Children’s Services Scrutiny Building Schools For the Future Update 11 April 2012.

Slides:



Advertisements
Similar presentations
The Role of Joint Ventures in Local Government Des Gardner Head of Regeneration (Legal) Manchester City Council.
Advertisements

Increasing Participation & Raising Standards. WHO strategy for reducing deaths from drowning based on: Increasing Participation Education Raising Standards.
Learning Disability Partnership Board Choice and Control - update (LD Strategy 2011 – 2014) Doris Sheridan – October 2013 Learning Disability - People.
Background PFI (Private Finance Initiative) School to be built by Miller Construction Government Funded Supported by the Local Authority School is designed.
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
1 BROOKHAVEN SCIENCE ASSOCIATES Central Chilled Water Facility – Phase II Alan Raphael MPO Project Manager CFAC Committee Review November 9, 2009 Sub-basement/Pipe.
Building Schools for the Future Maximising the Opportunities Monday 8 th February 2010 By: Alison Butcher – Programme Director.
Salford Building Schools for the Future Programme – Phase 2 proposals.
CoVE: Catalyst for Change David Fisher – CoVE Programme Manager LSC National Office.
Budget Scrutiny Committee Wednesday, 4 th November, 2009 Topical Issues.
Louisiana Community & Technical College System April 2013 Jan Jackson, Sr. Vice President for Finance & Administration PROGRESS of ACT 391 Construction.
I.Program Update The following summarizes major activities completed or in progress as of June 30 th, II.Program Budget Summary (Attachment A) The.
Salford Secondary Schools GCSE Results Headlines Provisional results indicate that 50% students gained 5+A*-C including English and maths, an improvement.
The West London Free School Palingswick House Update.
Performance Management Reporting: Quarter 4 Guide to Q4’s reporting Overall performance for Q4 Key Service Priorities Other performance indicators Next.
SEN and Disability Green Paper Pathfinders March 2012 Update.
PRESENTATION ON THE REVIEW OF THE PROJECT CYCLE BY R.K.D. Van-ESS Date: 27 th September, 2011 Venue: Erata Hotel.
Budget Update August 12, 2014 Mary Simon Senior Director, Budget Development & Planning Mary Simon Senior Director, Budget Development & Planning 1.
NEW MAINTENANCE CONTRACTS INC RESPONSIVE REPAIR REVIEW AND RIGHT FIRST TIME Customer Committee 27 th January 2015 Debbie Whitfield Head of Property Services.
I.Program Update The following summarizes major activities completed or in progress as of September 30, II.Program Budget Summary (Attachment A)
MSESP Grantee Webinar October 2, Agenda Record Webinar Welcome Administrative Updates Getting to know you….  Grantee Presentation: MN Green – BGAF.
University of Toronto Mississauga Campus: UTM Master Plan Update Campus and Facilities Planning | March University of Toronto Mississauga Campus.
Bond Oversight Committee Meeting Third Quarter October 29, 2013.
WICK COMMUNITY CAMPUS. The Wick Community Campus will comprise of the following: Replacement Wick High School Replacement community swimming pool Replacement.
Paradise Valley Community College CLC Update Jacalyn A Askin, Vice President of Administrative Services May 8, 2009.
By Charles K. Miller VPA Support Unit Mamba Point, Monrovia, Liberia West Africa Forest Governance Forum Held at: Grand Royal Hotel Monrovia, Liberia A.
Presentation to Environment, Housing and Planning Scrutiny “Recycling Service Update” Monday 18 th May 2009 David Robinson Assistant Director (Liveability)
Richard Cairns, Executive Director of Infrastructure and Regeneration Community Alliance 5 August 2015.
SUPERINTENDENT’S RECOMMENDATIONS Capacity Utilization Arlington Public Schools December 17, 2009.
Easter Bush Update December The New Teaching Building 12,500 square meters on three floor providing accommodation for up to 850 students and 200.
Standards for Better Health – update for Overview & Scrutiny Committee Jacqui Evans Clinical Governance Manager 22 February 2006.
Phil Royle District Operations Manager Greater Manchester Central and Cheshire District.
HEARTLAND COMMUNITY COLLEGE COLLEGE DEVELOPMENT PLAN PHASE II PROJECT SCHEDULE August 26, 2009.
Bond Oversight Committee Meeting Fourth Quarter February 7, 2014.
Salford School’s Provider Arm and the Education Improvement Plan…an update on progress to date Phil Smith Head of School’s Provider Arm.
Southend Together Secretariat 21 st February Developing Southend Together’s Sustainable Community Strategy
Manchester Town Hall Complex – Achieving Energy Performance.
Post Program Placement Planning A Strategy to Assist with Placement.
Welcome As 2015 draws to an end, we want to take this opportunity to update you on the exciting progress the school meals programme has made over the last.
November 2013 Performance Report RM Education Stoke BSF and Stoke CIS.
Choosing Health Consultation Ursula Sossalla-Iredale – Neighbourhood Manager Irlam & Cadishead Vicky Halliwell – Health Improvement Officer – Irlam & Cadishead.
Introduction. Service Update Property Investment Residential Care to Supported Living New Business Recruitment and Retention.
Middlesbrough Building Schools for the Future Update for Scrutiny.
Shropshire Providers Consortium (SPC) 2.5 years on.
Blaenau Gwent and Caerphilly Integration March 2012 Update.
QUARTERLY PERFORMANCE OF THE MUNICIPAL INFRASTRUCTURE GRANT (MIG) – 2005/06 AND 2006/07 FINANCIAL YEARS Presentation to the Select Committee On Finance.
OUTSOURCING CHILDREN’S SOCIAL WORK – THE DEVON EXPERIENCE AN UPDATE ON THE 2013 EXTERNALISATION OF AN INTEGRATED HEALTH & SOCIAL CARE SERVICE Brenda Bartlett.
CONSTRUCTING WEST MIDLANDS Question & Answer Session 22 nd March 2011 LOT 7 – CAPITAL WORKS.
Welfare Reform Working Group 26 th September 2012.
Industry Assistance Office (IAO) What we do * Focal point for the Goddard Contractor community regarding business opportunities at the Center * Critical.
Regional Schools Commissioners Norfolk Headteachers Tim Coulson 4, 5, 12 November
ESPLOST Update Savannah-Chatham County Public Schools March 5, 2008.
Welcome This partnership meeting will cover information and the timetable for the opening of the new KCEPS.
2017 Measure X First Quarterly Meeting
St Michael’s C of E Primary School Front of School Enhancements
Proposed merger update September 2016 Peter Homa, Chief Executive NUH & SFH Louise Scull, Chair, NUH & SFH.
Norfolk Constructing Excellence Awards 2016 Ben Llewellyn
Collaboration Work Based Learning.
All Wales Safeguarding Procedures Review Project
Northwest Hospital Childbirth Center Pre-submittal Meeting
Welcome! Hodgson Middle School Parent Information Night
Supplementary Services Project Management Services.
Children’s Hospital Update
Xoserve IX Refresh Customer Update 03/01/2019.
Applying for a place at Primary School
ETSI STF333: European accessibility requirements for public procurement of products and services in the ICT domain (Phase 1, EC Standardisation Mandate.
Offsite Construction Manufacturing BACH
Multi-discipline academic research science technology engineering & math (stem) building project phase 1 NAU Project No RFQ for Construction.
Chapter 2 – Review ‘construction management’
Presentation transcript:

Children’s Services Scrutiny Building Schools For the Future Update 11 April 2012

Phase 1 Walkden High and Irlam & Cadishead College – both are fully operational and there are no issues. Both buildings have been very well received by the schools and the communities. Laing O’Rourke have won ‘Considerate Contractor’ awards for both of these projects, Irlam gained a silver award and Walkden a bronze award. The facilities management aspect of this PFI contract has been well initiated and the new arrangements are working well. Phase 1b Oasis Academy is on schedule and will be ready for opening in September 2012 as planned. The building is externally complete and is looking really good on its site. The Salford BSF programme is now progressing smoothly and all phases are currently on schedule. The team of LA officers and private sector partners are working efficiently together to achieve steady progress in all phases.

Phase 2 St Patricks is currently being constructed and is ahead of schedule. This school project is being monitored closely by Laing O’Rourke as it is being used by the company as a national showcase project. The school is scheduled to open Easter St Ambrose Barlow is progressing well and a recent groundbreaking ceremony has been held by the school. This school is on programme to open with St Patricks at Easter Moorside High and Primary is progressing well and is also on schedule. This combined 2 school building is the largest construction project of the phase and will open in September 2013

Phase 3 We have recently gained all the approvals required and this final BSF phase will begin in April Phase 3a The design process will begin immediately after Easter 2012 for Wentworth and All Hallows and will be finalised within 12 months. Construction will begin by April 2013 and occupation of the two new buildings will be by September Phase 3b Work to address the condition needs of St Georges will be carried out, with a completion date of September 2014 in line with phase 3a. Salford BSF as a programme should have all remaining contracts in place by March 2013 and all construction works completed by September 2014.