1 MICE CM27 Engineering integration Andy Nichols, STFC 9 th July, 2010.

Slides:



Advertisements
Similar presentations
1 MICE Project Board Schedule and risk discussion Introduction Project Management comment Schedule considerations Adapting the schedule/reacting to circumstances.
Advertisements

July 2004 Use menu "View - Header & Footer" for Presentation title - Siglum - Reference Integrated CAD-Metrology and Alignment of Key Features of A380.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
MICE Target Report Chris Booth (for target team) Sheffield 7 th May 2009.
MICE Target Schedule Chris Booth Sheffield 12 th June 2006.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
1 UKNF/MICE Oversight Committee Open session Integration of the MICE project Background & local history Progress since 2007 Schedule & planning considerations.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
MICE Collaboration meeting at Berkeley 9 – 12 February 2005 Cooling Channel layout Presented by Stephanie Yang & Wing Lau.
1 UKNF/MICE OsC PM report Summary assessment of MICE Risks, pressures and worries Project management Electrical substation, accommodation Redefining the.
WBS & AO Controls Jason Chin, Don Gavel, Erik Johansson, Mark Reinig Design Meeting (Team meeting #10) Sept 17 th, 2007.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
MICE Collaboration Meeting March 29 - April 1, CERN MICE alignment, tolerances and supports Tuesday March 30 Room Edgar Black/IIT March17-
Target Assembly and Installation Update 20 th August 2009 Paul Hodgson The University of Sheffield.
Review of Liquid Resin Molding Specifications FAA Workshop September 2003 Scott Reeve National Composite Center.
Engineering Systems of.
MICE VIDEO Conference 17 th December 2003 Report on AFCSWG Safety Review -- Future Plan By Wing Lau -- Oxford.
1 Project Manager Report Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
1 MICE CM32 Summary Scheduling and planning; aims for this year Schedule update Main schedule drivers Keeping us on schedule Comment on Steps V & VI Detail.
1 MICE PSAG PM report Brief overview Re-planning the project Solenoids, decay and spectrometer Open issues and worries Andy Nichols, STFC, PSAG, 5/5/10.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
Software Requirements Engineering: What, Why, Who, When, and How
ATLAS EXPERIMENT INTEGRATION TASK: SPACE MANAGEMENT Tatiana Klioutchnikova 05/06/
LATLAT CU Beam Test 3rd May GLAST Program CU Beam Test CU Integration Francesco Nicola
1 BROOKHAVEN SCIENCE ASSOCIATES Abstract Magnet and Girder Integration Lewis Doom, NSLS-II Project National Synchrotron Light Source II (NSLS-II) will.
© 2012 xtUML.org Bill Chown – Mentor Graphics Model Driven Engineering.
Status of installed target Preparation of “demonstrator” target Chris Booth Sheffield 25 th January 2008.
Page 1 BaBar IFR Mechanical, Schedule Cost Review Outbriefing (1) Excellent job on preparing and presenting review Overall, the Committee feels that the.
Global Design Effort Beam Delivery System => EDR LCWS07 June 2, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi Yamamoto.
Technical Board and Safety Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Compressor status AWAKE Technical Board meeting 19 August 2015.
CLIC Permanent Magnet Quadrupole Engineering Development of second family member Norbert Collomb, STFC Daresbury Laboratory 1N. Collomb 07/11/2012.
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
Project Managers Report CM40 Collaboration Board – Rome Roy Preece 28 th October 2014.
1 MICE CM27 PM Report Re-defining the UK project this FY Schedule things Apologies and accommodation Andy Nichols, STFC 7 th July, 2010.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
1 Engineering Session Summary Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
1 03/21/2006 GLAST CU Beam Test Workshop Scanning Table.
1 MICE PM Report Infrastructure/integration progress Electrical work AFC, diffuser, etc Help with project control & staffing issues Worries & problems.
1 MICE Schedule Review no 1 Aims of review and description of review charge Motivation and external drivers Aims of the review A few of the problems Description.
NA62 Organisation of the work - proposal 2/24/20161PD/DT/PO-MH.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
LSST Camera Electronics Overview September 16, 2008 R. Van Berg for the LSST Electronics Team.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
Conventional Facilities integration: Approach and Issues Daniel Piso Fernández WP Leader (WP13 Conventional Facilities Integration Support) November 5,
Fieldbus Foundation General Assembly 2008 Project Planning and Execution Mike Downey Jacobs Engineering.
D. Missiaen – 13/06/2014. D. Missiaen 13/06/ Agenda Introduction to alignment techniques Reserved space for Survey The CERN Co-ordinates System.
MICE Target – Status & Plans Chris Booth Sheffield 28 th February 2006.
Learning to Improve Matthew Pike. Making a difference.
1 MICE Coupling Coil Cryostating and Test Steve Gourlay March 1, Office of Science.
1 MICE CM29 Engineering Summary Cooling channel moving platforms – Norbert Floor Beams and plates – Andy L Magnetic modelling – Mike RF Engineering – Andy.
SPHENIX Mechanical Don Lynch & Rich Ruggiero April 10, 2014.
1 MICE CM25 Engineering Session Summary Contents: Infrastructure Diffuser Coupling Coils Radiation Shutter AFC module EMR Andy Nichols, STFC, 4-7 th November.
Chris Booth Sheffield 29th March 2006
Mandate Priorities Other tasks Membership Forthcoming reports to CTC
MICE CM28 Engineering Session Summary (On behalf of Wing)
Status of the MICE Construction Project
ProtoDUNE SP – Slow control Status
Installation of an Instrument on a CERN machine
MICE CM31 Schedule summary
Status of the PANDA Magnet
MICE PM Report Progress with the Infrastructure A few problems
Ron Williamson, PhD Systems Engineer, Raytheon 20 June 2011
CAD/CAM services ensure complete tooling process coverage for mold tooling design in catia. You can use our CAD/CAM Services for mold tooling design.
Experience with an IT Asset Management System
ESHAC #8 Safety Readiness Review Thomas Hansson, ESH
East Hall under construction
Integrated CAD-Metrology and Alignment of Key Features of A380 Wings
Presentation transcript:

1 MICE CM27 Engineering integration Andy Nichols, STFC 9 th July, 2010

Installation of MICE Step VI in R5.2 Just in case we forget what we need to do

Integration Between now and year xxxx, MICE has to successfully build and install several large and complex subsystems, for example: –Two spectrometers –Three absorber-focus coils –Two RF-coupling coil magnets –And all their services and ancillaries In a very confined (more confined than we think) space to a reasonable degree of accuracy –Also have to accommodate several different engineering ‘cultures’ and standards –Have demonstrated that a more rigorous engineering approach pays dividends – eg, the MICE target –Now want to read that across to the other subsystems –Easier said than done

Integration So we’re changing the emphasis slightly, from infrastructure and surroundings to the subsystems and interfaces Top level assembly now successfully driven by one (large!) Solid Edge CAD assembly We MUST reinforce the RAL/DL engineering team Full time integration engineer (Jason) is appointed Am now working on support for him Monthly MICE Technical Board will be forum for integration issues Will build on work already done by Wing & Stephanie Integration activity will be centralised at and led by RAL - important Discussions just beginning with subsystem owners to encourage information flow Jason ready to start mid-late July 4

Integration Who is point of contact for the system? What does it do? How does it do it? What are its outputs, both required and unwanted (how are the latter dealt with)? What are the extent of non mechanical interactions (e.g. magnetic, EMC, etc) and is any hardware required to alleviate interaction problems that needs to be accounted for? What services does it require? Where will they come from? Considerations for routing (space, temperature from, temperature affect on, robustness, crosstalk etc). What systems, sub-systems & components are being manufactured by who? What drawing information already exists? What drawing information is missing (e.g. services)? What sub-systems or infrastructure are adjacent? What are its interfaces (parts, infrastructure, etc)? What level of accuracy is defined for the interfaces? Do these interfaces meet at extremes of tolerance? Is there any adjustment in the interfaces? Is there sufficient space for tooling or inspection equipment to be used on interface connections? Are there any orientation accuracy requirements (e.g. alignment with beam)? What are the datum features? What is the accuracy of the datum features? What standards have been used? How is quality monitored and controlled? Safety and requirements for installation & commissioning? Does it need to be moved again for installation of other subsystems later? 5 Lots of detail, but first thoughts from Jason:

Integration Even if we don’t do anything else, it is vital that we: –Define an envelope for each subsystem –Define a stay-clear zone –Define the interfaces –Translate the above into ONE set of top-level reference drawings –The absorber/focus coil interface difficulties would have benefitted from this approach! –Create the drawing depository at last – maybe a mini version of CERN CDD Important to remember that this culture must apply across the international project