list is located at:   "LSP - LTP Transmission Projects - August 2010

LSP Project List  The LSP Project List is a cumulative listing of proposed regulated transmission solutions that may meet LSP needs.  Lower voltage facilities contained in the LSP Project List pertain to facilities supplying our wholesale municipal customers.  The LSP Project List contains the status of each project:  Concept  Proposed  Planned  Under Construction  In Service

LSP Project List Definitions Project Status Descriptions (may vary slightly from RSP definitions) ConceptProject is under consideration as possible solution to a need, but little or no analysis is available ProposedNational Grid has internally determined that the project is an appropriate solution to a need, but has not yet obtained Proposed Plan Approval (PPA) from ISO-NE (1.3.9 ISO-NE approval) PlannedPPA has been approved (if required) and has internal approval. Under Construction Project has PPA approval and has internal approval. In ServiceProject is complete

Local System Planning Process  Local studies can result from:  Load Growth  Area Reliability Assessments  Point of Delivery Request from Customer  Generation Interconnection Request  Asset Replacements (included in list as a new addition)  A Planner –  summarizes the results from the needs assessment and provides: criteria, data and assumptions used in study  builds study cases with proposed alternatives  determines the most effective solution  summarizes the results of the solutions study

Criteria  All National Grid facilities that are part of the interconnected National Grid system shall be designed in accordance with the National Grid Transmission Planning Guide.  The National Grid Transmission Planning Guide is posted on our website under: as:  Transmission Planning Guide

Data and Assumptions Resources for studies:  NEPOOL Library cases for load flow and ASPEN short circuit studies  CELT Report Load forecasts for NE wide loads  Customer provided forecasted loads for local areas

Local System Plan – What’s New?

Addressing 2009 LSP Comments At the request of the Massachusetts Attorney General, National Grid added the following data categories to our LSP:  Dollar amounts for projects  Company Asset Owner

2010 LSP Projects

LSP – Massachusetts (Fonts in Red are new or updates)

LSP – Massachusetts Continued

LSP – Massachusetts continued

LSP – Rhode Island

LSP – Removed From List

Questions