LHC Crab Cavity Engineering Meeting, FNAL RF Power Amplifiers (PA) & Fundamental Power Couplers (FPC) 13-14 December 2012 Eric Montesinos,, CERN, BE-RF-PM.

Slides:



Advertisements
Similar presentations
Higgs Factory, HF2014 at IHEP, 2014 Oct. 101Eiji Kako (KEK, Japan) High Power Couplers for Higgs Factory Eiji KAKO (KEK, Japan)
Advertisements

All experimenters meeting – July 7, 2014 LHC Crab Cavity Overview Tom Nicol – Fermilab All Experimenter’s Meeting July 7, It’s a group effort –
MICE Refurbishment of CERN RF equipment for MICE M. Vretenar, CERN AB/RF.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
RF Measurement Plan Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory January 20, 2011 MICE Video Conference Meeting.
Safety Review: RF Issues Derun Li Absorber Safety Review December 9-10, 2003 Lawrence Berkeley National Laboratory Berkeley, CA
FCC week March 2015 Marriott Georgetown Hotel Superconducting RF: Novel Cavity Concepts & Cryomodules Fundamental Power Coupler (FPC) Eric Montesinos,
DESIGN OF A HIGH POWER TEST STAND FOR ESS SPOKE CAVITIES
Eric Montesinos Challenges in
Possible Assembly and Test of the Crab cryomodule in SM18 at CERN P. Maesen LHC Crab Cav meeting, 17 Sep’ 09 LHC-CC09Cryomodule Assembly & Test Stand.
Possible proposed designs Part I : general considerations SPL power coupler March 16, 2010Eric Montesinos / CERN-BE-RF-SR.
Meeting summary (so far, Monday morning) and comments Tom Peterson, Camille Ginsburg (FNAL), Alex Ratti (LBNL) Crab Cavity Meeting, CERN, 1-6 Aug 2013.
Ofelia Capatina on behalf of the CERN specification team
SPL cryo-module conceptual design review Cavity, helium vessel and tuner assembly N. Valverde, G. Arnau, S. Atieh, I. Aviles, O. Capatina, M. Esposito,
Status of 325MHz coupler S. Kazakov 11/29/ MHz coupler structure.
SPIE Conference - Photonics Applications in Industry and Research, Warsaw, 30 August, The RF Power Coupler Development Program at LAL-Orsay and.
Coupler without copper coating S. Kazakov 11/13/2013.
Status of RFCC-Module Development Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory MICE Collaboration Meeting at INFN-LNF, Frascati,
201 MHz NC RF Cavity R&D for Muon Cooling Channels
RF power & FPC status Eric Montesinos, CERN BE-RF on behalf of all people involved, great thanks to all of them !
201 MHz Cavity Status and Test Plans at MTA MICE Collaboration Meeting at RAL, UK October 22 ~ 24, 2005 Derun Li Center for Beam Physics Lawrence Berkeley.
Clustered Surface RF Production Scheme Chris Adolphsen Chris Nantista SLAC.
February 17-18, 2010 R&D ERL Alex Zaltsman R&D ERL High Power RF Systems Alex Zaltsman February 17-18, 2010 High Power RF Systems.
Andrew Moss ASTeC CM32 9t h February 2012 RAL MICE RF System.
WORKSHOP SUMMARY. 2 Workshop summary CWRF08: finally we have: 54 ~10 33 talks Number of participants rose by almost 6dB.
Recent Fundamental RF Power Coupler developments at CERN First SLHiPP meeting CERN, Geneva, 8 & 9 December 2011.
PSB dump: proposal of a new design EN – STI technical meeting on Booster dumps Friday 11 May 2012 BE Auditorium Prevessin Alba SARRIÓ MARTÍNEZ.
1.3GHz Input Coupler for ILC
LCWS13, November 2013 At the University of Tokyo W.–D. Möller Status of the TTF3 RF Power Coupler.
LCLS-II FPC Aluminum Waveguide Box Karen Fant with work done by Chris Nantista and Ken Premo 6/24/2015.
Ding Sun and David Wildman Fermilab Accelerator Advisory Committee
Renovation of the 200 MHz RF system LLRF issues. Cavities redistribution 26 October th LIU-SPS Coordination Meeting 2  2011 : 4 cavities 2 x 4.
20 years of high average Fundamental Power Coupler designs at CERN CWRF workshop 2014, Trieste Eric Montesinos, CERN-RF, on behalf of many colleagues CWRF.
Eric Montesinos - CERN - First SPL collaboration meeting - CERN December 11th 2008 First SPL collaboration meeting Experience with the LHC Main power Coupler.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
New plans for high power RF tests places at CERN O. Brunner BE/RF/KS – January ‘10.
ALBA RF Amplifiers based on IOTs CWRF08 - CERN, March 2008 Michel Langlois & Paco Sanchez 1 Michel Langlois & Paco Sanchez.
LIU-SPS RF Power upgrade | 09 December 2015.
 =1 cavity: parameters Dimensions for cavity fabrication before any chemical polishing and at room Temp. outer ½ cell pick-up side inner ½ cells outer.
MICE RF System Overview Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory Andrew Moss STFC Daresbury Laboratory MICE UK.
Cryostat & LHC Tunnel Slava Yakovlev on behalf of the FNAL team: Nikolay Solyak, Tom Peterson, Ivan Gonin, and Timergali Khabibouline The 6 th LHC-CC webex.
LHC Cryostat evaluation Nikolay Solyak Thanks Rama Calaga, Tom Peterson, Slava Yakovlev, Ivan Gonin C11 workshop. FNAL, Oct 27-28, 2008.
SPL waveguide distribution system Components, configurations, potential problems D. Valuch, E. Ciapala, O. Brunner CERN AB/RF SPL collaboration meeting.
High power RF tests places at CERN O. Brunner, CERN 4th SPL Collaboration Meeting jointly with ESS.
HiLumi-LHC/LARP Crab Cavity System External Review – May Work partly supported by the EU FP7 HiLumi LHC grant agreement No and by the.
Slide: Sixth CW and High Average Power RF Workshop Cavity combiners for transistor amplifiers M.Langlois, J.Jacob, J.M. Mercier.
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 15 th August 2012.
Preparation procedure and RF processining of cERL-ML power coupler at KEK Hiroshi Sakai, Takaaki Furuya, Masato Sato, Kenji Shinoe, Kensei Umemori, Kazuhiro.
FREIA: HIGH POWER TEST STAND Rutambhara Yogi & FREIA Group ESS RF Group Unit Leader for Spoke Power and RF Distribution FREIA Group Unit Leader, Uppsala.
Power couplers Timergali Khabiboulline (FNAL) FNAL-LBNL meeting on NGLS April 13, 2012.
201 MHz Cavity Plans Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory February 11, 2011 MAP Friday Video Conference Meeting.
RFQ Installation Status 10/27/2015 October 27, 2015 Jim Steimel & Curtis Baffes.
HiLumi-LHC/LARP Crab Cavity System External Review 5-6 May 2014, BNL SPS - RF Power and Coupler status Erk Jensen, Eric Montesinos, CERN BE-RF.
RFQ coupler S. Kazakov 07/28/2015. Requirements: Coupler requirements Expected problems: Heating (loop, ceramic window, etc.) Multipactor Solutions: Appropriate.
SPS High Energy LSS5 Thermal contact & cooling aspects
Infrastructure status and plans at CERN 1) W. Weingarten/CERN TTC Milano 28 February - 3 March W. Weingarten/CERN 1)Most of the slides are based.
DESIGN STUDY November 28 th - 30 th 2005First EURISOL Design Study TOWN MEETING High Power RF Amplifiers Development at LNL Fabio Scarpa - INFN LNL.
CERN SPL Fundamental Power Coupler Progress report SLHiPP-4 meeting, 2014, CERN, Geneva Eric Montesinos, CERN-RF SLHiPP-4, May, CERN, Geneva Eric.
TDR guideline discussion on Cavity Integration
CERN – Zanon discussions
An X-band system for phase space linearisation on CLARA
FPC & HPRF status Couplers mounting (FPC, HOMS & FA)
12 GHz High Power RF components requirements for CEA activities
SNS Fundamental Power Coupler History
CERN SPL Fundamental Power Coupler Progress report
CEPC Input Coupler Discuss 6th IHEP-KEK SCRF Collaboration Meeting
V. Veshcherevich Cornell University
Breakout Session SC3 – Undulator
Cryomodule Design for CW Operation 3.9 GHz considerations
IOT operation in the SPS Long term experience TWC 800 MHz
Presentation transcript:

LHC Crab Cavity Engineering Meeting, FNAL RF Power Amplifiers (PA) & Fundamental Power Couplers (FPC) December 2012 Eric Montesinos,, CERN, BE-RF-PM

Contents SPS Power Amplifiers : ▫SPS Power system overview ▫Finals ▫SPS available areas for PA ▫Transmission lines ▫Power supplies & peripherals ▫Drivers Conclusion ▫Power Amplifiers ▫Fundamental Power Couplers Fundamental Power couplers : ▫LHC-CC10, Executive Summary ▫Schedule ▫Air cooled couplers ▫LHC Cylindrical window ▫SPS Disk window ▫Monobloc ‘Plug & Play’ Waveguide ▫Double walled Tube (DT) ▫Common FPC platform ▫4Rod FPC integration ▫Double FPC Ridge integration ▫Quarter FPC Wave integration ▫Test box ▫Test areas December 2012LHC Crab Cavity Engineering Meeting 2

SPS Power system overview For the tests in the SPS we will have one RF power system per one new crab cavity : ▫Driver ▫Final ▫Transmission lines ▫Fundamental Power Coupler (FPC) Two power systems are to be built : December 2012LHC Crab Cavity Engineering Meeting 3 LLRF Driver Final Cryo module FPC Transmission lines

Finals During LEP time ( ), four 352 MHz SC Cavities were in operation in the SPS Specially designed tetrode amplifiers were developed at CERN to feed these cavities In 1998, a prototype 400 MHz cavity has been tested in the SPS It was powered with a 352 MHz amplifier modified to operate at 400 MHz Maximum output power was 40 kW cw The main idea is to re-use this amplifier and to modify three 352 MHz The goal is to obtain 50 kW cw (instead 60 kW cw specified) December 2012LHC Crab Cavity Engineering Meeting 4 SPS 400 MHz Tetrode Amplifier

SPS available areas for PA Only available area for cavities is ‘Coldex’ alcove Possible locations for Finals are : ▫Coldex ▫ECX4 cavern ▫BA4 surface building Possible locations for Drivers & LLRF are, because of radiations: ▫ECX4 cavern ▫BA4 surface building ECX4 (cavern) Coldex LSS4 Lift BA4 (surface building) Top view ECX4 (cavern) LSS4 Coldex Side view December 2012LHC Crab Cavity Engineering Meeting 5

SPS available areas for PA Only available area for cavities is ‘Coldex’ alcove Possible locations for Finals are : ▫Coldex ▫ECX4 cavern ▫BA4 surface building Possible locations for Drivers & LLRF are, because of radiations: ▫ECX4 cavern ▫BA4 surface building Distances : ▫ECX4 to Coldex = 75 m ▫BA4 to Coldex = 100 m ECX4 (cavern) Coldex LSS4 Lift BA4 (surface building) Top view ECX4 (cavern) LSS4 Coldex Side view 75 m 100 m December 2012LHC Crab Cavity Engineering Meeting 6

Transmission lines For 50 kW cw at 400 MHz, Waveguides (WG) would be WR2300 half-height WG cannot be installed between : ▫ECX4 and Coldex (ex-SWC100) as there is not enough space around ▫BA4 and Coldex as there is not enough space in the access gallery Another option would be the use of a low loss 6-1/8” flexwell coaxial cable : 400 MHz = 0.4 dB / 100 m ▫Insertion losses connectors = 2 x 0.1 dB ▫Amplifier output adaptor = 0.2 dB ▫~ dB : 50 kW -> 60 kW ▫Minimum Bending Radius = 1 meter December 2012LHC Crab Cavity Engineering Meeting 7 Tunnel between Coldex (left) and ECX4 (right) (ex-SWC100)

Transmission lines Having the Finals close to the cavities is therefore the best option Full power will be delivered to cavity through Waveguide as it was done with 352 MHz cavities Would then have low loss 1-5/8” flexwell coaxial cable : 400 MHz = 1.3 dB / 100 m ▫Insertion loss of connectors = 2 x 0.1 dB ▫~ 1.5 dB losses ▫Final gain = 14 dB ▫Drivers : 2.8 kW ▫Minimum Bending Radius = 0.2 meter SPS 352 MHz SCC during the 90’s December 2012LHC Crab Cavity Engineering Meeting 8

Power supplies and peripherals Anode HV power supplies, other power supplies, controls, LLRF cannot sit in the same tunnel area, not enough space, radiation concerns Two options are looked at : ▫BA4 surface building ▫ECX4 underground cavern Choice will mainly be driven by free cable trays and infrastructure availability Other peripherals will have to be close to the Finals : ▫Air blower ▫De-ionized water should also be available ▫HV Filtering Box (due to the distance between Finals and their HVPS) December 2012LHC Crab Cavity Engineering Meeting 9 Four HVPS for SPS 352 MHz tetrode amplifiers Air blower and HV filtering box close to the tetrode amplifier

Drivers 2.8 kW will be needed With some margin : 6 x 500 W or 8 x 400 W Off the shelf modules from several vendors (500 W : 6 k€ to 35 k€) Combining system will be built by CERN (λ/4, n to 1) There will be an individual circulator per module These will be located ECA4 or BA4 close to LLRF system 0 dBm From LLRF 2.5 kW to Final Drivers option with 6 x 500 W SSA December 2012LHC Crab Cavity Engineering Meeting 10

Fundamental Power Coupler SUMMARY OF THE 4TH “LHC-CC10” CRAB CAVITY WORKSHOP, EXECUTIVE SUMMARY : … Also power couplers should be tested Each cavity needed a special power coupler, but a common platform for power coupler development is highly desirable to focus the R&D … December 2012LHC Crab Cavity Engineering Meeting 11

Schedule Cavities to be installed in SPS in December 2015 Cryostat fully tested Q Cryostat fully dressed Q2-015 Couplers available for cryostat Q Couplers RF processed 50 kW SW cw all phases Q Couplers assembled in clean room Q onto test box Special processes FPC + Test Box (Cleaning, Brazing, EB welding, Gold plating, Ti coating) completed Q All couplers + Test Box parts machined Q All raw material delivered Q All raw material ordered Q (common) Coupler design completed February 2013 (+ Test Box !) December 2012LHC Crab Cavity Engineering Meeting 12 February

Air cooled Coupler Very tight schedule No time for a ‘from the scratch’ design CERN’s rule : ▫No jointing with direct contact between water and vacuum to allow vacuum leak detection in case of failure  If water cooled, Body and Antenna will be machined from single massive copper block without Brazing neither Welding or they will have to be air cooled December 2012LHC Crab Cavity Engineering Meeting 13

LHC window Design of the window has taken 7 years, from 1996 to 2002 Very powerful window : ▫575 kW full 400 MHz with LHC couplers ▫1 MW TW and 575 kW SW all 704 MHz with SPL prototype couplers December 2012LHC Crab Cavity Engineering Meeting 14 LHC window with beginning of crack ¼ LHC windowLHC window

In operation with 16 cavities in LHC Following ESRF-LEP window defects (5), has also been integrated in new ESRF & new APS coupler designs Has been 352 MHz up to 300kW cw at ESRF and 100 kW cw at APS (still on-going) Both ESRF and APS designs with H loop A third new redesign based on this ceramic is also on-going with E antenna for SOLEIL LHC Power couplers ESRF (H loop) Power coupler December 2012LHC Crab Cavity Engineering Meeting 15

LHC window crack at APS H loop : the only ceramic breakage due to stress into the ceramic Mechanical stress while connecting WG to the coupler or thermal stress during bake out at APS premises ? APS (H loop) Broken ceramic December 2012LHC Crab Cavity Engineering Meeting 16

Disk Window Design of the window for SPS power load, but designed as a coupler window : ▫Titanium Flange outer line ▫Metalized on its edge disk Ceramic ▫Copper tube inner line Very powerful window : ▫500 kW 200 MHz with SPS loads ▫1 MW TW and 1 MW SW all 704 MHz with SPL prototype couplers Spring RF contact SPS Window: very simple brazing process Air cane December 2012LHC Crab Cavity Engineering Meeting 17

Crab Cavity FPC window We do not need these power levels (Crab Cavities 50 kW cw TW + 50 kW cw SW all phases) Nevertheless, these two ceramics designs have proven to be powerful and reliable (SPS & LHC) CERN very well masters both brazing processes Few LHC ceramics are already available Pretty quick to have disk ceramic available if within the same range of dimensions (100 mm external diameter or smaller) December 2012LHC Crab Cavity Engineering Meeting 18

Mono bloc ‘plug and play’ waveguide ‘Plug and Play’ waveguide with matching step and DC capacitor included : 1.Connect the waveguide to the body line 2.Insert the contacts ring (DC biasing capacitor) 3.Final assembly of air cooling system (or water cooling) No doorknob, reduced height, with no mechanical stress to the ceramic Successfully tested with ESRF, APS and SPL couplers December 2012LHC Crab Cavity Engineering Meeting 19

Double walled Tube (DT) As 50 kW cw are requested, we plan to have a DT to connect FPC to cavity DT are copper plated, and it is never a simple process, copper peeling -> 1 year delay in SPL coupler production Regarding schedule, we would prefer to design only one common DT This means a common outer transmission line for all FPC Preferably a very simple straight tube December 2012LHC Crab Cavity Engineering Meeting 20 SPL Double walled Tube (copper peeling)

Common FPC Platform : SPL example Same Double Walled Tube (Outer line of a coaxial transmission Line) With same interface flange To cavity and cryomodule Same Waveguide with integrated matching step (instead of a doorknob) And same DC capacitor Cylindrical ceramic window Coaxial disk ceramic window December 2012LHC Crab Cavity Engineering Meeting 21

4rod FPC Both FPC proposals seem quite easy to be integrated with respect to the cryomodule Be on top of the cavity Input coupler port 40 mm December 2012LHC Crab Cavity Engineering Meeting 22

Double Ridge FPC A bit more complex with respect to the proposed angle regarding beam pipe Can this angle be increased ? Need an antenna to short circuit minimal distance (d) and with some free space room regarding beam pipe Input coupler port 36 mm What about cryomodule DT integration at the end side ? December 2012LHC Crab Cavity Engineering Meeting 23 Conflict between DT and Vacuum beam pipe FPC port α Sizing is more a GHz WG than 400 MHz WG d

Quarter Wave FPC H loop as with ESRF & APS is possible (nevertheless, remind that the only ceramic breakage was with that configuration) Input coupler 40 mm with a ‘Triaxial’ line E antenna preferable as no stress given to the ceramic, but in that case what about E coupling axis and again beam pipe vs antenna axis compatibility ? December 2012LHC Crab Cavity Engineering Meeting 24

Common Crab Cavity FPC Platform We propose to stick to these design parameters : ▫LHC window or Disk window ▫Waveguide line to coaxial antenna ▫Plug and play waveguide ▫DC biasing (if E antenna) ▫Preferably E antenna (no stress to the ceramic) ▫Same simple straight pipe DT ▫If possible 50 Ω antenna (easier for mock-up measurements) Specifications from Rama : ▫cavity FPC port diameter : 40 mm / 36 mm / 40 mm ▫DT : 40 mm ▫Inner line : 17 mm (two tubes, cooling inlet (4/6) + cooling outlet (13/17)) Can we increase the DT diameter ? ▫Incompatibility between the sizes and power level requested ▫Should be the main topic at the FPC dinner table tonight December 2012LHC Crab Cavity Engineering Meeting 25

Common Crab Cavity FPC Platform We propose to stick to these design parameters : ▫LHC window or Disk window ▫Waveguide line to coaxial antenna ▫Plug and play waveguide ▫DC biasing (if E antenna) ▫Preferably E antenna (no stress to the ceramic) ▫Same simple straight pipe DT ▫If possible 50 Ω antenna (easier for mock-up measurements) Specifications from Rama : ▫cavity FPC port diameter : 40 mm / 36 mm / 40 mm ▫DT : 40 mm ▫Inner line : 17 mm (two tubes, cooling inlet (4/6) + cooling outlet (13/17)) Can we increase the DT diameter ? ▫Incompatibility between the sizes and power level requested ▫Should be the main topic at the FPC dinner table tonight ! December 2012LHC Crab Cavity Engineering Meeting 26 Inner cooling tube FPC RF power amplifier

Test box Almost the same amount of work as to design a coupler As well as coupler, must be prepared in clean room Not yet simulated, but probably based on the SPL principle : ▫Two covers ▫All vacuum flanges machined all- in-one ▫Self supporting ▫Easier for copper coating SPL Test box assembly in DESY clean room SPL Test box December 2012LHC Crab Cavity Engineering Meeting 27

Test area(s) We are refurbishing our test area to be able to test all amplifier chain as well as to perform coupler processing on test box (TW & SW all phases) Goal is to be ready by end 2014 with tested couplers ! Then once couplers will be delivered for clean room mounting, all these will be moved to SM18 for fully dressed cavity test at high power prior to installation in the SPS FPC conditioning process : Vacuum controlled power generator Starts with very short pulses Long repetition time Ramp from low power to full power December 2012LHC Crab Cavity Engineering Meeting 28

Conclusion : Power Amplifiers Tight schedule, but for SPS, Power system seems not to be a trouble maker Power system will be very similar to the one we already operated at this exact location 15 years ago SSA Drivers are available from vendors Cable work will be prepared during LS1 (not installed as incompatible with Coldex) As we will need amplifiers for FPC tests on test box & on cavity, sooner than we need them in the SPS, we will be ready on time December 2012LHC Crab Cavity Engineering Meeting 29

Conclusion : FPC Common platform has to be understood as a quite ‘large’ proposal range : ▫LHC ceramic ▫Disk ceramic, various sizes ▫H loop possible ▫E antenna preferred However, with respect to the so tight schedule, parameters must be decided and frozen very quickly (tonight ? coming weeks the latest) As design will not be from the scratch, we should be able to have the design ready soon after parameters have been defined We will then be able to launch raw material purchasing needed for couplers, as well as material needed for test box December 2012LHC Crab Cavity Engineering Meeting 30

Thank you very much for your attention APS ▫Ali Nassiri, Doug Horan, Gian Tenko, Dave Brubenker, and team CEA : ▫Stephane Chel, Guillaume Devanz, Michel Desmond, and team DESY : ▫Wolf-dietrich Moeller, Axel Matthaisen, Birte Van der Horst, and team ESRF : ▫Jorn Jacob, Vincent Serriere, Jean-Maurice Mercier, and team SRF 2003 DESY, Brian Rusnak : CAS 2010, Wolf-Dietrich Möller : /Lectures/Moeller.pdf /Lectures/Moeller.pdf CERN Mechanical & Material Engineering group : ▫Francesco Bertinelli, Serge Mathot, Agostino Vacca, Thierry Tardy, Thierry Calamand, Thierry Renaglia, Ofelia Capatina, Marc Polini, Laurent Deparis, Philippe Frichot, Jean-Marie Geisser, Jean-Marc Malzacker, Pierre Moyret, Alain Stadler, and team Vacuum, Surface & Coating group : ▫Miguel Jimenez, Sergio Calatroni, Wilhelmus Vollenberg, Marina Malabaila, Nicolas Zelko, and team Magnets, Superconductors & Cryostats group : ▫Vittorio Parma, Arnaud Van de Craene, Rossana Bonomi, and team RF group : ▫Sebastien Calvo, Antoine Boucherie, all FSU-AB03 members

‘Moveable’ cavities In addition, cavities must be able to mechanically be removed from beam pipes An additional reason for having the amplifiers close to the cavity Fin al Cryomodul e WG FPC December 2012LHC Crab Cavity Engineering Meeting 33

‘Moveable’ cavities In addition, cavities must be able to mechanically be removed from beam pipes An additional reason for having the amplifiers close to the cavity Fin al Cryomodul e WG FPC December 2012LHC Crab Cavity Engineering Meeting 34