25.05.2009 LHC Status - Planck09 - Padova,IT 1 Status of the LHC Machine J. Wenninger CERN Beams Department Operation Group Acknowledgements to R. Schmidt.

Slides:



Advertisements
Similar presentations
LHC Machine Protection
Advertisements

Rüdiger Schmidt - Wuppertal Januar Der LHC Beschleuniger Rüdiger Schmidt - CERN Universität Wuppertal Januar 2004 Herausforderungen LHC Beschleunigerphysik.
(ATLAS) Higgs Prospects at HL-LHC. ATLAS CMS ALICE LHCb Center-of-Mass Energy ( ) 7 TeV Center-of-Mass Energy (Nominal) 14 TeV ? Center-of-Mass.
1 The LHC Accelerator Complex Jörg Wenninger CERN Accelerators and Beams Department Operations group Hadron Collider Summer School - June 2007 Part 1:
A. Bay Beijing October Accelerators We want to study submicroscopic structure of particles. Spatial resolution of a probe ~de Broglie wavelength.
1 Where to Search for the Higgs  A direct search for the Higgs was carried out by the four LEP experiments from CMS energy of GeV The.
Laurent Tavian Thanks to contribution and helpful discussions with M. Jimenez, V. Parma, F. Bertinelli, J.Ph. Tock, R. van weelderen, S. Claudet, A. Perin,
The LHC: an Accelerated Overview Jonathan Walsh May 2, 2006.
CRYOGENICS AND POWERING
1 Commissioning challenges of the LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group February 2008 LHC overview Magnets Luminosity.
The Sector 3-4 incident at the LHC: fault tree and corrective measures Ph. Lebrun Risk Analysis Review Committee CERN, 5 March 2009.
J. Wenninger LNF Spring School, May LHC : construction and operation Part 2: Machine protection Incident and energy limits Commissioning and operation.
LHC Status ReportLHC Status Report Lyn Evans 96 th LHCC meeting, CERN 19 th November 2008.
A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
LHC status & 2009/2010 operations Mike Lamont. Contents Consolidation – brief recall Splices Operational energies Potential performance Present status.
LHC Status - SUSY Bonn 1 Drawing by Sergio Cittolin Status of the LHC 6 months of beam operation in 2010 J. Wenninger CERN.
CERN Rüdiger Schmidt FCC week 2015 Long Magnet Stringpage 1 Incident September 19 th Architecture of powering and protection systems for high field.
Partikeldagarna, Göteborg 21 September 2007 LHC: Status and Plans Lyn Evans.
LHC - a world machine LHC-world machine Hans Hoffmann, CERN honorary1 “Leadership” in particle physics: SSC-LHC, Colliding beam accelerators:
PostMortem Workshop January LHC “Post Mortem” Workshop: Introduction Initiative by Robin Lauckner, Adriaan Rijllart and myself, helped by many other.
Updates on FLUKA simulations of TCDQ halo loads at IR6 FLUKA team & B. Goddard LHC Collimation Working Group March 5 th, 2007.
L. Serio COPING WITH TRANSIENTS L. SERIO CERN, Geneva (Switzerland)
Consolidation and Upgrade plans for the LHC Vacuum System
Hadron Collider Summer School - June 2009
3 November 2008 D.Acosta 1 Most Powerful Solenoid Magnet u 18kA, 3.8T solenoid u 3m radius, 15m length u 2.5 GJ stored energy u Can be discharged in a.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
Chamonix 2006, B.Dehning 1 Commissioning of Beam Loss Monitors B. Dehning CERN AB/BDI.
LHC Machine Protection: an introduction Jörg Wenninger OP training March 2006 Acknowledgments to my colleagues of the MPWG for input and material.
Future Circular Collider Study Kickoff Meeting CERN ERL TEST FACILITY STAGES AND OPTICS 12–15 February 2014, University of Geneva Alessandra Valloni.
A. Bertarelli – A. DallocchioWorkshop on Materials for Collimators and Beam absorbers, 4 th Sept 2007 LHC Collimators (Phase II): What is an ideal material.
MPP Meeting 07/03/2007 MPP Main Ring Magnet Performance Panel Meeting Wednesday 7th March 2007 Agenda: 1)Matters arising 2)Recommendations for the case.
Steve Playfer University of Edinburgh 15th Novemebr 2008 Large Hadron Collider at CERN.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
1 Operational challenges of the LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group November 2007 Part 1: LHC overview and status.
LHC Commissioning Status Gianluigi Arduini CERN – AB Department For… 23/10/20081LHC Commissioning Status - G. Arduini.
B. Todd, A. Apollonio, M. Kwiatkowski, R. Schmidt, S. Wagner, J. Walter a Risk-Based Approach 1v2 to Machine Protection Systems.
Workshop on cryogenic & vacuum sectorisation of the SPL Vacuum Sectorisation Paul Cruikshank, CERN Technology Department (TE) Vacuum Surfaces & Coatings.
The Large Hadron Collider The 19 th Sep 2008 incident [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] NIKHEF Seminar ( )
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
News from the LHC J. Wenninger CERN Beams Department Operation Group
BEAM LOSS MONITORING SYSTEM
Powering LHC magnets version 30/3/2007.
Emergency dumping of proton and ion beams in SIS100 F
LHC schedule.
LHC : construction and operation
12 October 2009 RRB Plenary R.-D. Heuer
The LHC - Status Is COLD Is almost fully commissioned
Long Shutdown for the LHC: Vacuum Beam Pipes
Status of LHC Commissioning
Powering the LHC Magnets
Dipole circuit & diode functioning
Powering from short circuit tests up to nominal
Lecture 2 Live Feed – CERN Control Centre
Status of the BLHC ….work in progress! Mike Lamont CERN/AB 18/01/2008
The Status of the LHC machine
The LHC Accelerator Complex
Operational challenges of the LHC
BEAM LOSS MONITORING SYSTEM
Rüdiger Schmidt and Karl Hubert Mess
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
Machine Protection Xu Hongliang.
The LHC Accelerator Complex
J. Uythoven, W. Venturini Delsolaro, CERN, Geneva
6 months of beam operation in 2010
Optic design and performance evaluation for SPPC collimation systems
LHC Beam Operations Past, Present and Future
LS 1 start date 12th June Schedule Extension 2012 run Extension of 2012 run approved by the DG on 3rd July 2012.
Review of hardware commissioning
Cryogenic management of the LHC Run 2 dynamic heat loads
Presentation transcript:

LHC Status - Planck09 - Padova,IT 1 Status of the LHC Machine J. Wenninger CERN Beams Department Operation Group Acknowledgements to R. Schmidt for some slides and many discussions.

Outline LHC Status - Planck09 - Padova,IT 2 Introduction Commissioning 2008 Incident of September 19 th Repair and consolidation 2009/10 LHC run Conclusions

LHC LHC Status - Planck09 - Padova,IT 3 ATLAS CMS LHCB ALICE 7 years of construction to replace : LEP: e+e- collider 4 experiments max. energy 104 GeV circumference 26.7 km in the same tunnel by LHC : pp & ion-ion collider 4+ experiments energy 7 TeV

LHC overview LHC Status - Planck09 - Padova,IT 4 Tunnel depth m

LHC Layout LHC Status - Planck09 - Padova,IT 5  8 arcs (sectors)  8 long straight sections (700 m long): IR1 to IR8  2 separate vaccum chambers  beams cross in 4 points J. Wenninger - ETHZ - December IR6: Beam dumping system IR4: Radio frequency acceleration IR5:CMS experiment IR1: ATLAS experiment IR8: LHC-B experiment IR2: ALICE experiment Injection IR3: Collimation IR7: Collimation

ATLAS detector LHC Status - Planck09 - Padova,IT 6

CMS detector LHC Status - Planck09 - Padova,IT 7

The LHC challenge LHC Status - Planck09 - Padova,IT 8 The LHC surpasses existing accelerators/colliders in 2 aspects :  The energy of the beam of 7 TeV that is achieved within the size constraints of the existing 26.7 km LEP tunnel. LHC dipole field8.3 T HERA/Tevatron ~ 4 T  The luminosity of the collider that will reach unprecedented values for a hadron machine: LHC pp ~ cm -2 s -1 Tevatron pp3x10 32 cm -2 s -1 SppbarSpp6x10 30 cm -2 s -1 Very high field magnets and very high beam intensities:  Operating the LHC is a great challenge.  There is a significant risk to the equipment and experiments. A factor 2 in field A factor 4 in size A factor 30 in luminosity

LHC stored energy challenge LHC Status - Planck09 - Padova,IT 9 Increase with respect to existing accelerators : A factor 2 in magnetic field A factor 7 in beam energy A factor 200 in stored beam energy

To set the scale LHC Status - Planck09 - Padova,IT 10 As an indication… Few cm long groove on an SPS vacuum chamber from the impact of ~1% of a nominal LHC beam during an incident:  vacuum chamber ripped open.  3 day repair. The same incident at the LHC implies a shutdown of > 3 months.  The 11 GJ of enery stored in the magnets are sufficient to heat and melt 15 tons of Copper (~1.7 m 3 ).  The 350 MJ stored in each beam correspond to ~90 kg of TNT. Plasma-hydrodynamic simulations indicate that the beam will drill a ~30 m long hole into Copper.

Dipole magnet challenge LHC Status - Planck09 - Padova,IT 11  1232 dipole magnets.  15 m long.  Magnetic field K.  2 magnets-in-one design : two beam tubes with an opening of 56 mm.

Super-conducting magnet quench LHC Status - Planck09 - Padova,IT 12  A ‚quench‘ is the phase transition from the super-conducting to the normal conducting state.  Quenches are initiated by an energy in the order of few mJ –movement of the superconductor (friction and heat dissipation), –beam losses, –cooling failures, –any other heat sources...  When part of a magnet quenches, the conductor becomes resistive, which can lead to excessive local energy deposition due to the appearance of Ohmic losses. To protect the magnet: –the quench must be detected. –the energy in the magnet /electrical circuit must be extracted. –the magnet current has to be switched off within << 1 second. An energy density of ~1 mJ/cm 3 is sufficient to destroy super-conductivity in a magnet (quench) : a local loss of 1 ppm of the beam is sufficient !

Collimation (1) LHC Status - Planck09 - Padova,IT 13 A 4-stage halo cleaning (collimation) system is installed to protect the LHC magnets from beam induced quenches.  A cascade of more than 100 collimators is required to prevent the high energy protons and their debris to reach the superconducting magnet coils.  the collimators must reduce the energy load into the magnets due to particle lost from the beam to a level that does not quench the magnets. Operating the LHC beams is ~ 1000 more critical than TEVATRON.

Collimation (2) LHC Status - Planck09 - Padova,IT 14 1 mm ~3-5 mm The collimator opening corresponds roughly to the size of Spain !

LHC Commissioning LHC Status - Planck09 - Padova,IT 15

First dipole lowered 7 th March LHC Status - Planck09 - Padova,IT 16 Transport in the tunnel with an optically guided vehicle Approx magnets to be transported over up to 20 km at 3 km/hour

3 km long cryostats LHC Status - Planck09 - Padova,IT 17

LHC cool-down in LHC Status - Planck09 - Padova,IT 18 Cool-down time to 1.9 K ~ 4-6 weeks/sector [sector = 1/8 LHC] All sectors at nominal temperature First beam around the LHC

Magnet Commissioning LHC Status - Planck09 - Padova,IT 19 April to September 2008:  Commissioning of the magnets & circuits (power converter, quench protection, interlocks..) following predefined test steps. 1’700 circuits, 10’000 magnets  The initial target energy of 7 TeV had to be reduced to 5 TeV because of a large number of re-training quenches of the magnets from one of the three companies. All magnets were trained to 7+ TeV on test stands. This typically requires a few quenches until the coils settle. The magnets are then stored, moved to the tunnel and installed. Assumption is usually that the magnets come back to their test stand performance with no or few quenches. Turned out to be wrong for one company! Not understood !

September 10 th - control (show) room LHC Status - Planck09 - Padova,IT 20

Beam threading 21  Unique feature of LHC: threading the beam around is a tricky exercise.  After 3 days beam circulates with good lifetime, optics measured and most instrumentation operational. Beam 2

Courtesy of ATLAS ATLAS & CMS ‘events’ LHC Status - Planck09 - Padova,IT 22 Courtesy of CMS ‘Beam-on-collimator’ events Synchronized to beam timing !

September 19 th Incident LHC Status - Planck09 - Padova,IT 23

Event sequence on Sept. 19th LHC Status - Planck09 - Padova,IT 24 Introduction: on September 10 th the LHC magnets had not been fully commissioned for 5 TeV. A few magnets were missing their last commissioning steps. The last steps were finished the week after Sept. 10 th.  Last commissioning step of the main dipole circuit in sector 34 : ramp to 9.3kA (5.5 TeV).  At 8.7kA an electrical fault developed in the dipole bus bar (the bus bar is the cable carrying the current that connects all magnet of a circuit).  An electrical arc developed which punctured the helium enclosure. Secondary arcs developed along the arc. Around 400 MJ were dissipated in the cold-mass and in electrical arcs.  Large amounts of Helium were released into the insulating vacuum. In total 6 tons of He were released.

Inter-connection LHC Status - Planck09 - Padova,IT 25 Dipole busbar Vac. chamber

Pressure wave LHC Status - Planck09 - Padova,IT 26  Pressure wave propagates in both directions along the magnets inside the insulating vacuum enclosure.  Rapid pressure rise : –Self actuating relief valves could not handle the pressure. designed for 2 kg He/s, incident ~ 20 kg/s. –Large forces exerted on the vacuum barriers (every 2 cells). designed for a pressure of 1.5 bar, incident ~ 10 bar. –Several quadrupoles displaced by up to ~50 cm. –Connections to the cryogenic line damaged in some places. –Beam vacuum to atmospheric pressure.

Incident location LHC Status - Planck09 - Padova,IT 27 Dipole bus bar

Collateral damage : displacements LHC Status - Planck09 - Padova,IT 28 Quadrupole-dipole interconnection Quadrupole support Main damage area ~ 700 metres.  39 out of 154 dipoles,  14 out of 47 quadrupole short straight sections (SSS) from the sector had to be moved to the surface for repair (16) or replacement (37).

Collateral damage : beam vacuum LHC Status - Planck09 - Padova,IT 29 Clean Copper surface. Contamination with multi- layer magnet insulation debris. Contamination with sooth.  60% of the chambers  20% of the chambers Beam vacuum was affected over entire 2.7 km length of the arc.

Incident Trigger LHC Status - Planck09 - Padova,IT 30

Dipole magnets in arc cryostat  154 dipole magnets are connected together as one circuit to the power converter.  Time for the energy/field ramp is about min (energy from the grid)  Time for regular discharge (ramp down) is about the same (energy to the grid) Power Converter Energy Extraction: switch closed Magnet 3 Magnet 2Magnet 152Magnet 154Magnet 4 Energy Extraction: switch closed DFB Magnet 1Magnet 153Magnet 5 31

Dipole magnet protection Power Converter Energy Extraction: switch open Magnet 1Magnet 3Magnet 153 Magnet 2Magnet 152Magnet 154 Magnet 5 Magnet 4 Energy Extraction: switch open DFB  Quench detected: energy stored in magnet dissipated inside the magnet (time constant of 200 ms).  Parallel diode becomes conducting: current of other magnets through diode.  Resistances are switched into the circuit: up to 1 GJ of energy is dissipated in the resistances (current decay time constant of 100 s). Bus-bar must carry the current for some minutes, through interconnections 32

One of ~1700 bus-bar connections LHC Status - Planck09 - Padova,IT 33

Bus-bar joint (1) LHC Status - Planck09 - Padova,IT 34  Superconducting cable embedded in Copper stabilizer.  Bus bar joint is soldered (not clamped).  Joint resistance ~0.35 n  1.9 K).  Protection of the joint during quench relies on good joint quality. ~2 cm

Bus-bar joint (2) LHC Status - Planck09 - Padova,IT 35  A post-mortem analysis of the data from the sector with the incident revealed the presence of a 200 n  non-conform resistance in the cell of the primary electrical arc. This acted as a heat source that quenched the superconducting cable. >> Unfortunately the evidence is destroyed…  A careful inspection of many other joints revealed non-conformities like bad soldering and.or reduced electrical contact as in the example to the right.

superconducting cable with about 12 mm2 copper copper bus bar 280 mm2 Magnet  Everything is at 1.9 Kelvin.  Current passes through the superconducting cable. For 7 TeV : I = 11’800 A Normal interconnect, normal operation Interconnection joint (soldered) This illustration does not represent the real geometry current 36 Helium bath

copper bus bar 280 mm2 Magnet  Quench in adjacent magnet or in the bus-bar.  Temperature increase above ~ 9 K.  The superconductor becomes resistive.  During the energy discharge the current passes for few minutes through the copper bus-bar. superconducting cable interconnection Normal interconnect, quench 37

copper bus bar 280 mm2 Magnet  Interruption of copper stabiliser of the bus-bar.  Superconducting cable at 1.9 K  Current passes through superconductor. Non-conform interconnect, normal operation superconducting cable interconnection 38

copper bus bar 280 mm2 Magnet  Interruption of copper stabiliser.  Superconducting cable temperature increase to above ~9 K and cable becomes resistive.  Current cannot pass through copper and is forced to pass through superconductor during discharge. superconducting cable interconnection Non-conform interconnect, quench. 39

copper bus bar 280 mm2 Magnet  The superconducting cable heats up because of the combination of high current and resistive cable. superconducting cable interconnection Non-conform interconnect, quench. 40

copper bus bar 280 mm2 Magnet  Superconducting cable melts and breaks if the length of the superconductor not in contact with the bus bar exceeds a critical value and the current is high.  Circuit is interrupted and an electrical arc is formed. superconducting cable interconnection Non-conform interconnect, quench. Depending on ‘type’ of non-conformity, problems appear :  at different current levels.  under different conditions (magnet or bus bar quench.. ). 41

copper bus bar 280 mm2 Magnet  Anomalous resistance at the joint heats up and finally quenches the joint.  Current sidesteps into Copper that eventually melts because the electrical contact is not good enough. September 19 th hypothesis superconducting cable quench at the interconnection 42 >> New protection system will be installed to anticipate such incidents in the future,

Repair and consolidation LHC Status - Planck09 - Padova,IT 43

Repair (I) LHC Status - Planck09 - Padova,IT 44  39 dipoles and 14 quadrupoles short straight sections (SSS) brought to surface for repair (16: 9D + 7SSS) or replacement (37: 30D + 7SSS). All magnets are back in the tunnel. Interconnection work ongoing.  A method to localize a bad quality joints by measuring the resistance of the copper cable (+joint) has revealed to be very powerful. - Ongoing race to identify and repair faulty joints. - Unfortunately poor quality joints are localized in many places – likely to slow down progress with the machine re-commissioning. - ½ LHC is still cold (<= 80 K)…  The vacuum chambers are cleaned in situ.

Repair (II) and consolidation (I) LHC Status - Planck09 - Padova,IT 45  Major upgrade of the quench protection system. - Protection of all main quadrupole and dipole joints. - High statistics measurement accuracy to < 1 n . - Installation of > 200 km of cables, production of thousands of electronic boards. >> protection against similar issues in the future.  Reinforcement of the quadrupole supports.  Improvement of the pressure relief system to eventually cope with a maximum He flow of 40 kg/s in the arcs (maximum conceivable flow, 2 x incident).

LHC run 2009/ LHC Status - Planck09 - Padova,IT 46

LHC Experiments Desiderata LHC Status - Planck09 - Padova,IT pb -1 of good data at  s = 10 TeV. Many new limits set on hypothetical particles pb -1 of good data at  s = 10 TeV. Start competing with Tevatron on Higgs masses ~ 160 GeV/c 2. 1 fb -1 of good data at  s = 10 TeV. Higgs discovery possible ~ 160 GeV/c 2.

Luminosity Targets 2009/ LHC Status - Planck09 - Padova,IT 48  Operation modes for 2009/10.  Short Pb ion run foreseen end Ion setup should be ‘straight forward’ as little difference wrt protons.  Present 4-stage collimation system limits the total intensity to  10% of the nominal intensity. No. bunches/ beam Protons/ bunch % of nominal intensity Peak L (cm -2 s -1 ) 43 5  x  x  x (50 ns) 5  x  x10 34 Int. luminosity target achievable with ~40% availability Design

Outlook (1) LHC Status - Planck09 - Padova,IT 49  With beam the LHC is a wonderful machine (at injection). All key systems were operational, very efficient beam startup.  The incident in sector 34 was due to a poor quality bus-bar joint. Good understanding of the incident mechanism. Quench protection system upgrade under way – largely improved protection for the future. Large quality control campaign on joint underway – is revealing localized issues in a number of places.  Sector 34 repair is progressing well, re-commissioning will start soon.

Outlook (2) LHC Status - Planck09 - Padova,IT 50  Cool-down of the first sectors has started. First magnet powering in June.  Beam commissioning scheduled to resume in September or October Followed by a 12 months run over winter. Schedule is very tight. Physics energy target so far still 5 TeV.

Reserve slides LHC Status - Planck09 - Padova,IT 51

Superconducting cable LHC Status - Planck09 - Padova,IT 52  1 mm  6  m Typical value for operation at 8T and 1.9 K: 800 A Rutherford cable width 15 mm A.Verweij NbTi filaments embedded in a Copper matrix

LHC dump block LHC Status - Planck09 - Padova,IT 53 Approx. 8 m concrete shielding beam absorber (graphite) concrete shielding beam absorber (graphite)  This is the ONLY element in the LHC that can withstand the impact of the full beam !  The block is made of graphite (low Z material) to spread out the hadronic showers over a large volume.  It is actually necessary to paint the beam over the surface to keep the peak energy densities at a tolerable level !

LHC cycle LHC Status - Planck09 - Padova,IT 54 energy ramp preparation beam dump injection collisions 450 GeV 7 TeV start of the ramp 15/12/2008ITER-CERN WS - J. Wenninger Dipole current (A)