Gas system for NA62 Straw detector Roberto Guida On behalf of Gas Service Team NA62 Straw working meeting, March 26, 2012 Outline: P&I Drawing Schedule.

Slides:



Advertisements
Similar presentations
ALICE TPC Ne/CO2 Gas System. Mixing Rack CO 2 -Removal & (O 2,H 2 O)- Cleaning Rack.
Advertisements

Peter Chochula CERN-ALICE ALICE DCS Workshop, CERN September 16, 2002 DCS – Frontend Monitoring and Control.
Sc Magnet test facility Consolidation Project presentation M. Bajko for the TEMB on behalf of the MSC TF section team 31. Aug
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
The RPC Closed loop Gas System. Schedule for completion - update Status Supplier: ok Mixer: ok Humidifier: ok Purifiers: installed, but not completely.
MICE RF TEST STAND Major Milestones (2006) –Testing of BURLE 4616 circuit September 2006 –Testing of 4616 circuit with full amplitude and phase control.
Planning a Mentoring Program A CALENDER FOR A FIRST-YEAR TEACHERS’ PROGRAM.
Dean R Walters Undulator Vacuum October 12-13, 2004 Facility Advisory Committee Undulator Vacuum System/Mechanical By Dean R Walters.
Plans for the Muon Gas and Cooling Systems LHCb infrastructure workshop February Burkhard Schmidt, with important input from Roberto Guida and Beatrice.
WP2: Detector development Summary G. Pugliese INFN - Politecnico of Bari.
IBL CO 2 cooling control system development status Lukasz Zwalinski – PH/DT/DI Maciej Ostrega – PH/DT/DI Florian Corbaz – EN/CV/DC.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
WP2: Detector development Summary G. Pugliese INFN - Politecnico of Bari.
Status and plans for online installation LHCb Installation Review April, 12 th 2005 Niko Neufeld for the LHCb Online team.
21 March 2007ATF2 Power Supplies ATF2 High Availability DC Magnet Power Supplies By Paul Bellomo, Antonio de Lira, David MacNair and Briant Lam*
04/02/ FH Plans for 2005 PH-DT1-GS. 04/02/ FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea.
André Augustinus 17 June 2002 Technology Overview What is out there to fulfil our requirements? (with thanks to Tarek)
15 October 2013 CHANTI Status Report F. Ambrosino, T. Capussela, D. Di Filippo, P. Massarotti, M. Mirra, M. Napolitano, L. Roscilli, G. Saracino Università.
CONSTRUCTION Andrea d'AURIA PH / DT-DI / GAS.
Active gas system status. S.Konovalov, K.Zhukov. Active gas system operation. S.Konovalov "Active gas system..."TRT Overview  Good design.
1 H. Pernegger/CERNIBL cooling review 15/5/2012 IBL Cooling Requirements H. Pernegger.
Test beam setup: status report 02/03/2009 M. Alfonsi (CERN)
R. Fantechi. TDAQ commissioning Status report on Infrastructure at the experiment PC farm Run control Network …
ALICE Collaboration Meeting Heidelberg Services Update  Progress on services Detector cabling Gas systems Cooling systems  Rack footprint  Primary electrical.
TOF Gas System Project Overview. Content Prototype for Aging tests done for RPC’s TOF Gas System: parameters and module layouts. Special Technology: channel.
GIF in EHN1- layout, construction and schedule Adrian Fabich, EN-MEF-LE GIF users meeting, 12 th February 2014.
19/02/2014A. D'Auria CERN/PH-DT-DI Maintenance ID flushing system:  Maintenance 2 dryers  Installation 2 flow meters  Maintenance of several hygrometers.
The RPC Closed loop Gas System Slides from Bianco and Guida.
ATLAS TRT CO 2 cooling system project status Beaufort 12: “Hurricane” (>119 km/h) Saffir-Simpson 5: “catastrophic damage” (>250 km/h) (CO 2 distribution.
Straw Working Group Status assembly at CERN Plans 10/2/14Straw WG.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
ALICE-TRD gas system 1/4/2015R. Guida PH-DT-DI1. TRD gas system Few numbers:  Total number of modules/racks: 20 (max leak rate certified at construction.
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
Status of NA62 straw electronics Webs Covers Services Readout.
M. Bonesini - MICE Inst Meeting M. Bonesini INFN Milano TOF installation plans.
CMS Experiment at the LHC, CERN Date Recorded: :21 CET Run/Event: / Candidate Collision Event Report from Belgium Michael Tytgat.
Status of and Installation Plan for DC Gas Control System and Target Work Scheduling Meeting 4 August 2006 PSI W. Molzon, Feng Xiao.
GIF++ gas systems 11/07/2014Ernesto, Roberto PH-DT-DI gas service1.
The Building 180 Cryogenic infrastructure water cooling system Status Update Stefano Moccia, EN-CV Coordination meeting 14/10/15.
ALICE TPC Gas Control System (toward the first fully implemented LHC gas system) S. Haider EP-TA1-GS.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
1 HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 Outline:  Full scale prototype status  Light source test  Construction Schedule.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
26/03/2014L-Ph. DE MENEZES & F. MERLET CERN/PH-DT-DI New recuperation system for n-Pentane:  Installation of the module in parallel of the first.
Status of the ATLAS ID Evaporative cooling system JCOV 25 Nov P. Bonneau TS/CV/Detector Cooling CONTENTS Overall statusOverall status Cooling plant.
26-Feb-16S.Movchan Straw manufacturing and QC1 Dubna NA62 straw tracker assembly area (milestone) halls plans conclusion Presented by S.Movchan.
A2-A5: The drawing has been revised (minor changes), the bid has been approved by INFN management and the invitation letter to the companies will be sent.
WG1 Decommissioning Kickoff Workshop WG1 Decommissioning Kickoff Workshop Long term Storage & ID tooling management R. Vuillermet on behalf of TC team.
Gas System Construction Status Oct FH. General Construction is proceeding well, (nearly on-schedule). Testing of Racks is longer than foreseen Testing.
8/4/2015R. Guida PH-DT-DI1 Info 1)Air conditioning system Status: Adrian Fabich contacted CV and he is waiting for info. Today I’m going to meet experts.
Active gas system status & plans. S.Konovalov, K.Zhukov, K.Vorobev.
CMS-GEM gas system GEMs for CMS High Eta Muons - Workshop III, CERN April R.Guida PH-DT-DI.
The closed loop system at ISR We moved the system at ISR in January. Preliminary tests has been done in order to verify the possible use in the “ISR conditions”:
Totem Gas Systems ( T1, T2 ) F. Hahn and S. Haider PH / DT1.
GIF++ gas system Outline:  Beam and cosmic trigger  Gas distribution panels  Gas detection (present and final layout)  Conclusions 14/1/2015R. Guida,
TRD Gas System Layouts Production Readiness Review 03 – Nov F. Hahn.
Straw Working group Ferrara 4/9/2014. Outline Status and Plans Installation of Chambers 1-3 Chamber 4 Vacuum test SRB Readout, monitoring and software.
MUSE NSF Review March 24, MUSE Project Management Ronald Ransome Rutgers The State University of New Jersey For the MUSE Collaboration.
September 5, Burkhard Schmidt Integration and Installation Outline: Integration and Infrastructure issues -Suspended platforms -Cable chains -Beam.
CLAS12 DAQ & Trigger Status
Francois and Lau EATM 17 July 2012
Gas system Commissioning procedures and status
Totem Gas Systems ( T1 , T2 ) S. Haider PH / DT1.
Gas System Commissioning
CMS gas systems meeting
Current Status Future Progress Monitoring
10/month is the present production rate 2 FTE + sporadic contributions
RPC HV&LV status Introduction HV power supply tender
GAUSS Work plan Software Week 6 March 2002 F.Ranjard / CERN.
Presentation transcript:

Gas system for NA62 Straw detector Roberto Guida On behalf of Gas Service Team NA62 Straw working meeting, March 26, 2012 Outline: P&I Drawing Schedule Distribution racks Mixer and control racks Conclusions

P&I drawing

Construction schedule Key dates: -All racks ready for beginning June -Installation during July/August -Test/commissioning beginning September

Gas distribution racks - Gas distribution is made using Festo pneumatic units controlled through profibus - System tested for ageing in TRT test set-up - All material received - Construction of distribution racks is started Check/finalize length and routing of last capillary pipe on the chambers to be discussed

Mixer and Control racks - Mixer and Control racks are in a early stage of construction - 70% of material for Mixer is arrived - For Control rack layout we are waiting few inputs on PLC and interfaces choices - 24 V power supplies to be ordered - We expect to fix these points this week MixerControl rack

Conclusions The construction of the gas system for the NA62 Straw detector is on going Gas distribution racks are a bit more advanced mixer and control racks are still on-schedule URD for the software controls definition is started and it will be send to EN in 1-2 weeks Software controls (EN) expected to be read beginning September Review/Update of the status in about 2 months (when all racks should be almost ready) Budget status Used about 60% of allocated budget Mainly for materials.