Near-term schedule Scott Horner. Background MCCS software engineering build #3 was delivered in June and tested by the SIL team in early July A number.

Slides:



Advertisements
Similar presentations
East Hampton High School July 2013 – July 2014 Design Phases.
Advertisements

SOFIA SOFIA Science Steering Committee Meeting Palmdale, Feb 18, 2010 Dietmar Lilienthal / Alois Himmes.
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
Science Instrument Requirements Document Reorganization Scott Horner SITR – 19 February 2010.
SOFIA SSSC Program Status Robert Meyer Program Manager February 18, 2010.
GLAST LAT ProjectLAT Engineering Meeting, April 1, 2003 GLAST Large Area Telescope: Performance & Safety Assurance Darren S. Marsh Stanford Linear Accelerator.
SOFIA SSSC Program Status Robert Meyer Program Manager September 29, 2009.
GLAST LAT ProjectDOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001 Scott Williams 1 GLAST Large Area Telescope: Instrument Operations Center Scott.
GLAST LAT Project ISOC Peer Review - March 2, 2004 Document: LAT-PR Section 2.3 Verification and Validation 1 Gamma-ray Large Area Space Telescope.
GLAST LAT ProjectISOC CDR, 4 August 2004 Document: LAT-PR-04500Section 4.11 GLAST Large Area Telescope: Instrument Science Operations Center CDR Section.
NGAO Team Meeting Management Peter Wizinowich May 26, 2009.
PALM-3000 Instrument commissioning schedule Antonin Bouchez Team Meeting #7 27 February, 2008.
1 Universities Space Research Association SOFIA Program Options SSSC 18 February 2010 Mina Cappuccio SOFIA Science Project Manager NASA Ames Research Center.
SOFIA Program Overview CSTA Eddie Zavala Deputy Program Manager October 21, 2011 SS1 Orion Image.
SOFIA — The Observatory open cavity (door not shown) TELESCOPE pressure bulkhead scientific instrument (1 of 7) Scientist work stations, telescope and.
LSU 01/18/2005Project Life Cycle1 The Project Life Cycle Project Management Unit, Lecture 2.
LSU 07/07/2004Communication1 Communication & Documentation Project Management Unit – Lecture 8.
The ESS vacuum team has overall responsibility for all technical vacuum systems used on the: Accelerator, Target and Neutron Scattering Instruments and.
1 Engineering the James Webb Space Telescope Paul Geithner JWST Deputy Project Manager - Technical March 26, 2011.
Effective Methods for Software and Systems Integration
LSU 05/02/2006Launch Trip1 The LaACES Launch Trip Ballooning Unit, Lecture 6.
MCCS Status Update SOFIA SITR Kendall Mauldin SOFIA Platform Project Flight Systems Lead SOFIA Stratospheric Observatory for Infrared Astronomy.
1 R. D. Gehrz 66th International Symposium on Molecular Spectroscopy, Columbus, OH, June 23, 2011 The Stratospheric Observatory for Infrared Astronomy.
TA Testing Plans Walter E. Miller OSC/ARC SSSC 29 September 2009.
Common PDR Problems ACES Presentation T. Gregory Guzik March 6, 2003.
Presentation EddiCam consortium, FF, Madrid 13/06/2002 Eddington programmatic status Fully approved by SPC as part of ESA’s science program as project.
FORCAST Line Operation #1 Pasquale Temi NASA-Ames.
ASPERA-3 April. 25, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/01 Schedule statused.
SOFIA Observatory Overview and Specifications Last Updated –
1 INSTITUTE OF SPACE SYSTEMS Universität Stuttgart Universities Space Research Association Deutsches SOFIA Institut American-German.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Telescope Integration and Tests Tuesday Afternoon.
Cycle 1 Planning Process B-G Andersson (SOFIA Science Operations Manager) & Ravi Sankrit (User Support Scientist) SSSC, May 11, 2011 Mountain View.
1/11/2011AAS SOFIA splinter (Seattle, WA) 1. 1/11/2011AAS SOFIA splinter (Seattle, WA) 2 SOFIA Stratospheric Observatory for Infrared Astronomy 2.7-meter.
1 HIPO Trimester Review Status Report Ted Dunham Lowell Observatory 11 December, 2008.
1 R. D. Gehrz 64th International Symposium on Molecular Spectroscopy, Columbus, OH, June 23, 2009 The Stratospheric Observatory for Infrared Astronomy.
Software Development Life Cycle (SDLC) Presented by The Smartpath Information System An ISO 9001:2008 Certified Organization
1 R. D. Gehrz 67th International Symposium on Molecular Spectroscopy, Columbus, OH, June 21, 2012 The Stratospheric Observatory for Infrared Astronomy.
THE PROJECT LIFE CYCLE PROJECT MANAGEMENT LIFE CYCLE LSU 01/18/2005 PROJECT LIFE CYCLE 1.
SSC SI Data Processing Pipeline Plans Tom Stephens USRA Information Systems Development Manager SSSC Meeting – Sept 29, 2009.
SOFIA--The Next Generation Airborne Observatory 2.5-meter (100-inch) telescope in a Boeing 747SP Based at NASA-Dryden’s Aircraft Ops Facility in Palmdale,
Solar Probe Plus A NASA Mission to Touch the Sun March 2015 Instrument Suite Name Presenter's Name.
Proposal: staged delivery of Scheduler and OpSim V1 (2016) meet most of the SRD requirements – Deliver a system that can be extended with an improved scheduler.
1 FLITECAM December 11, 2008 Ian McLean (Principal Investigator) UCLA Infrared Laboratory University of California, Los Angeles.
1 FLITECAM April 28, 2009 Ian McLean (Principal Investigator) UCLA Infrared Laboratory University of California, Los Angeles.
1 HIPO Trimester Review Status Report Ted Dunham Lowell Observatory 28 April, 2009.
FourStar Status SAC Meeting 13mar2010 Persson, Murphy, Birk, Monson, Kelson, Uomoto.
Introducing the INS Master Schedule Wayne Baggett.
SOFIA Program Status Bob Meyer January 10, 2010 Program Manager.
SOFIA--The Next Generation Airborne Observatory
Telescope Assembly, Integration and Verification (AIV) WBS 04C. 14 J
SOFIA — The Observatory
Project Management BBA & MBA
HFT Overview Flemming Videbæk BNL 3/14/12 F2F LBNL.
I&T&C Organization Chart
Rosetta Science Ground Segment Overview
GLAST Large Area Telescope:
Copyright Scott Bloss, All rights reserved.
0.0 Instrument Suite Name Presenter’s name
SOFIA Stratospheric Observatory For Infrared Astronomy
GLAST Large Area Telescope:
Management Breakout: MREFC Budget Summary Victor L
User instrument policy
Launch and On-orbit Checkout
Click to add title Planning for LSST Verification George Angeli LSST All Hands Meeting Tucson August 15, 2016.
GLAST Large Area Telescope
Introduction and Overview
GLAST Large Area Telescope
LCLS Undulator System Status and Schedule
Integration & Test Instrument Operations Coordination
Presentation transcript:

Near-term schedule Scott Horner

Background MCCS software engineering build #3 was delivered in June and tested by the SIL team in early July A number of bugs were identified, preventing tier 4 level testing in the SIL and line operations with this build MCCS software engineering build #4 was added to the schedule – delivery from L3 to DFRC 30 Sept FORCAST completed tier 1-3 testing with EB3 2

IMS:SOFIA_MS090924Dyn.mpp Created 09/25/2009 TA Activation FCF TA Characterization First Light attempt TA Characterization 10% 100% ISF FRR #3 AFSRB Segment 2 “lego” schedule This period was going to be used to integrate FORCAST, balance the TA, test the FORCAST to MCCS software interface, and perform EMI testing of FORCAST FORCAST is not installed until this period. FORCAST installation, MCCS change- over from open door build to EB4, MCCS checkout, and observatory checkout will need to occur prior to the start of line operations. The EMI testing needs to be inserted into the flow of line operations at an appropriate point. Science Flight Platform Flight TA Flight Ground Testing Data Analysis Contingency Flight

FORCAST flow change The silver lining –The previous schedule had MCCS software engineering build #4 arriving just- in time for testing on the aircraft with FORCAST – this represented a high risk to the success of the tests planned for that period –MCCS software engineering build #4 will be tested (tier 1-4) with the FORCAST software in the SIL in November prior to FORCAST delivery or installation on the aircraft 4

Integrated Master Schedule The IMS has been modified to include filters for FORCAST and GREAT tasks –Caveats: The FORCAST tasks in the IMS are not up to date and this has task has priority over my checking the GREAT flow FORCAST flow (SCI-AR-MEM-PM ) – was up to date with the IMS but now needs to be revised based on the new plan GREAT flow – will finish once the FORCAST flow is released FORCAST and HIPO use for TA testing needs to be worked out 5

Filtered FORCAST schedule 6

Segment 2 – Tracking Dates TA Characterization IMS:SOFIA_MS090911ajl.mpp Created 09/14/2009 Science Flight Platform Flight TA Flight Ground Testing Data Analysis Contingency Flight FORCAST and/or HIPO may be utilized for TA characterization during this period. Detailed planning for this period cannot occur until we have TA flight performance data.

Southern Hemisphere Deployment Segment 3 flight phase overview – Tracking Dates LOC FOC Observing Flights Instrument Commissioning Aircraft maintenance/Observatory upgrade Platform flights Germany Deploy either/or IMS:SOFIA_MS090924Dyn.mpp Created 09/25/2009

Lab construction at DAOF SI labs at DAOF are scheduled to be completed in FY10 Should only impact FORCAST – impact should be minor but we need to keep track of both schedules 9

Hangar floorplan 10 Outside Hangar Main entrance

Lab ceiling Most of the labs will have 11’6” (3.5m) ceilings Areas of two of the labs will have 11’ ceilings 11’6” requirement was derived from need to change out fill tubes Most operations that require high ceilings can be done in the PIF area or on the hangar floor if needed 11

Documents Need SI review –TASS specification (SCI-AR-SPE-SE01-040) –Vacuum specification (APP-AR-SPE-SE01-028A) –SI equipment to counterweight rack ICD (SCI-AR-ICD-SE ) –SI cart to facility ICD (SCI-AR-ICD-SE ) –SI cart to aircraft ICD (SOF-AR-ICD-SE ) Available soon –FORCAST integration flow (SCI-AR-MEM-PM ) –GREAT integration flow (SCI-AR-MEM-PM ) For your information –HIPO line operations test report (SCI-US-TRP-SV ) –FORCAST line operations test plan (SCI-US-PLA-SV01-????) –Franziska Harms’ dissertation, “A Contribution to Characterizing and Calibrating the Pointing Control System of the SOFIA Telescope” –Sven Schmid, et al. 2009, Journal of Aircraft Vol. 46, No. 4, July–August 2009 “Passive Control of the Flow Around the Stratospheric Observatory for Infrared Astronomy” –Stefan Brüggenwirth’s dissertation, “Development, Analysis and Verificaiton of the SOFIA Telescope Assembly Software Simulator” – “good reading for background on how the TA actually works” 12