THEMIS Instrument CDR 1 UCB, April 19-20, 2004 EFI Preamp Sensor G.T. Delory, A. Hull, D. Schickele, J. Bonnell & The EFI Team University of California.

Slides:



Advertisements
Similar presentations
THEMIS Instrument PDRRob Duck 1 UCB, October 15-16, 2003 EFI Axial Booms (AXB) Preliminary Design Review Rob Duck Mechanical Engineering Department and.
Advertisements

THEMIS Instrument CDR 1 UCB, March 24-25, 2004 EFI AXIAL BOOMS (“AXB”) Critical Design Review Rob Duck Mechanical Engineering Department Space Sciences.
Science Specification Table 12 keV keV for neutral particles 40.5 cm 2 image plane Electronic Noise 3 keV FWHM Proton Dead Layer
THEMIS INSTRUMENT PER 1 UCB, May, 2005 EMC / Mag Instrument Test Plan & Results Michael Ludlam University of California - Berkeley.
SPP FIELDS V5 Antenna Mechanical Peer Review David Glaser, Paul Turin, Jeremy McCauley, John Bonnell, Dennis Seitz SSL UCB 7/17/13.
SPP FIELDS V5 Antenna Mechanical Peer Review Draft 2 David Glaser, Paul Turin, Jeremy McCauley, John Bonnell, Dennis Seitz SSL UCB 7/17/13.
THEMIS Mission CDRInstrument I&T 1 UCB, June , 2004 Instrument Integration and Test Rick Sterling / Sharon Jelinsky University of California – Berkeley.
THEMIS Instrument CDR 1 UCB, April 19-20, 2004 Integration and Test Critical Design Review Rick Sterling University of California – Berkeley Thm_CDR_IT_Revc.
SVX4 chip 4 SVX4 chips hybrid 4 chips hybridSilicon sensors Front side Back side Hybrid data with calibration charge injection for some channels IEEE Nuclear.
SPP FIELDS DFB Quarterly June 2014 Solar Probe Plus FIELDS Instrument Quarterly Digital Fields Board 1.
3-4 Sept. 2008EFW INST+SOC PDR141 Electric Field and Waves (EFW) Spin Plane Boom (SPB) Gregory Dalton Space Sciences Laboratory University of California.
Selda HeavnerFIELDS iPDR – Antenna Electronics Board Solar Probe Plus FIELDS Instrument PDR Antenna Electronics Board Selda S. Heavner U.C. Berkeley
THEMIS-SCM THM – SCM – CDR – 08-April-2004 in Velizy
LPW Preamp/Sensor Overview Greg Delory, LPW Co-I MAVEN PFP Pre-CDR Peer Review May 10, 2011.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW I-PER 21 January EFW Test Plan Michael Ludlam Space Sciences Laboratory.
THEMIS Instrument CDR 1 UCB, April , 2004 EFI Axial Booms Thermal Christopher Smith Thermal Engineer
MPSREFI- 1 UCB, Oct 26, 2006 THEMIS MISSION PRE-SHIP REVIEW “Our Gateway to the Cape…” The Electric Field Instrument (EFI) John Bonnell University of California.
THEMIS Instrument CDR 1 UCB, April 19-20, 2004 THEMIS Electric Field Instrument Fabrication, Integration, and Testing.
THEMIS Engineering Peer Review 1 UCB, October 15-16, 2003 Electric Field Instrument (EFI) Electrical Fabrication and Test.
THEMIS Mission CDR -UCB, June 14-18, 2004 Search Coil Magnetometer (SCM) MCDR Alain Roux, CETP-Velizy Co-i: O.Le Contel Technical Manager: B.de la Porte*
THEMIS Mission PDR/CAR 1 UCB, November 12-14, 2003 Search Coil Magnetometer (SCM) Mission PDR/CAR Alain Roux CETP-Velizy Co-i: O.Le Contel Technical Manager:
THEMIS Instrument CDR 1 UCB, April 19-20, 2004 Boom Electronics Board (BEB) Engineering Peer Review Apr. 20, 2004 Hilary Richard.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW Boom PER 30 June RBSP EFW Spin Plane Booms Greg Dalton Space Sciences.
THEMIS Instrument PDRParts- 1 UCB, October 15-16, 2003 Parts Requirements Preliminary Design Review Jorg Fischer University of California - Berkeley.
THEMIS FGM CDR Peer ReviewBerlin, April 6, 2004 THEMIS FGM Engineering Peer Review SC Integration and Test Ellen Taylor University of California - Berkeley.
THEMIS SCM CDR MC VASSAL - 3D PLUS CETP 04/08/ Preamplifiers in 3D Technology EM manufacturing Part list and component Lot Acceptance Tests FM manufacturing.
THEMIS Instrument CDR 1 UCB, April 19-20, 2004 Boom Electronics Board (BEB) Engineering Peer Review Apr. 20, 2004 Hilary Richard.
FM1 Instrument Suite Pre-Ship Review (PSR)Thermal-1UCB, September 21, 2005 THEMIS FM1 INSTRUMENT SUITE PRE-SHIP REVIEW (PSR) THERMAL Chris Smith University.
CubeSat for Ions, Neutrals, Electrons and Magnetic Fields PI Robert Lin, SSL Project Manager Thomas Immel, SSL Systems Engineer Jerry Kim, SSL Mechanical.
THEMIS Mission PDR/CAR 1 UCB, November 12-14, 2003 Instrument Integration & Test Dr. Ellen Taylor University of California - Berkeley.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW I-PER 21 January EFW Overview and Status Keith Goetz University of Minnesota.
Preamps (PRE) and Sensors Rachel Hochman John Bonnell Space Sciences Laboratory University of California, Berkeley CDR September 30-October1, 2009 RBSP-EFW.
THEMIS Instrument FM2/FM3 PEREnvironments- 1 Teleconference 8/30/2005 THEMIS Instrument FM2/3 Pre-Environmental Review Environments Jeremy McCauley University.
STEREO IMPACT Critical Design Review 2002 November 20,21,22 Acuña1 MAGNETOMETER (MAG) M. H. Acuña NASA/GSFC Laboratory for Extraterrestrial Physics.
THEMIS SUITE PRE-ENVIRONMENTAL REVIEW 1 UCB May 2, 2005 THEMIS Pre-Environmental Review Instrument Verification Overview Ellen Taylor University of California.
Solar Probe Plus Fluxgate Magnetometer QSR – Oct SPF MAG Quarterly Report – Oct 2014 The MAG EM1 (EQM) (board and frame at right) was successfully.
THEMIS INSTRUMENT CDR Peer ReviewSYSTEM- 1 UCB, April 19, 2004 TITLE: Test Flow RFA CODE: UCB-10 REQUESTED BY: Preble SPECIFIC REQUEST: We recommend that.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes LVPS+PCB Peter BergRBSP/EFW CDR /30-10/1 IDPU LVPS AND PCB Critical Design Review.
AEP Mechanical and Power System H. Heetderks. CDR July, 2001NCKU UCB Tohoku AEP Mechanical and Power System H. Heetderks 2 AEP Mechanical Design System.
THEMIS Instrument PDR 1 UCB, April 19-20, 2004 Spin Plane and Axial Boom Preamps & Sensor Cable Fabrication Critical Design Review Daniel Schickele University.
FIELDS iCDR – RFS Analog Dennis Seitz 1 Solar Probe Plus FIELDS Instrument CDR RFS Analog Dennis N. Seitz UC Berkeley SSL
SWT Overview 1 UCB, Nov15/16, 2006 THEMIS SCIENCE WORKING TEAM MEETING Mission Overview Peter R. Harvey Project Manager University of California - Berkeley.
THEMIS MISSION PDRINSTRUMENT OVERVIEW- 1 UCB, November, 2003 THEMIS INSTRUMENT PAYLOAD SYSTEM OVERVIEW Dr. Ellen Taylor University of California - Berkeley.
THEMIS Engineering Peer Review 1 UCB, October 15-16, 2003 Electric Field Instrument (EFI) Operational Concept.
FGM peer CDR FGS - 1 Berlin, April 6, 2004 FGS Mechanical Design Hans-Ulrich Auster Institut für Geophysik und Meteorologie TU Braunschweig.
THEMIS Instrument Pre-Environmental Review 1 UCB 5/02/2005 THEMIS Instrument Pre-Environmental Review Project Status May 2, 2005 Peter R. Harvey THEMIS.
THEMIS Engineering Peer Review 1 UCB, October 15-16, 2003 Electric Field Instrument (EFI) Engineering Peer Review Overview Dr. John W. Bonnell and the.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW CDR /30-10/1 Thermal Design Christopher Smith RBSP Thermal Engineer Space.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW I-PER 21 January EFW Systems Engineering Michael Ludlam Space Sciences.
Pre-Ship IIRT Telecon EFI 1 Telecon, Dec. 5, 2006 THEMIS Pre-Ship IIRT Telecon EFI Preamp Current Consumption John Bonnell EFI Lead University of California.
Preamps (PRE) and Sensors Rachel Hochman John Bonnell Space Sciences Laboratory University of California, Berkeley CDR September 30-October1, 2009 RBSP-EFW.
Status 1 5/07/08 UCB RBSP EFW STATUS 5/07/08. Status 2 5/07/08 UCB Agenda Project Stuff Monthly Report Submitted Schedule Submitted  Milestones Upcoming.
1 PFP IPDR 2010/6/ Particles and Fields Package (PFP) Instrument Preliminary Design Review Integration & Test David Curtis, PF Package Manager.
THEMIS-SCM SCM – OVERALL RESSOURCES – STATUS versus REQUIREMENTS ItemSpecificationStatus Sensor Bandwith Sensor Sensitivity Up to 4 kHz 1 pT/√Hz at 10.
BonnellFIELDS iCDR – AEB Solar Probe Plus FIELDS Instrument CDR Antenna Electronics Board AEB J. Bonnell, D. Seitz UC Berkeley, SSL
Boom Electronics Board (BEB) Engineering Peer Review Oct
Particles and Fields Package (PFP) SWEA Pre-CDR Peer Review
Gayle K. Martin November 14, 2016
SPF MAG Quarterly Report – Feb 2015
Spacecraft Interface and I&T
(EFW Systems Engineer) University of California, Berkeley
Electric Field and Waves Instrument (EFW)
Mars Atmosphere and Volatile EvolutioN (MAVEN) Mission
Search Coil Magnetometer (SCM) CDR/Peer review CETP-Velizy
Solar Probe Plus – FIELDS Verification Instrument mini-PER (V5)
Boom Electronics Board (BEB)
Low Voltage Power Supply & Power Controller Board
THEMIS Electric Field Instrument
University of California, Berkeley
GLAST Large Area Telescope
Presentation transcript:

THEMIS Instrument CDR 1 UCB, April 19-20, 2004 EFI Preamp Sensor G.T. Delory, A. Hull, D. Schickele, J. Bonnell & The EFI Team University of California - Berkeley

THEMIS Instrument CDR 2 UCB, April 19-20, 2004 Overview Evolution of the CLUSTER-II Design

THEMIS Instrument CDR 3 UCB, April 19-20, 2004 Requirements & Specs Measurement Performance Electric Fields DC kHz DC: Coupling impedances up to 10,000 M . AC: Input Capacitance = 8 pF Radial C coupling ~13 pF, Axial C coupling ~6.5 pF Environmental Requirements  C operating temp; survive 12 cycles to  132 C. ~750 kRAD/year behind 1 mm of Al

THEMIS Instrument CDR 4 UCB, April 19-20, 2004 Electrical Performance

THEMIS Instrument CDR 5 UCB, April 19-20, 2004 Block Diagram Spin-Plane Boom (SPB) Unit Sub Axial Boom (AXB) Unit 3m thin wire, d ~10 mil sphere, d ~8 cm Preamp Housing, d ~2.3 cm 3m Preamp Housing, d ~2.3 cm 1 m

THEMIS Instrument CDR 6 UCB, April 19-20, 2004 Electrical Diagram

THEMIS Instrument CDR 7 UCB, April 19-20, 2004 Layout Engineering Model Layout

THEMIS Instrument CDR 8 UCB, April 19-20, 2004 Mechanical & Thermal OP15 (TO-99 pkg) Mechanical Tantalum rad shield Socket Spring contact Connector shell Usher (positive bias) Guard (negative bias) PCBPin Spacecraft Wire/sphere

THEMIS Instrument CDR 9 UCB, April 19-20, 2004 Layout – Cont’d

THEMIS Instrument CDR 10 UCB, April 19-20, 2004 Mass, Power, & Thermal Mass 40 g each unit (can be lowered by using Al instead of brass for top piece) Power <70 mW per Preamp (allocated 85 mW) Thermal Must survive  132 C for ~12 cycles (3 hr eclipse) Nominal operating T of Dag-coated surface ~50 C

THEMIS Instrument CDR 11 UCB, April 19-20, 2004 Parts Op-Amp OP-15AJ MIL-STD 883, CRRES Heritage Meets radiation requirement Requires further thermal screening (hermetic integrity, pin- pull test, die-bond inspection) Passive Components Meet all requirements except thermal Thermal screening will occur using subset of tests for OP-15

THEMIS Instrument CDR 12 UCB, April 19-20, 2004 Schedule April –Vibration tests –Cable/connector/EM assembly May –Thermal tests to  132 C –Integration of preamp EM with BEB EM, full end-to-end EFI system test June –Additional parts screening (outside facility) –Destructive testing/inspection of fully assembled unit at lowest thermal predict July –Implement any design modes necessary for qualification issues –Final layout, loading, and electrical testing –System level testing: Preamp/Boom/BEB signal chain

THEMIS Instrument CDR 13 UCB, April 19-20, 2004 Schedule – Cont’d Aug –Begin flight unit fabrication Sep –1 st Flight Unit Delivery

THEMIS Instrument CDR 14 UCB, April 19-20, 2004 Issues THERMAL Plan: Qualify preamp as complete unit in parallel with individual parts qualification program Develop several alternative strategies to mitigate potential issues/failures at  132 C –Ceramic board –Hybrid construction Consider addition of temperature sensor to 1 SPB and 1 AXB sensor/spacecraft Similar systems regularly undergo temperature swings down to ~  100 C (i.e., CLUSTER II). We will verify this for the THEMIS design