B.Puccio MPE Workshop for LS1 / 22 & 23 Nov. 2012 Logistics for DYPB activities Bruno PUCCIO (TE/MPE)

Slides:



Advertisements
Similar presentations
SGI Confidential Copan 400 Installation. SGI Confidential Installation Overview The approximate minimum time to complete this procedure is.
Advertisements

1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
A. Perin, CERN, TE-CRG, 26 May Review of the cryogenic by-pass for the LHC DS collimators 26 May 2011 Modifications to the DFBs, DSLC and cryogenic.
Fibres & copper Cabling activities LIU meeting 27/09/2013 F Duval 27/09/2013 F Duval Cabling acxtivities LIU 1.
TE-MPE-TM 09/08/2012, TE-MPE-MS section WIC: Overview of on-going projects + Outlook to LS1 activities: - Short introduction to WIC systems - Booster renovation.
Remote manipulations / diagnostics in radioactive areas and handling of radioactive material Workshop, Geneva, Switzerland 6 th May 2013 THE REPLACEMENT.
TE/MPE/EE J. Mourao T/MPE/EE 1 November 2012 LHC Machine Local protection Redundant Power supply (DQLPUR) - Review.
TE-MPE-EP, RD, 26-Jul Quench Heater Supervision for MB Status of System Integration R. Denz TE-MPE Technical Meeting July 26 th Acknowledgements:
Alfa-Omega Team Coordination LS1 Collaboration Seminar, 27 th November 2014 Anna Chrul, IFJ PAN Kraków.
TE-MPE-EP, VF, 11-Oct-2012 Update on the DQLPU type A design and general progress. TE-MPE Technical Meeting.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
41 st LSC – March 21, 2014 G.J. Coelingh, TE-MPE-EE Long Shutdown 1 Status Report The upgrade of 600 A Energy Extraction Systems.
Upgrades and Activities of 13kA EE systems during LS1 Bozhidar Panev TE-MPE-EE
How to achieve higher redundancy of the UPS for QPS ? -The lack of redundancy concerns the supply lines from UPS to consumer but equally parts of the UPS.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
June 1 rst, Consolidation for E-cloud and High Voltage cards N.Vauthier TE-CRG LS1 projects review:
TE/MPE/EE J. Mourao T/MPE/EE 1 November 2012 LHC Machine Local protection Redundant Power supply (DQLPUR) & interface Module (DQLIM) progress status.
18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page
DQHDS Upgrade: Status of Hardware Design. Approach to implementation of the new heater measurement system. 08/06/2011V. Froidbise.
Update and status for the Work Unit ‘Energy Extraction’ - equipping the three test benches for series testing of Super-FRS Dipoles D2, D3, D4 and Quadrupoles.
Technical Support Activities in PH-ADO-PO
TE-MPE LS1 review 02/06/2015, Mateusz Bednarek, TE/MPE-EE ELQA during LS1 – the “unexpected” activities New developments Exceptional NCs Other tests.
TE/MPE/EE J. Mourao T/MPE/EE 23 December 2012 LHC Machine Redundant Power supply (DQLPUR) & interface Module (DQLIM) assembling during LS1.
TE-MPE-CP, RD, 09-June Enhanced Diagnostics & Supervision for Quench Heater Circuits R. Denz TE-MPE-CP.
AT-MEL-PM, R. Denz, CERN, CH-1211 Geneva 23 1 QPS system and its risks  Principal risks  General remarks  Quench heater circuits  Quench detection.
K. Foraz, S. Prodon TS-IC TS workshop – May 2005 Underground logistics K. Foraz, S. Prodon TS-IC.
K. Foraz & Perrot A. L., EN/MEF - R2E Project LMC 25th May 2011 Thanks to EN/EL, EN/HE, EN/MEF, equipment owners the LHC integration team & the R2E team.
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
January 4, 2007 RHIC II Project Internal Cost Review Existing RHIC power supply Modifications Don Bruno & George Ganetis January 4, 2007 Power Supply Modifications.
TE-MPE-EP New DQLPU type A Production of 1300 new protection units TE-MPE-EP, VF, 23-Nov-2012.
Beam Interlock System MPP Internal ReviewB. Puccio17-18 th June 2010.
TE/MPE activities currently planed for YETS Reiner Denz, Knud Dalherup-Petersen, Markus Zerlauth & Bruno Puccio YETS coordination meeting.
André Augustinus Infrastructure  Turbines  Radmon  Thermocouple readout  Netgear redundancy  Other cavern items  Cooling CRs  Other CR and surface.
TE-CRG-CE OMP Meeting 06 / 11 / 2014TE-CRG-CE OMP Meeting.
TE/MPE/EE Summary of Electrical Engineering Session Ed & Knud K. Dahlerup-Petersen TE/MPE/EE 23 November RB – RQ EE facility consolidation & upgrades.
1 J. Mourao (TE/MPE/CP) Enhanced DQHDS functionality  Status for 2011  Increase Magnet diagnostic capabilities  Our proposals.
MPE Workshop for LS1 / 22 & 23 Nov. 2012, G. D’Angelo TE/MPE-EE ELQA during LS1 train, Special measurements and NCs Magnet replacement: AIV Splices consolidations:
TE-MPE participation on the GSI-CERN Collaboration for Testing Super-FRS's Superconducting Magnets (aka FAIR project) Daniel Calcoen Acknowledgements:
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
Interface of FP420 to LHC FP420 meeting 28-Sep-2006.
D. Delikaris, TE-CRG, LSC 25th Meeting Page 2 October 18 th, 2013 LS1 Committee (LSC)- 25 th Meeting D. Delikaris, TE-CRG Cryogenics activities.
TE-CRG Activities D. Delikaris, TE-CRG.
R2E relocation & shielding LS1 preparation Anne Laure Perrot EN/MEF- LE Discussion with OP colleagues, 5 th July 2012.
Each converter 3 racks (fighting for 2?) Access from front and rear of each rack! 56 racks total + 6 racks Ethernet/control Existing RF equipment to be.
TE/MPE/EE - LHC Knud 8/3/2012 Project for Upgrade of the Electrical Circuits, the Powering Scheme and the Quench Heater Supervision for Enhanced Monitoring.
MPE Workshop for LS1 / 22 & 23 Nov  DFB Instrumentation Upgrade  Cabling Issues  R2E Consolidation  Current Lead Insulation Project  DFB Instrumentation.
February 4 th, Quality assurance plan: production, installation and commissioning N.Vauthier TE-CRG Technical Review on Beam Screen Heater Electronics.
Bruno Vullierme Sept LHC-CC09 - 3rd LHC Crab Cavity Workshop Slide 1 CRAB CAVITY INTEGRATION CRYOGENICS INSTALLATION.
Plans for the UT Installation LHCb infrastructure workshop February Burkhard Schmidt for the UT group.
VELO Replacement Girish Patel University of Liverpool.
MPE LS1 workshop Summary Session 4 – Quench Detection R. Denz, D. E. Rasmussen.
ELENA installation progress F. Butin / ELENA collaboration.
Main MPE Activities during YETS/EYETS/LS2 and the Provision of Resources Andrzej Siemko Andrzej Siemko TE-MPE1.
Mikhail Ovsienko TE-MPE-EE
Daniel Calcoen TE-MPE-EP
Identification of the unused cables
Upgrade of the DYPB racks : the Organization and the Logistics
FCC Cryo-magnet Logistics
Document Plan & Milestones WP7
Injectors BLM system: PS Ring installation at EYETS
RELIABILITY OF 600 A ENERGY EXTRACTION SYSTEMS
Nikolaos TRIKOUPIS on behalf of TE-CRG-CI CRG-TM for LS2 preparation Preliminary activities of the CI section 25/09/2017
MPE main activities planned for LS2
Renovation of the 45-year old PS magnets
LS1 TE/MPE/EE CABLE ACTIVITIES
Re-Commissioning (IST) of Electrical Systems: QPS, EE & PIC
GIS Portal Racks Project
LS3 Study & Readiness Meetings
ILO Industrial Opportunities Days, 6-7 June 2019
Presentation transcript:

B.Puccio MPE Workshop for LS1 / 22 & 23 Nov Logistics for DYPB activities Bruno PUCCIO (TE/MPE)

2 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov Introduction  The “DYPB Logistics” activity is mainly composed of: Cables disconnection & securing Moving out equipment from tunnel Storage at Meyrin site (ISR-I2 area) Modification and Tests (building 281) Moving back to tunnel Reconnection & Tests  Why during LS1? For the “Technical” decisions: [see 2 previous talks] Concerning the “Logistics” part, let’s go back also to initial question: Do we have to leave or to remove DYPB racks during SMACC activities? PROS & CONS of each solution have been evaluated. After a (long) internal debate, it has been decided to move them out...

3 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov  DYPB activity is evidently depending to the general LS1 schedule Scheduling LS1 Global Schedule v1.5 Sector 1-2 example DYPB dismounting DYPB reconnection

4 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov ) Before DYPB racks removal  Disconnection and securing of cables  Removal of chassis, interconnection cables and patches from DYPB racks.  RP control at the surface:  If OK: Transport (to 281), dismounting and recuperation of components from removed chassis, interconnection cables and patches.  If NOT OK: Transport to dedicated area(s) (867?) and perform the same tasks as above.  Quick and partial RP inspection of all DYPB racks => special labeling if above threshold Allocated time: 1 week per sector Schedule v1.5 On-going discussions with RP…

5 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov ) Moving out from tunnel Due to expected rate, transport of single DYPB rack won’t be used 3 DYPB racks will be pilled up on a pallet Allocated time: 2 weeks per sector Schedule v1.5 Courtesy Serge Pelletier (EN/HE)

6 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov ) Transport from LHC to Storage area(s)* Pt4 Pt6 Pt8 Pt1 Pt2 4 x 52 palettes 3 x 52 palettes 2 x 52 palettes 3 x 52 palettes 4 x 52 palettes rate: 2 x 12 racks per day If RP check NOT OK => Transport to a dedicated area (867?)

7 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov Location of ISR-I2 area Building 30 Building 281 Building 181 “ ISR-I2 area ” ≈ 400 m 2

8 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov ) Storage in ISR-I2  … racks (i.e. 416 palettes) stored on metal shelving (5 layers)

9 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov Daily rotation between ISR-I2 and 281 Building 281 ( building 181) ISR-I2 area foreseen rate to modification & tests: 9 racks per day (i.e. 3 pallets/day)

10 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov Resources  Manpower (Technical part): [c.f. 2 previous talks]  EE & EP section  External collaborators (AGH contract) + FSU  Manpower (Logistics): :  EN/HE & Bruno  Missing resources?  No (for the logistics part)  Support from other MPE section(s)  No (except EP & EP mentioned earlier)  Contributions from other groups:  DGS-RP  EN/HE for transport

11 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov Flowchart Remove Crawford boxes, interconnect cables & DQLPUs Move DYPB racks to buffer zones Transport to 281 Transport to ISR-I2 EE preparation work & tests EP preparation work & tests Transport to 281 Final test Transport & Storage in ISR-I2 Conditioning & Packaging DQLPUs in 281Craw. Boxes in 281 Racks in ISR-I2 Re-install DYPB racks in tunnel Reconnection & Tests Disconnect and secure cables Racks in 281 Condemnation of switch breakers, RP control Transport to dedicated area(s) RP checks

12 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov Scheduled dates for sectors 5/6, 6/7, 7/8 & 8/1

13 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov Scheduled dates Q2/13 17/05 29/04 17/04 07/05 29/04 Q3/13 12/06 31/0529/05 Q4/13 Q1/14 10/02 17/03 06/01 06/02 Q2/14 07/04 30/04 14/04 30/05 Time interval (weeks* ) for DYPB racks removal for racks re-installation ( Planning Rev1-5) *: - 2 weeks for Xmas break

14 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov Unknowns When all material ready will be available at 281? When testers will be ready? 9 racks per day: is it realistic?

15 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov SW tools  What SW tools are planned to be used?  Are they ready to be used? Who will provide them?  Is there any benefit to further automate the process of your tasks (testing, commissioning)?  What would be the effort implied?  What is the long term strategy with regard to maintainability of testing equipment and related software? Not applicable (for the logistics part)

16 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov Issues & showstoppers Potential showstoppers?  Unexpected number regarding the quantity of irradiated racks. Potential issues?  Readiness of new DYPB element(s) [c.f. 2 previous talks]  9 racks per day: correct rate? (if delay) Are we able to increase it? Like 12/day? Warning:  On today, our request for extension cables (or new cables) has been NOT agreed by both EN/EL & LS1 project leader.  EN/EL is still open to find a compromise  we must provide more precise number & propose solution for partial re-routing  we must go in tunnel during TS#4 and perform an evaluation in “x” sector(s).

17 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov. 2012

18 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov Spare slides

19 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov DYPB Upgrading (EP part) 3 With support of EM section, 1250 units will be produced  Exchange of 1232 Local Protection Units for Dipole Magnets to integrate the enhanced quench heater supervision and adapt to redundant UPS powering. (front view) DQLPU Type ‘A’ (rear view)  Current version With support of EM section, 1300 motherboards will be produced The new DQLPU crate will be assembled in 281 by Ext. Collaborators (AGH contract) (estimation 1hour per crate => 1232 man/h in total)

20 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov Preliminary flowchart concerning the upgrade of crates type DQLPU A. All activities will be performed in building 281. (courtesy: Reiner) Flowcharts for the EP part (1/4)

21 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov (courtesy: Reiner) Flowcharts for the EP part (2/4)

22 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov (courtesy: Reiner) Flowcharts for the EP part (3/4)

23 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov (courtesy: Reiner) Flowcharts for the EP part (4/4)

24 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov  Improvement and Extension Plan for the 4928 Quench Heater P.S. Introduction of a discharge current measurement for each Quench Heater Power Supply through insertion of a new Transducer module (DQLIM) [in replacement of the "Crawford box” ] QRL side Way side Courtesy: Joaquim x DQLIM units will be assembled at Cern.  New redundant power supply (DQLPUR) Required for new DQLPU crate 2600 DQPUR units will be produced DYPB Upgrading (EE part)

25 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov Installation & connection of the electrical systems of DYPB upgrade The new Interface Module will be installed from the top (ballonet system without screws) => access required from above for each individual rack at the moment of installation. All intra-rack cables are already attached to the Interface Module prior to insertion in the yellow rack. The new Interface Module are assembled elsewhere at CERN (support of Betty / FSU contract) Manufacturing of internal cables: WP given also to FSU ·Testing of upcoming Transformers: included in existing AGH contact => update of WP of existing collaboration Estimated installation / connection time: 10 minutes per rack. -Testing must obviously be performed when the upgraded systems of both EP and EE sections are installed, connected and powered. However, the EE systems are already, to a large extend, tested prior to their installation in the yellow rack. Courtesy: Knud

26 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov Flowchart for the EE part (1/3) (courtesy: Knud)

27 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov Flowchart for the EE part (2/3) (courtesy: Knud) In B281: Assembling of the new DQLIM Interface Module. Completing by installation of two DQLPR Power Modules and four DQLCT pulse transformers. Manufacture of new sets of cables. In B281: Individual system testing of the assembled new Modules prior to installation. Participation in the development of a global test facility for EP and EE equipment of the nDYPB system.

28 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov Flowchart for the EE part (2/3) (courtesy: Knud) In B281: Assembling of the new DQLIM Interface Module. Completing by installation of two DQLPR Power Modules and four DQLCT pulse transformers. Manufacture of new sets of cables. In B281: Individual system testing of the assembled new Modules prior to installation. Participation in the development of a global test facility for EP and EE equipment of the nDYPB system.

29 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov Flowchart for the EE part (3/3) (courtesy: Knud)

30 B.Puccio MPE Workshop for LS1 / 22 & 23 Nov Courtesy M. Bernardini DYP B Time slots scheduled for DYPB racks transport