WP4 Activities J. Nash – SLHC-PP SG SLHC-PP WP4 Feb 20091J. Nash - CMS Upgrades.

Slides:



Advertisements
Similar presentations
US CMS DOE/NSF Review: May 8-10, US CMS Cost & Schedule Mark Reichanadter US CMS Project Engineer DOE/NSF Review 8 May 2001.
Advertisements

CMS Upgrade Issues LHCC 1 July July 20081J. Nash - CMS Ugrades.
O. Buchmueller, Imperial College, W. Smith, U. Wisconsin, UPO Meeting, July 6, 2012 Trigger Performance and Strategy Working Group Trigger Performance.
CMS Phase 2 Upgrade: Scope and R&D goals CMS Phase 2 Upgrade: Scope and R&D goals October 21, 2014 Jeremiah Mans On behalf of the CMS Collaboration.
The LHCf experiment Measurement of Photons and Neutral Pions in the Very Forward Region of LHC Letter Of Intent: May 2004 Technical report: September 2005.
Sept. 18, 2008SLUO 2008 Annual Meeting ATLAS Detector Upgrade Opportunities M. G. D. Gilchriese Lawrence Berkeley National Laboratory.
Tullio Grassi ATLAS–CMS Power Working Group 31 March 2010 DC-DC converters and Power Supplies requirements for CMS HCAL Phase 1 Upgrade.
WP2: Detector development Summary G. Pugliese INFN - Politecnico of Bari.
US CMS Phase 2 R&D Discussion 30-July-2013 “Phase 2 muon R&D” J. Hauser, UCLA  Add redundancy (power) to trigger where most needed  First and innermost.
D. Lissauer, BNL. 1 ATLAS ID Upgrade Scope R&D Plans for ATLAS Tracker First thoughts on Schedule and Cost.
US CMS Collaboration Meeting, May 19, PWO Crystal ECAL Ren-yuan Zhu California Institute of Technology May 19 th 2001.
U.S. ATLAS Executive Meeting Upgrade R&D August 3, 2005Toronto, Canada A. Seiden UC Santa Cruz.
The LHCf experiment Measurement of Photons and Neutral Pions in the Very Forward Region of LHC Letter Of Intent: May 2004 Technical report: September 2005.
Progress on the CMS Pixel front-end system ACES Workshop CERN 4. March 2009 R. Horisberger Paul Scherrer Institut.
WP2: Detector development Summary G. Pugliese INFN - Politecnico of Bari.
M. Gilchriese ATLAS Upgrade Introduction January 2008.
Pixel Upgrade Status and Plan G.M. Bilei Firenze Mar. 6 th 2013.
Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1.
CMS Upgrade Workshop, November 2008 H. W. K. Cheung (FNAL) 1 Simulation WG Summary There was no actual separate Simulation Working Group/sessions.
Workshop 24 Jun 11 AB Workshop on GEMs for CMS high  Last September’s workshop showed that MPGD technology is now mature. Stable operation of large area.
Barrel Endcap The RPC System Baseline Six stations in the Barrel Four station in the Endcap up to  = 2.1 Baseline Six stations in the Barrel Four station.
CMS Upgrade Requirements and Upgrade Plans Hans-Christian Kästli, PSI CHIPP Workshop on Detector R&D.
CERN, Main challenges for the ATLAS upgrade project in the coming year.
CMS Phase I upgrades LHCC September 2009 Meeting LHCC Sep 2009J. Nash - CMS Upgrades1.
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese Revised Version December 18, 2000.
SiD R&D tasks for the LOI - Subsystem R&D tasks - Summary of SiD R&D - Prioritization of R&D tasks -> Document for DoE/NSF ~Feb 2009 (Mainly based on Marty’s.
Pixel Endcap Power Distribution Phase 1 Upgrade Plans Fermilab, University of Mississippi, University of Iowa Lalith Perera University of Mississippi CMS.
Pixel Upgrade Phase I CMS Upgrade Week 27. April 2010 R. Horisberger, PSI.
M. Gilchriese U.S. Pixel Mechanics Overview M. G. D. Gilchriese Lawrence Berkeley National Laboratory April 2000.
UCSC August 12, 2008 U.S. Upgrade R&D Meeting: Strip Detector  Seiden.
All CMS 30 May07 TSV1 All CMS 3 30 May 2007 LHC machine CMS Progress Overall Schedule.
Overview of a Plan for Simulating a Tracking Trigger (Fermilab) Overview of a Plan for Simulating a Tracking Trigger Harry Cheung (Fermilab)
Compilation of Dis-/Advantages of DC-DC Conversion Schemes Power Task Force Meeting December 16 th, 2008 Katja Klein 1. Physikalisches Institut B RWTH.
Peter Sharp CERN CMS Tracker Summary of the Tracking Trigger Working Group Peter Sharp 21 November 2008.
Pixel power R&D in Spain F. Arteche Phase II days Phase 2 pixel electronics meeting CERN - May 2015.
DC-DC Conversion Studies – Status Report from Aachen Tracker Upgrade Power WG Meeting February 13 th, 2009 Lutz Feld, Rüdiger Jussen, Waclaw Karpinski,
9/17/2008TWEPP 2008, R. Stringer - UC Riverside 1 CMS Tracker Services: present status and potential for upgrade Robert Stringer University of California,
TC Straw man for ATLAS ID for SLHC This layout is a result of the discussions in the GENOA ID upgrade workshop. Aim is to evolve this to include list of.
Software Tools for Layout Optimization (Fermilab) Software Tools for Layout Optimization Harry Cheung (Fermilab) For the Tracker Upgrade Simulations Working.
General Muon Meeting, 03-March-2014 Jay Hauser “Update on Phase 2 muon Technical Proposal”  Recent developments:  ME0 inserted into HGCAL as for other.
News and Miscellaneous UPO Jan Didier Contardo, Jeff Spalding 1 UPO Jan Workshop on Upgrade simulations in 2013 (Jan. 17/18) -ESP in.
CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Update ME4/2 Chambers and Tooling A construction of new ME4/2 prototype at CERN Factory tooling,
Upgrade PO M. Tyndel, MIWG Review plans p1 Nov 1 st, CERN Module integration Review – Decision process  Information will be gathered for each concept.
News and Misc Didier Contardo, Jeff Spalding UPO 3/2/12 1 UPO 2/2/12 o The MM, cost estimates and reporting o Milestones and scheduling o Chamonix Meeting.
1 Towards Phase 2 TP releases 2013 Didier Contardo, Jeff Spalding Status of current simulations studies and ongoing issues Needs for TP preparation.
Geoff HallLECC LHC detector upgrades Introductory comments on electronic issues Organisation of this short session.
CMS Upgrades Progress LHCC February 2009 Meeting LHCC Feb 2009J. Nash - CMS Upgrades1.
Tracker Upgrade Mechanical/Thermal Engineering 3 June meeting theme: Modules and Structures News on Phase 1 BPIX Upgrade Mechanics & Modules, R. Horisberger.
R&D for SLHC detectors at PSI and Geneva CHIPP workshop on the high-energy frontier of particle physics Zürich 6. September 2006 R. Horisberger (Paul Scherrer.
Upgrade Intro 10 Jan 2010 Norman Gee. N. Gee – Upgrade Introduction 2 LHC Peak Luminosity Lumi curve from F.Zimmermann : Nov Upgrade Week ? ?
Introduction to L1Calo Upgrade L1Calo Collaboration Meeting Cambridge 23-Mar-2011 Norman Gee.
Summary of IAPP scientific activities into 4 years P. Giannetti INFN of Pisa.
WBS 1.05 Commissioning Detector Scope, Cost & Schedule Sven Vahsen University of Hawaii.
Straw man layout for ATLAS ID for SLHC
University of Wisconsin
Scope R&D Participants/Infrastructure
News and Misc UPO Meeting Jan 16, 2012
IOP HEPP Conference Upgrading the CMS Tracker for SLHC Mark Pesaresi Imperial College, London.
Tracker Upgrade Simulation Task List Harry Cheung (Fermilab), Alessia Tricomi (Catania)
P. Morettini Towards Pixel TDR PM - ITk Italia - Introduction 8/2/2017.
Mini-drawers, FE-ASIC , Integrator
TK Upgrade report.
Francesco Forti University and INFN, Pisa
DC-DC Conversion Studies – Status Report from Aachen
Silvan Steuli Roland Horisberger Stefan König CMS Upgrade Workshop
2nd ACES workshop, CERN Hans-Christian Kästli, PSI
The LHCb Front-end Electronics System Status and Future Development
Upgrade Phase 2 Mechanics meeting, 21 March 2013 Introduction
Presentation transcript:

WP4 Activities J. Nash – SLHC-PP SG SLHC-PP WP4 Feb 20091J. Nash - CMS Upgrades

Task 4.1 SLHC-PP WP4 Feb 20092J. Nash - CMS Upgrades

Task – Management Structure  Project management structure defined  Management team put in place  Team and mandate approved by CMS  Now a “project” (ala Tracker/ECAL…)  Regular meetings of management team  Monthly meetings of overall upgrade team  Regular meetings of many subgroups within sub-detector upgrade projects  Two Workshops held, more planned SLHC-PP WP4 Feb 2009J. Nash - CMS Upgrades3

Upgrade project organization SLHC-PP WP4 Feb 2009J. Nash - CMS Upgrades 4

Milestone 4.1 – Upgrade Scope  Workshop in May 2008 at CERN to define the scope of upgrades  What needs to be done in Phase I, Phase 2  Follow up workshop held November 2008 in FNAL (150 participants) to track progress, and prepare work plan for the following six months  Goal prepare TP for phase I upgrades  Workshop to be held in May 2009 to present, approve plans for phase I upgrades, and also progress towards a “Strawman” for phase 2 upgrades. SLHC-PP WP4 Feb 2009J. Nash - CMS Upgrades5

SLHC-PP WP4 Feb 2009 J. Nash - CMS Upgrades 6 Collimation phase 2 Linac4 + IR upgrade phase 1 New injectors + IR upgrade phase 2 Early operation To be revised First phase imminently Second phase more known after start of LHC data taking To be revised First phase imminently Second phase more known after start of LHC data taking Upgrades required to keep CMS operating at maximum potential throughout

Upgrade Scope SLHC-PP WP4 Feb 2009 J. Nash - CMS Upgrades 7 System Phase 1Phase 2 Pixel New Pixel Detector (1 or 2 iterations?) Tracker FEDs?New Tracking System (incl Pixel) HCAL Electronics + PD replacementHF/HE? ECAL TP (Off Detector Electronics) ?EE? Muons ME4/2, ME1/1,RPC endcap, Minicrate spares, some CSC Electronics Electronics replacement Trigger HCAL/RCT/GCT to  TCA Complete replacement Agreed at the May 2008 Upgrades Workshop Agreed at the May 2008 Upgrades Workshop

Documents Phase I Upgrades Phase 2 Upgrades SLHC-PP WP4 Feb 2009 J. Nash - CMS Upgrades 8 Concept mid 2008 LOI/TP mid 2009 TDR Early 2010 Strawman Mid 2009 TP/LOI Mid 2010 TDR 2012 Work Plan agreed at the May Workshop Pixel ME4 Pixel ME4

November Workshop at FNAL  Meeting held November 2008 at FNAL   Checkpoint to assess progress towards 2009 milestones  Goals for the meeting  follow progress, concentrate on phase I, some look at critical Phase 2 areas  establish the workplan for the coming 6 months  Key output for this workshop: a program of work which helps us arrive at a planning for the Phase I upgrades.  Excellent levels of attendance and quality of discussion indicate what a success this meeting was  Around 150 participants many from outside the US  Workshop atmosphere  Good to think outside of the box – CMS has been successful by being ambitious  Real progress has been made in identifying key areas to focus effort on in the coming months  Also a chance to look at “cross-disciplinary” areas SLHC-PP WP4 Feb 2009 J. Nash - CMS Upgrades 9

BPIX Options for 2013 replacement/upgrade Option Cooling C 6 F 14 CO 2 Readout analog 40MHz analog 40MHz analog 40MHz analog 40MHz  -tw-pairs digital 320MHz  -tw-pairs digital 640 MHz  -tw-pairs Pixel ROC PS46 as now 2x buffers 2xbuffer, ADC 160MHz serial 2xbuffer, ADC 160MHz serial Layer/Radii 4, 7, 11cm 4, 7, 11, 16cm Modules Power as now DC-DC new PS as 2008 Slide from 21. May 2008 SLHC-PP WP4 Feb J. Nash - CMS Upgrades

After many discussions, considerations & iterations 4 layer pixel system 4, 7, 11, 16 cm  1216 full modules CO2 cooling based Ultra Light Mechanics BPIX modules with long 1.2m long microtwisted pair cables Shift material budget from PCB & plugs out of tracking eta - region ROC buffers for 1.5 x and serial binary MHz Serialized binary optical readout at 320 MHz to old, modified px-FED Recycle & use current AOH lasers  320MHz binary transmission Same FEC’s, identical TTC & ROC programming Keep LV-power supply & push more current through cables SLHC-PP WP4 Feb J. Nash - CMS Upgrades

BPIX Upgrade Phase 1 (2013), 4 Modules long SLHC-PP WP4 Feb J. Nash - CMS Upgrades

BPIX/FPIX Envelope Definition for 4 Layer Pixel System Various iterations forth and back by R.H. / Silvan Steuli / Kirk Arndt  no further changes since ! All barrel layers 4 module long  small eta hole of  ~ 0.08 at  =1.288 SLHC-PP WP4 Feb J. Nash - CMS Upgrades

Current Pixel System with Supply Tubes / Cylinders FPIX service cylinder BPIX supply tube DOH & AOH mother board + AOH’s Power board endflange prints Layer 3 & 1+2 SLHC-PP WP4 Feb J. Nash - CMS Upgrades

BPIX Cabling & flexible cooling pipes SLHC-PP WP4 Feb J. Nash - CMS Upgrades

Shift PCB/Plug Material out of tracking Volume FPIX service cylinder DOH & AOH mother board + AOH’s power board Modules with long pigtails (1.2m) CCA wires 16x(2x125  Move DOH & AOH boards back by 50-60cm SLHC-PP WP4 Feb J. Nash - CMS Upgrades

Present BPIX New 2013 BPIX Comments Empty mechanics 1103 g550 g possible, with ~ 94g for 1.5mm/1.4mm pipes 384 Module 872 g522 g 1.36g/mod no SiN strips 75  ROC no HV-cap 384 Signal cable 167g 7 g 2 x ( 2x125  CCA) 384 Power (6x250  CCA) 82g 68 g 5x250  CCA 384 Power plug 16g 0 g none 32 Print 499 g 32 g radial power cable to ST Cooling (C 6 F 14 ) 810 g 83 g CO 2 in 1.45mm diam. pipe Silicon tube incl. fluid 372g 5 g CO 2 pipes to supply tube Total 3921g1267 g factor 3.1 down New weight of replacement/upgrade BPIX detector (2013) Transparecy 21.May 2008 SLHC-PP WP4 Feb J. Nash - CMS Upgrades

SLHC-PP WP4 Feb 2009 J. Nash - CMS Upgrades18 Moving to Phase II Tracker - Draft Upgrade Structure Material Budget, Power Consumption, cooling key issues for a new tracker Tracker upgrade team has been actively studying these areas Material Budget, Power Consumption, cooling key issues for a new tracker Tracker upgrade team has been actively studying these areas

Results summarized by Lutz in October meeting System Test with DC-DC Converters SLHC-PP WP4 Feb J. Nash - CMS Upgrades  Noise of Enpirion converters can be controlled by combination of shielding and filtering (LDO). --- No converter --- Converter --- Converter + 30  m Alu shielding --- Converter + LDO --- Converter + LDO + 30  m Alu shielding Studies with commercial buck converters documented in Jans thesis CMS TS-2009/003 “System Test Measurements with a DC-DC Conversion Powering Scheme for the CMS Tracker at SLHC”

C02 Cooling for phase II SLHC-PP WP4 Feb 2009 J. Nash - CMS Upgrades20 Almost essential to re- use the current cooling pipes on YB0, can this be done? Met with CERN safety commission to discuss issues Looks possible, agreed plan of validation with CERN safety Almost essential to re- use the current cooling pipes on YB0, can this be done? Met with CERN safety commission to discuss issues Looks possible, agreed plan of validation with CERN safety

Example: Layout for the Tracking Trigger Project CMS Tracker  2.5 A conceptual layout for a tracking detector was proposed  Trigger groups to understand what could be achieved with stubs  Tracker produces stubs to feed the Trigger Layout concept for stacked rods proposed  study groups to look at the practical aspects – What questions do we need to answer to understand if this can be built? A conceptual layout for a tracking detector was proposed  Trigger groups to understand what could be achieved with stubs  Tracker produces stubs to feed the Trigger Layout concept for stacked rods proposed  study groups to look at the practical aspects – What questions do we need to answer to understand if this can be built? A tracker which inputs to L1 will have overlaps with all Sub dets SLHC-PP WP4 Feb 2009 J. Nash - CMS Upgrades

Examples with two “Pt” layers at lower radii Layout Task Force D. Abaneo Layout Task Force D. Abaneo SLHC-PP WP4 Feb J. Nash - CMS Upgrades

Trigger  Technologies for Phase I upgrades  Micro TCA implementations  The hope is to develop a common infrastructure for use in trigger upgrades  Reduce the large number of standards currently in use in the trigger system  Increase reliability/flexibility  Tracking Trigger discussions  Possible candidate architectures  Simulations  Key R/D for phase II  Need to establish which ideas most likely to be successful and dedicate sufficient resources to determine viability  Can it be implemented  How well does it work  Power/Material implications SLHC-PP WP4 Feb 2009 J. Nash - CMS Upgrades23

Calorimeters  HCAL  Progress on using Silicon PMs as a new Photo Detector  New off detector electronics  Upgrade strategies  ECAL  Data on radiation damage to crystals and VPTs in the EE  Establish what will be the performance at SLHC  Simulations of SLHC and EE  How well will the EE perform given any performance degradation  ECAL/HCAL joint electronics issues  e.g. Trigger electronics SLHC-PP WP4 Feb 2009 J. Nash - CMS Upgrades24

WP 4.2 Deliverables SLHC-PP WP4 Feb J. Nash - CMS Upgrades

Task – Upgrade TC Unit established  Upgrade TC named (W. Zeuner)  Working within the current technical coordination unit.  Have started work on defining the working methodology  Planning for Muon system phase I upgrade (ME 4/2 Construction and installation) progressed well at the FNAL workshop  Meetings between Executive Board, and Project Managers to discuss procedures for reviews, TC needs for upgrades, engineering support issues SLHC-PP WP4 Feb 2009J. Nash - CMS Upgrades26

Muons  Planning for Phase I upgrades  CSC production  RPC production  Planning for installation  Concepts for using the Muon system in a tracking trigger SLHC-PP WP4 Feb 2009 J. Nash - CMS Upgrades27

ME4/2 Upgrade Schedule  t 0 -- CD2 approval, money flows, begin work on Bldg 904  t 0 +3 months -- orders sent out for all parts  t 0 +6 months -- production tooling shipped to CERN and assembled in Bldg 904  t 0 +9 months -- chamber parts delivered, shipped to CERN  t months -- production begins at Bldg 904 at 2 CSCs/month  t months -- production ramps to 4 CSCs/month  t months -- FAST site begins assembly & testing at CERN (Bldg 904?), spare CFEB boards installed on ME4/2s  t months CSCs finished and tested -- ready for installation of 1st endcap, recover 200 CFEB boards from ME1/1s  t months -- all 76 CSCs finished  t months -- final 36 chambers ready for installation on 2nd endcap SLHC-PP WP4 Feb J. Nash - CMS Upgrades

Future meetings  Upgrade Days  Meetings scheduled once per month  Keep momentum  Track progress  Topics which cross detector groups, or go into depth on a particular topic  Examples : Sensor R/D, HCAL/ECAL common readout electronics, tracking trigger issues  Upgrade Workshop May 2009 CERN SLHC-PP WP4 Feb 2009 J. Nash - CMS Upgrades29

Spend Profile CERNDESYETHZImperial Total Project Spend to date SLHC-PP WP4 Feb 2009J. Nash - CMS Upgrades30

Reports  We have to produce reports this month for the two deliverables we have achieved.  Fairly lightweight  See PP/MILESTONES.htm#Milestoneshttp://info-slhc-pp.web.cern.ch/info-SLHC- PP/MILESTONES.htm#Milestones  J. Nash for  W. Zeuner for  In 6 Months time we have a milestone to report on  Project scope defined  should be a direct outcome of our May workshop. SLHC-PP WP4 Feb 2009J. Nash - CMS Upgrades31

Conclusions  Good progress on tasks/Milestones  Upgrades teams established  Upgrade Scope understood  Details being studied/prepared  Phase I/Phase 2 split actually allows us to deliver a fairly complete upgrade plan during the course of this FP7 project SLHC-PP WP4 Feb 2009J. Nash - CMS Upgrades32