Update on the M1 schedule Muon Meeting March 23, 2009 Burkhard Schmidt.

Slides:



Advertisements
Similar presentations
March 02, 2009LHCb Muon Commissioning meeting 1 First week of chambers test Alessandro Cardini, Davide Pinci, Fernando Rodrigues, Maria Luisa Porto, Rafael.
Advertisements

M1 Installation Schedule Plans Burkhard Schmidt Muon Meeting
January 6. January 7 January 8 January 9 January 10.
02-Mar-09A. Cardini / CERN & INFN1 Muon Detector Status (week 9: Feb 23 rd  Feb 27 th ) Present: Ale, Thomas, Nikolai, Oleg, Sasha, Maria Luisa, Perluigi,
Whole School Attendance Whole School Attendance 94.64% Overall School Absence 5.36%
Special Linac WG meeting: Assembly of the ISOLDE Cryomodules – HIE-ISOLDE Survey and Alignment – March 19 th 2014 Jean-Christophe GaydeEN/MEF-SU Guillaume.
Chamber Calibration Bench Status Barrel Muon Alignment Group 9 April 2003, J MocholíWorkshop on "LHC Physics with High-Pt Muons in CMS'‘, Bologna, Italy.
MONDAYTUESDAYWEDNESDAYTHURSDAYFRIDAY March 16March 17March 18March 19March 20 Signing up for roles ACT III 1 st period Discussing ideas Planning ACT III.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
TGC Big wheel Sector assembly plan Tatsuo Kawamoto ATLAS workshop 2005.
Start Counter Construction Update Eric Pooser 08/21/2014.
Preparation of wall position Alignment of A and C side in closed position Creation of reference system Translation of reference system to open position.
WP2: Detector development Summary G. Pugliese INFN - Politecnico of Bari.
Malte HildebrandtDC Status Report, Dear MEG Committee,PSI, April 14 th 2009 this is the first report concerning the drift chamber status as.
V. Bobillier1 Long distance cable installation status Calorimeter commissioning meeting.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
Muon Stations M2-M5 Hardware status Outline: Gas System status UF/PNPI HV-system status Remaining M2-M5 installation tasks – Air cooling system status.
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
Technical Support Activities in PH-ADO-PO
G. Carboni – Muon Meeting – April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to
On behalf of joint ITEP / IHEP team: A. Arefiev, N. Filimonov, T. Kvaratskheliya, I. Machikhiliyan, P. Shatalov, T. Zakoryuchkina, A. Zhokhov, S. Zvyagintsev.
Michel RAYMOND – April 14 th, 2011 Technical Support Activities in PH-ADO-PO Goals for 2011.
CALO Commissioning Plans Pascal Perret LPC Clermont 17 March 2008.
D0 PMG 6/15/00 PMG Agenda June 15, 2000  Overview (Tuts) u Detector status u Reportable milestones u Financial status u Summary  Response to DOE review.
Available Review Cycles Tokyo to Vienna Assumptions: ExC Review limited to 5 days Specification submitted for QR by 11/2 Editing/Integration limited to.
G. Carboni - Muon Meeting – Draft Agenda Muon Meeting 6 April 2004 Introduction (15 min) Total 15 min MWPC prodution Material supplies,
SunSatFriThursWedTuesMon January
G. Carboni - Muon Meeting – Muon Meeting 12/ Agenda IntroductionGiovanni (30’) GEM and TDR AddendumWalter (20’) Update on M1 ratesAlessia.
October 18, Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.
Status of Muon Activities W.Baldini, N. Bondar, O.Maev, B. Schmidt LS1 Meeting Dec. 20-rd 2013.
8/September/2008Calo Running and Operation Meeting 1 SPD running and operation: progress report and plans Calo running and operation meeting – CERN 8 th.
10/7/2003Thomas Schneider1 Status report of CERN/PNPI Tooling support for PNPI M2R2 Prototype Plans towards the PRR.
Parallel & Perpendicular Lines... Example 1: Find the slope of a line passing through the points (2, 3) and (0, -1) (-2, 4) and (-2, 6) (5, 2)
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities.
V. Bobillier1 Cable installation status.
M1 Central Part Cable Routing R3 FAR R2 CLOSE R2 FAR + GEM A3 B From chain GEM R2 CLOSE R2 FAR A1 20 A1 A1 A2 A CHAIN Access Front Dané.
Gas System Construction Status Oct FH. General Construction is proceeding well, (nearly on-schedule). Testing of Racks is longer than foreseen Testing.
Muon System Update: Next Steps Alessandro Cardini INFN Cagliari.
Tile HCAL status Felix Sefkow CALICE Technical Board Review April 19, 2007.
6 September 2007VELOEddy Jans 0 VELO-installation++ activities September 6, 2007 General items Detector installation plans.
1 PS cabling status and planning Overview Rustem DZHELYADIN (CERN&IHEP, Protvino) PS-Cabling: what has been done : 1.PS/C top cable tray (3days)installed.
MUON Project Overview Action Items from September meeting New Action Items Update to the List of Worries Update of plans for the next 6 months.
Project Office Activities R. Vuillermet 08/09/2015R. Vuillermet PH-ADO-PO1.
System of Equations Solve by Substitution. A System of Equations:  Consists of two linear equations  We want to find out information about the two lines:
Trigger efficicency on double tracks Trigger efficiency on isolated tracks Final results of the Trigger Test on the 25ns beam Bx NUMBER Fraction of Triggers.
1 Planning DCS WS L.Jirdén. 2 TPC HMPID ACORDE FE PC Console DSS Disk SRV DB-SRV App GW sensors actuators DSS sensors actuators PC room SXL2.
Michel RAYMOND – December 7 th, 2012 Technical Support Activities in PH-ADO-PO Statement of 2012 activities Schedule & Organization on LS1.
ECAL status and plans C-side A-side Further plans People involved: Alexander Arefiev, Boris Bobchenko, Yury Gilitskiy, Tengiz Kvaratskheliya, Irina Machikhiliyan,
Status of the Muon detector Alessandro Cardini CERN & INFN Cagliari Thanks do Davide, Rafael, Maurizio, Oleg, for part of the material included here.
CALO News Pascal Perret LPC Clermont 22 January 2012.
Linac4 Project Meeting 1/ /01/ st priority 2  First priority: from the Linac4 project, the best wishes to you and your families for a 2010.
E.Gushchin,S.Filippov(INR,Moscow) 16 April 2008Calo commissioning meeting CERN PS/SPD LED monitoring system status General status LED signal is used for.
21 January Summary: Updating of the activities carried out on-site (Done) in DEC + ½JAN List activities on going (Next steps) and scheduled till.
Plans for the UT Installation LHCb infrastructure workshop February Burkhard Schmidt for the UT group.
September 5, Burkhard Schmidt Integration and Installation Outline: Integration and Infrastructure issues -Suspended platforms -Cable chains -Beam.
Gantt Chart October November December Step One Step Two
GCOS IP and Update on CEOS Response
Updated with comments 22 may 2017 Updated again 29 June 2017
G. Carboni for the Muon Group
Renovation of the 45-year old PS magnets
Support for Malwarebytes Updation Issues
Current Event Schedule
6 Weeks Tests: April 26th – 28th
RPC Readiness for installation
South Milford Pre-School Playgroup
50% Written Exam Explained
RNE Technical meeting February 2018, PCS UG.
BOARD MEETINGS Thursday, August 27th TBA NJHS MEETING SCHEDULE
Presentation transcript:

Update on the M1 schedule Muon Meeting March 23, 2009 Burkhard Schmidt

Preparatory work for chamber installation No Access A-side (SPD/PS work) A conflict between Calo work and cabling activities on M1 C-back has still to be solved.

Planning RICH2 – M1 – SPD/PS No Access C-side (RICH2-HPD work) No Access A-side (SPD/PS work) No Access A-side (RICH2-HPD work) Severe limitations in March due to parallel activities on SPD/PS and RICH 2. No conflicting activities are foreseen in April May.  This has to be guaranteed, otherwise it is impossible to follow with the planning

Installation/Testing/Alignment 1 st layer We should aim to complete the installation of the first layer by Easter (April 10) The 1 st layer should be completed also in terms of testing and alignment by May 15  We have not yet the persons for each task; manpower is still missing

Installation/Testing/Alignment 2 nd layer

Tasks – Manpower Activities for weeks of February 23 – March 6: – Alignment work, including tool preparation: Thomas, Wander/Luca, Jean-Christoph, Sasha, Cedric – Cabling work inner part: Emilano, Massimo, Marco, Luca, Stas – Chamber installation R3/R4: Mario, Pierluigi, Fabrizio – Chamber testing: Alessandro, Fernando, Raphael – Chamber preparation (alignment cross + transport): Giovanni S. Activities for weeks March 9 – 20: – Alignment work: Thomas, Wander, Jean-Christoph, Sasha, Cedric, Burkhard – Cabling work inner part: Stas, Sacha, we miss a person – Chamber installation (R3/R4): Marcellino, we miss people – Chamber installation (R1/R2): Fabrizio, Alessandro, Burkhard – Chamber testing: Alessandro, Fernando, more people are needed  We don’t have yet all the manpower needed to get the work scheduled done !