Transmission Services Report: North and West RPG Projects Bill Bojorquez TAC July 7, 2005.

Slides:



Advertisements
Similar presentations
October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
Advertisements

March 6, 2008 Technical Advisory Committee Luminant Energy & Oncor Tyler Grande Autotransformer Addition and 138 kV Line Upgrade Project Jay Teixeira Manager,
Company LOGO Cleco Planning Process. Models Cleco uses SPP’s annual series of models to determine the NERC reliability violations. Cleco uses SPP or VST.
Regional Planning Group Project
NTTG Economic Study and Biennial Study Update NTTG Economic Study and Biennial Study Update NTTG Study Cycle.
Houston Import Evaluation Cross Texas Transmission & Garland Power & Light ERCOT RPG Meeting August 27th, 2013.
KURTEN SWITCH PROJECT (BRYAN/ COLLEGE STATION AREA UPGRADES) Technical Advisory Committee December 1, 2005 Transmission Services.
Oncor Electric Delivery Company LLC TOGETHER WE DELIVER ODESSA UPDATE Jan 22, 2013 Presentation to ERCOT Regional Planning Group Austin, TX Mike Juricek.
Houston Region Import Capacity Project August 27, 2013 Regional Planning Group Meeting.
January 5, 2012 TAC Cross Valley 345 kV Project Jeff Billo Manager, Mid-Term Planning.
1 Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans,
RTP Update RPG Meeting July 21, RTP update  Reliability analysis for the contingencies where load shed is not allowed is complete.
Determine Facility Ratings, SOLs and Transfer Capabilities Paul Johnson Chair of the Determine Facility Ratings Standard Drafting Team An Overview of the.
Report on the NCTPC 2006 Collaborative Transmission Plan Mark Byrd, Manager – Transmission Planning Progress Energy Carolinas, Inc January 25, 2007.
JACKSBORO TO WEST DENTON 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
Managing West Texas Wind SWEDE 2008 Conference May 2, 2008 Presented by Paul Hassink AEPSC Texas Transmission Planning.
10/03/ Report on Existing and Potential Electric System Constraints and Needs Within the ERCOT Region October 3, 2002.
April 16, 2010 RPG Meeting ERCOT Five-Year Transmission Plan Update Jeff Billo.
Engineering a sustainable future 1 ERCOT Voltage Ride-Through Study Workshop June 26 th, 2009.
John Dumas Director of Wholesale Market Operations Jeff Billo Manager of Mid Term Planning Dan Jones Director with Potomac Economics, the ERCOT IMM Board.
West to North CSC Location Scenario 3b WMS August 20, 2008.
Kurten Switch Project ERCOT Board of Directors Bill Bojorquez System Planning December 13, 2005.
October 16, 2009 RPG Meeting ERCOT 2009 Five-Year Transmission Plan Update Jeff Billo.
Proposed North – South Congestion Mitigation Plan Luminant Energy July 2008.
POWER SYSTEM PLANNING CHARTER AND PROCESSES UPDATES Presentation to TAC Sept 9, 2004 Transmission Services Ken Donohoo, Manager of System Planning
Jones Creek Project Submitted to RPG on July 7, 2014 July 22, 2014 Regional Planning Group Meeting.
Current Export Initiatives Jerry Mossing Exports Workshop February, 16,2006, Metropolitan Center, Calgary.
1 Entergy Louisiana, Inc. (South) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
WEST LEVEE TO NORWOOD 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
April 16, 2010 RPG Meeting Lamesa Area Upgrades ERCOT Independent Review Jeff Billo.
2008 Annual Five Year Plan Update 2 10/12/2007 Regional Planning: Jay Teixeira, Harry Liu, Brad Schwarz, Jeff Billo, Chris Ngai.
JACKSBORO TO WEST DENTON and WEST LEVEE TO NORWOOD 345-kV PROJECTS April 20, 2004 Transmission Services Operations.
Jeff Billo Manager, ERCOT Transmission Planning Kenedy to Nixon to Seguin Line Upgrade Project Regional Planning Group (RPG) Review; ERCOT Independent.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
TAC02/01/2007 DW 1 TAC Briefing on: - Report on Constraints and Needs: Five Year Plan Development - Long Term System Assessment (LTSA) - Entergy Integration.
SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.
2010 CSC & Zone Selection: 6 Lines W-N & 4 Zones (WN2_SN0-4Z) Shams Siddiqi, Ph.D. Crescent Power, Inc. (512) August 19,
ERCOT TAC11/2/ CREZ Study Update ERCOT TAC 11/2/2006.
February 13, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
1 State Estimator performance. 2 State of Technology Many metrics have been proposed for measuring State Estimator performance.. PI = min Σ( Z – h i (x))^
Transmission Voltage Management Ross Owen Oncor Electric Delivery.
October 16, 2009 RPG Meeting ERCOT Independent Review of the Corpus Christi Improvements Project Jeff Billo.
Current Operational Challenges Computing the West – North Limits Potential IROLs Local Voltage & Thermal issue (OOME) High Voltage Outages.
ERCOT ROS Planning Working Group (PLWG) Scope Approved at ROS Meeting.
RPG: September 24, Long-Term System Assessment Introduction Jeff Billo, Manager, Transmission Planning September 2013 Regional Planning Group.
3/28/2008 RPG CREZ Meeting CREZ Transmission Optimization (CTO) Study And The Oscar Goes To… Warren Lasher Manager, System Assessment.
Jeff Billo Manager, Transmission Planning
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
OPSTF – Issue 7 Long-term unavailability of autotransformers.
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
Panhandle Renewable Energy Zone (PREZ) Study
June 3, 2010 Technical Advisory Group RMR Exit for Spencer 5 – Remedial Action Plans Jay Teixeira.
May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
POWER SYSTEM PLANNING CHARTER AND PROCESSES Presentation to TAC May 6, 2004 Transmission Services Ken Donohoo, Manager of System Planning Dan Woodfin,
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
December 14, 2007 RPG - CREZ Meeting CREZ Transmission Optimization Study: Update Warren Lasher ERCOT System Assessment.
2006 Reliability Study James Manning Bryan Guy May 12, 2006.
Response to TAC Questions on PGRR031 TAC– January 28, 2014 Jeff Billo, ERCOT 1.
03/06/2008 TAC CREZ Transmission Optimization (CTO) Study Update Dan Woodfin Director, System Planning.
2006 Preliminary Reliability Study Results Bryan Guy September 7, 2006.
2008 Annual Five Year Plan Update 4 For RPG-CREZ Meeting 12/14/2007 Department of Regional Planning Harry Liu.
Houston Area Constraint Mitigation Project ERCOT Board of Directors March 15, 2005.
ONCOR Electric Delivery/ Texas New Mexico Power East Bell County to TNP One 345 kV Line Upgrade Projects Board of Directors July 17, 2007.
Barrilla Junction Area Transmission Improvements Project
ERCOT 2009 Five-Year Transmission Plan Update
Warren Lasher Manager, Long-Term Planning and Policy
Modifications to Planning Charter
ITP20 Flowgate Selection Introduction
Presentation transcript:

Transmission Services Report: North and West RPG Projects Bill Bojorquez TAC July 7, 2005

DFW Recent Improvements (2004/2005) 2 – 345 kV Circuits 14 – 138 kV Circuits 2 – 345/138 kV Autotransformers 1 – new 138kV Substation 9 – Reactive Capacitors Projects 2 – 138/69 kV Autotransformers

DFW Improvements Completed Based upon May 2005 TPIT submissions from transmission owners

2006 DFW Congestion Relief Study Results

Study Introduction Initial study meeting of North RPG in April 2004 Scope included 2006 & 2008 Congestion Relief Studies 2008 was separated from first study at November 16, 2004 North RPG meeting with group consensus

Process Overview Preformed AC contingency analysis on 2006 power flow case with an economic dispatch to identify overloads. Stakeholders proposed projects to resolve overloads. Determined subset of projects that were needed to meet reliability needs. –When multiple projects resolved the same reliability need then economic analysis was done to select the preferred project. New base case was created for economic studies which includes reliability projects. Economic analysis was performed on remaining projects to identify those with net economic benefit.

Reliability Project Improvements Added to Case for Economic Evaluation

Recommended Projects Reliability Projects Liggett Series Reactor Royse – Terrell Switch 69-kV Line Rebuild Allen Switch - Plano Alma 138-kV Terminal Equipment Upgrade E. Levee – Reagan Street 138-kV Line Rebuild Reliability Projects That Provide Additional Economic Benefits Plano Tennyson 345/138-kV Autotransformer Installation ($4.0 M) Economic ProjectsCost Centerville Switch – Parkdale 138-kV Line Rebuild $9.8 M Ben Davis – Royse 345-kV Line Upgrade (TMPA)$4.5 M Johnson Switch – Venus 345-kV Line Upgrade$4.0 M DeCordova Everman 345-kV Line Upgrade $8.2 M TOTAL$30.5 M Annual Benefit (2006)$19.3 M

Reliability Projects Reliability/Economic ProjectsEconomic Projects

Reliability Projects Reliability/Economic ProjectsEconomic Projects

Other Recommendations TXU ED should install breakers at the Decordova bus on the Decordova to Everman 345-kV circuit and at the Benbrook bus on the Benbrook to Sycamore Creek 345- kV circuit, if feasible Perform follow up study to determine additional upgrades with longer lead times that would be economic to reduce the impact of congestion

DFW/North Zone 2009 Congestion Relief Study Goal is to identify longer lead time reliability-driven and economic projects for DFW and surrounding area throughout planning horizon Process Overview: –Develop a Preliminary Study Case –Identify reliability problems in Study Case –Identify reliability projects and develop a Economic Base Case –Identify congestion problems for various generation scenarios, based on this case –Identify projects to alleviate identified congestion –Analyze economics of proposed projects –Include the economic projects in the case and iterate steps –Make recommendation Study will be complete in 6-8 months

McCamey Area Study Results

May 2003, the ERCOT BOD approved two 345 kV transmission projects contingent upon IAs totaling 1500 MW and 2000 MW in McCamey Nov 2004, ERCOT Staff completed examination of the transfer capability out of the McCamey area –Indicated significant 138 kV additions substantially improve transfer capability –Showed voltage control and thermal overload issues above 600 MW transfer level –Recommended reconsideration and acceleration of 345 kV transmission projects

McCamey Area Study Results Jan 2005 (West RPG Meeting), AEP presented reactive plan and temperature adjusted line ratings ERCOT Staff reexamined application of reactive plan and adjusted ratings –Staff concluded 755 MW (total McCamey generation) can be exported from the McCamey area –Assumes full implementation of plan and adjusted ratings ERCOT Staff and TSP’s will continue to review the need for 345 kV lines as additional generators request interconnection in McCamey

Questions ? ? ? ?