AMS Tracker Meeting31/01/06 Eric Perrin (GE) on behalf of the Tracker group Tracker mechanics at Uni -Ge Safety issues Assembly Still to be made.

Slides:



Advertisements
Similar presentations
SCT BARREL PAR - RAL May 2003 Status of Barrel Mechanical Structures - Cylinder manufacture - Bracket and small components manufacture - Dry assembly.
Advertisements

ATLAS Pixel Detector February 2003 N. Hartman LBNL 1 Pixel Support Tube PRR: Assembly, Production, Schedule February 2003.
AMS-02 Cryosystem Phase III Flight Safety Review January 12, 2010 Phil Mott.
THERMO-MECHANICAL TESTS ON TRACKER LADDERS (Low temperature problem on plane 1) Status Report: D.Rapin Sept 26,2012 (help from Giovanni, Franck, Mingming,...)
G.Barber Tracker Planning & Mechanical Preparation June Tracker Planning & Mechanical Preparation An outline of (known) outstanding work to be carried.
AMS-02 tracker mechanics status of assembly and integration at UniGe Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop.
AMS-02 tracker mechanics status of assembly and integration Inner tracker integration completion: - Assembly and cabling - Temperature and magnetic field.
AMS tracker hardware status (mechanics and cabling) Divic RAPIN, UniGe AMS splinter tracker, Septidi 7 Brumaire 217 (october 28, 2008) off-line operations.
AMS-02 tracker mechanics status of construction, assembly, integration Production: - Ladder integration - Installation on planes Inner tracker assembly:
Background to the current problem 1. As a result of the high stresses in the bobbin due to the magnet load, the bobbin end plate needs to be increased.
CERN, November 25, 2003 – Technical Board Support chariot for ITS & FMD services on the RB24 side Foreward –This presentation reports the current ideas.
SPACE FRAME Interface between the LGT and the IST 21/06/2011 Marco Ciapetti.
ZQNA Electrostatic Quadrupoles for ELENA Transfer Lines 1.Conceptual design 2.Performance 3.Engineering details 4.Interfaces 5.Production planning D. Barna,
Reproduction interdite © ALMA EUROPEAN CONSORTIUM Reproduction forbidden CRE Policy, Labelling 2006/06/22 - Toulouse ANTD SFP Page 1 Design,
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
Engineering Division 1 Mechanical and Integration CD0 Walkthru, 19-Dec, 2007 Eric Anderssen, LBNL.
1 AMS-02 Integration & Test Plans & Status Trent Martin 24 January, 2007.
VELO workshop, Amsterdam, april ‘00M.Ferro-Luzzi Difficulties with current mechanical design recent FEA results: to obtain sufficient stiffness of center.
Update on alignment kit and stave 250 frame M.Gibson (RAL) 1.
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Section Mechanical Systems X-LAT Assy1 GLAST Large Area Telescope: Mechanical.
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Document: LAT-PR-0XXXX Section 5.1 Grid Box Design 1 GLAST Large Area Telescope:
CLASSE prototype: mechanical concepts G. De Michele, EPFL-PSI-CERN on behalf of CERN team SLAC, 16 th April, 2012.
Design Progress Allen Ellis 18-September
09/03/2010 ADO-PO section meeting Beam Pipe Extraction/Insertion R. Vuillermet.
G.Barber KEK Test Beam Update, Berkeley 9 Feb KEK Test Beam – Tracker Progress Contents:- Station Space Frame Light Guide Map Station Connectors.
Neil JacksonUK-V RAL 8th September Module to Disc Assembly Infrastructure –Services and test box –Evaporative cooling system –Disc Handling Tests.
1 AMS-02 Integration & Test Plans & Status Ken Bollweg/NASA John Heilig/JS Robert Becker/MIT 12 January, 2007 AMS JSC.
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Section Mechanical Systems Radiator Assy1 GLAST Large Area Telescope: Mechanical.
AMS-02 tracker mechanics status of construction, assembly, integration Ladder assembly Ladder installation on planes Integration details, cooling loop,
Regional Meeting on Applications of the Code of Conduct on Safety of Research Reactors Lisbon, Portugal, 2-6 November 2015 Diakov Oleksii, Institute for.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
RICH1 Gas Enclosure Installation. Experimental Area Meeting at CERN on 21st June 2006 Bill Cameron (Imperial College London) on behalf of the RICH1 team.
LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015.
Status of Anti project. F. Raffaelli,A. Checchetti,C. Capoccia. INFN CERN, July 14 th, Status of the Anti construction test and schedule. -Status.
G.Barber Mice Tracker Mechanical Progress Tracker Mechanical Progress Contents:- Station Space Frame Station Layout Light Guide Map Connectors Patch.
G.Barber Mice Tracker Integration Harbin Jan Mice Tracker Integration Installation requirements & Procedure.
SLHC Engineering Upgrade FCAL Remove-Install step by step procedure. Mircea Cadabeschi-University of Toronto March 01,
1 03/21/2006 GLAST CU Beam Test Workshop Scanning Table.
LAT Transport Container1 GLAST LAT Project8 September 2005 LAT Transport Container Design Review 8 September 2005 LAT Transport Container Design Review.
Lavs Issues Lav 12. Tube Planning future activities. Conclusions.
OLAV3 Engineering Integration and installation of experimental beam pipes: the case of LHC 7/8/20111P.Lepeule for VSC group.
AMS-02 Delta CDR Structural Analysis and Certification Process Carl Lauritzen Structural Analysis Lead Jacobs Engineering
Walter Sondheim 6/9/20081 DOE – Review of VTX upgrade detector for PHENIX Mechanics: Walter Sondheim - LANL.
CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Update ME4/2 Chambers and Tooling A construction of new ME4/2 prototype at CERN Factory tooling,
PHASE II FLIGHT-SAFETY REVIEW AMS-02 EXPERIMENT sub-detector SILICON TRACKER Roberto Battiston - AMS-02 Phase II Safety Review - Houston JSC May 21-25,
LAT Design Integration and Analysis1 GLAST LAT Project24 May 2005 LAT Monthly Status Review 24 May 2005 Design Integration and Analysis LAT Monthly Status.
CLIC Permanent Magnet Quadrupole Engineering Development update Norbert Collomb, STFC Daresbury Laboratory 1N. Collomb 03/10/2011.
G.Barber Mice Tracker Mechanical Ral June Tracker Mechanical Update Contents:- Station Space Frame Station Layout Connectors Patch Panel Still to.
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Document: LAT-PR-0XXXX Section 5.3 Fab & Assy Plans 1 GLAST Large Area Telescope:
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
Tomelleri S.r.l. ® Copyright 2007 © ASTRONOMY AND RESEARCH July 23rd 2008 VST Meeting1.
AMS Tracker Meeting17/10/05 Eric Perrin (GE) Tracker mechanics at Uni -Ge Safety issues Assembly Still to be made.
Meeting at Chooz PMTs Mechanical support on the Buffer. Updates. Enrique Calvo Alamillo
Chamber mechanics Chamber mechanics Production in China Peking University Group – 20 Aug
SPHENIX MECHANICAL D. Lynch August 21, /15/2014sPHENIX Mechanical Design.
Tracker cooling plant refurbishment Project status Revised plan Financial impact.
SVD QCG Report F.Forti. Outline Sep 09, 2015QCG Report, F.Forti2 view/Detector/SVD/SvdQCQAGrou p.
USCMS Pixel PMG, Nov 29, Mechanics Status Disks, ½ Service Cylinders Installation USCMS FPIX FNAL PMG Joe Howell Bruno Gobbi Nov. 29, 2006.
24 September 2012 Immanuel Gfall (HEPHY Vienna) SVD Status of Mechanics PXD-SVD Meeting Göttingen.
24 September 2012 Immanuel Gfall (HEPHY Vienna) Annekathrin Frankenberger (HEPHY Vienna) SVD Status of Mechanics PXD-SVD Meeting Göttingen.
K.Long/G.Barber Mice Tracker Mechanical Status CM20 Feb 08 1 Mice Tracker Mechanical Status Contents:- Tracker 1 Status Tracker 2 Status Further Hardware.
Baby-MIND Modules & Services
Update on PANDA solenoid design
GLAST Large Area Telescope:
Service channels between Tracker and PP1
Internal review of IR2 LEP cryostats (WP11/WP5) Close out session
Discussion items SVD mechanics session.
DOM Integration Meeting D. Vivolo - DOM Integration Meeting
Far Detector Activities Late 2017 – Early 2018
Remote Handling Workshop Introduction
Presentation transcript:

AMS Tracker Meeting31/01/06 Eric Perrin (GE) on behalf of the Tracker group Tracker mechanics at Uni -Ge Safety issues Assembly Still to be made

Bolt analysis Has been done for the 6 Tracker structural joints. - ISAtec extracted maximum loads on bolts from the Tracker FEA model - For the different load cases, as specified in the structural verification plan. - Arndt Schultz von Dratzig (Aachen) gave useful recommandations. - Antonio Alvino (SERMS, Terni) performed the bolt analysis itself on Mathcad. - For 5 joints, slight improvements were needed. A change for stronger bolts or nuts solved the problem. These joints declared Fail-safe by engineering judgement. - In the case of the Tracker feet to Tracker shell joints, further calculations of the loads on each bolt was needed and analysis re-made. The « outer bolt » still exhibits a negative margin of safety on joint separaration. Seems acceptable. 2 cases of Fail safe analysis done: a) 7/8 tracker feet b) highest loaded bolt removed. - All documents at: A memo has been submitted to Jacobs Sverdrup. Approval needed to : - Start Tracker assembly - Procure new fasteners - Finalize Tracker feet

The bolts chosen for joint 2 require small changes to be done to the Tracker feet. Change to be implemented before fabrication

Tracker fastener list and back off prevention method List delivered to Jacobs Sverdrup Has been updated for structural fasteners (Appendix to Memo) Back-off prevention method defined - Two cases: i) Contained small fasteners : Vibratite accepted ii) Other : Vibratite not accepted ==> Mylar patch or self locking insert Several small modifications in existing parts were or are still needed. Fracture of composites Memo delivered to Jacobs Sverdrup. Item closed Material list Delivered to Jacobs Sverdrup - Still some issues: - Some al. alloy plates to be surface treated in-situ. Alodine 1132 pen received. Coating still to be done. - Stress report demanded for a few components prone to stress corrosion. (ladder feet, inserts ) Work in progress (EP)

Sehr geehrter Herr Perrin, die rechnerische Abschätzung der Composite-Belastung für die Verbindung zwischen Tracker Shell und Conical Flange, Joint 2, ergibt für die Komponente Support Flange einen Margin of Safety von 0.39 und für die Komponente Tracker Shell einen Margin of Safety von Beide Werte berücksichtigen einen Sicherheitsfaktor von 2. Der Nachweis der Composite-Festigkeit ist damit erbracht. Dabei ist der ungünstige Fall betrachtet worden, dass nur die 0/90-Grad Lagen tragen. Die ± 45-Grad Lagen wurden im Sinne einer zusätzlichen Sicherheit vernachlässigt. Die zu Grunde gelegte Kraft beträgt 5315 N. Sie resultiert aus LC 2 und wirkt auf eine äußere Schraube. Zusammen mit einem Sicherheitsfaktor 2 ist dieser Fall schlimmer, als der max. Fail Safe Fall, FS LC 2 mit 9363 N, da hier nur ein Sicherheitsfaktor von 1 angewendet wird. Die zulässigen Werte sind dem derzeit gültigen ESA Insert Design Handbook (ESA PSS Issue 1, June 1987, Fig für eine HM-Faser unter Kompression) entnommen worden. Die verwendeten Werte korrespondieren gut mit Contraves-Daten für HM UD-Laminate unter Drucklast. Für Rückfragen stehen wir gerne zur Verfügung! Mit freundlichen Grüßen ISATEC GmbH i.A. Frank Miehlich Isatec also verified that the stronger bolts with higher preload used for joint 2 were nor creating problems for the composite parts themselves

We suggested to Bruce Sommer or one of his colleague to present the safety related items in the TIM Tracker session. See answer ( ) below: Eric I’ve spoken with Leland and Paul regarding your request that we present a short presentation during the tracker presentations. It is our opinion that there is really not any significant safety or structural issues regarding the Tracker that would warrant a formal presentation. Quite frankly the Tracker is in great shape. The bolt issues have all been resolved, you’ve provided us with the necessary certificates of compliance for the composites and honeycomb components of the tracker and we have the necessary information to go forward to the Safety Panel for the Phase II Safety review. At the most we could have Paul stand up and mention that to everyone if thats what youre looking for Let us know, Regards Bruce

Tracker assembly at Uni-GE The Tracker Assembly Frame (TAF) « Frankenstein machine » has been moved into the « Veranda » Modifications started: - Remove / reposition telescopic supports for inner planes. - Build adapters for conical flanges

Assembly of the inner tracker at UniGe Proposed set-up for storage & insertion into the magnet. The various lengths of the cables were calculated. Cables are in UniGe Cables must be installed before the supporting shells. Extra length must be attached to temporary supports. Divic Rapin

Dry assembly of parts partly done

Assembly Inner Tracker assembly can start as soon as : - The three inner planes are complete and released for assembly  Done ---- Request for exhibiting two planes at CERN end of Feb ?? - Bolt analysis has been closed. - Assembly equipment is ready. To minimize the risks, and the time the Tracker has to stay in the Veranda, we have decided to delay slightly the start of this assembly: - To finish assy equipment. - To verify that the Tracker cable fixations inside the Tracker volume is adequate. ==> Some further vibration tests needed. - Star Tracker lower supports will be available early March to be bonded to the top conical flange. We plan to do this operation in situ.

Assembly procedure for inner Tracker This procedure is clear, except for some details still needing tuning, specially in view of risk minimizing. These points will be discussed and decided in a GE-Tracker Meeting in the next 2-3 weeks. - Mount the top conical flange into the TAF. - Transfer the 3 inner planes into the TAF in order P2, P3 and P4. - Add ladder protection. - Mount the bottom conical flanges into the TAF. - Adjust the position of the planes and connect thermal connectors. - Mount top and bottom cable support structure. - Mount and connect cables on ladders of three external rows +Y and -Y. - Test cable - ladder connections - Mount the two 100° shell sectors - Mount and connect all other cables - Test cable - ladder connections - Mount the two 80° shell sectors - Arrange cables on cable support structure. - Inner Tracker ready to be tranported to CERN Inner Tracker assembly ==> Duration ~2.5 months CERN clean room ready ==> end of 2006 Subdetectors expected at CERN ==> April 2007

In parallele, the two outer planes will be equipped with ladders P5 completed with ladders  ~Mid March 2006 P1 completed with ladders  ~End of April 2006 (Tests are not accounted for )

Still a lot of things to finalize / fabricate - Tracker feet --- Modifications for joint 2 bolts, --- Production drawings --- Specification, organise quotation --- Place order and follow fabrication - Procure fasteners which need to be replaced - Light tightness at exit of conical flange and around the Tracker feet - Cable clamping Structure to support cables outside the Tracker Paddle on Vacuum case (Design A. Alvino) Clamp at Vacuum case edge (Design A. Alvino) Balcony in front of Tracker crates - Container for Inner Tracker. - Dry assembly of evaporators - Etc...

Further assembly steps / parts needed - Redo some bracketry for new evaporators in two parts ? ==> Details to be discussed and agreed with Bart soon - Mount outer evaporator rings to P1 and P5 - Modify (if possible) outer plane containers to be compatible with evaporators For integration - Integration procedure - Inner Tracker handling gear - Installation jig for Inner evaporator (design A. Alvino) - Cable « paddle » and clamps on Vacuum case (design A. Alvino) - Cable balcony for Tracker crates. Miscellaneous: - Prototype condenser (made) - Parts for heat exchanger