P.-R. KettleMEG-Review July 20041 MEG Beam Line Studies  E5 Z-Branch Collaborative Effort !!! Effort !!!  E5 Z-Branch Collaborative Effort !!! Effort.

Slides:



Advertisements
Similar presentations
PEPPo Weekly Status Meeting February 16, 2011 & 6MSD Planning Meeting February 23, 2011 Part 1 – Technical summary of layout Part 2 – Month-by-Month Installation.
Advertisements

1 MICE Beamline: Plans for initial commissioning. Kevin Tilley, 16 th November. - 75days until commissioning Target, detectors, particle production Upstream.
Preliminary studies for T2 primary target for the NA61 fragmentation beam run 11 th October 2010 – NA61 Collaboration Meeting M. Calviani on behalf of.
Peter-Raymond Kettle MEG Review February Cockcroft-Walton Status Carlo Bemporad Angela Papa Giovanni Signorelli Peter-Raymond Kettle Carlo Bemporad.
COBRA Magnet Test Milestone AssemblyDesignManufactoring DesignAss.TestWinding & Cryo. Deliv. PSI Test Platform Calibration Mapping device.
P.-R. KettleMEG-Review February MEG Beam Line Studies  E5 Z-Branch NOW !!! NOW !!!
P.-R. KettleMEG Review July MEG Beam Line Studies.
Pair Spectrometer Design Optimization Pair Spectrometer Design Optimization A. Somov, Jefferson Lab GlueX Collaboration Meeting September
P.-R Kettle MEG Review February Beam Line & Target Status Topics to be Addressed: Results of Beam Line Commissioning Phase Results of Beam.
1 G4MICE studies of PID transverse acceptance MICE video conference Rikard Sandström.
Progress on the final TWIST measurement of James Bueno, University of British Columbia and TRIUMF on behalf of the Triumf Weak Interaction Symmetry Test.
Beam line summary paul drumm for beam line group.
Status report about the e-  identifier Study of shielding against the stray magnetic field at the downstream end of the spectrometer F. Huveneers, Gh.
Downstream e-  identification 1. Questions raised by the Committee 2. Particle tracking in stray magnetic field 3. Cerenkov and calorimeter sizes 4. Preliminary.
Dec 2005Jean-Sébastien GraulichSlide 1 Improving MuCal Design o Why we need an improved design o Improvement Principle o Quick Simulation, Analysis & Results.
1 PSI 27/6/2006 C.Bemporad “THE TAMING OF MEG” News on Calibration Methods Cockcroft-Walton Accelerator  -sources on wire  -lines from neutron capture.
Genova/Pavia/Roma Flavio Gatti, PSI, July 1st, Timing Counter july 2004.
Status of IPBSM Improvement N. Terunuma, KEK 2012/July/13 ATF2 Weekly Meeting.
COBRA Magnet Test Milestone AssemblyDesignManufactoring DesignAss.TestWinding & Cryo. Deliv. PSI Test Platform Calibration Mapping device.
Malte HildebrandtMEG Review Meeting, 14th February 2007 Report of Run Coordinator Run 2006 Summary Malte Hildebrandt MEG Review Meeting, 14th February.
The PEPPo e - & e + polarization measurements E. Fanchini On behalf of the PEPPo collaboration POSIPOL 2012 Zeuthen 4-6 September E. Fanchini -Posipol.
HLab meeting 10/14/08 K. Shirotori. Contents SksMinus status –SKS magnet trouble –Magnetic field study.
P.-R Kettle MEG Review July Beam Transport & Target Systems BTS Success Novosibirsk 24/5/ : A 300 A.
Emittance measurement: ID muons with time-of-flight Measure x,y and t at TOF0, TOF1 Use momentum-dependent transfer matrices to map  path Assume straight.
ハイパー核ガンマ線分光用 磁気スペクトロメータ -SksMinus- 東北大学 大学院理学研究科 白鳥昂太郎 ATAMI.
TWIST Measuring the Space-Time Structure of Muon Decay Carl Gagliardi Texas A&M University TWIST Collaboration Physics of TWIST Introduction to the Experiment.
HKS Analysis Status Report HKS Analysis Status Report Liguang Tang (Hampton/JLAB) Hall C User Meeting, Jan. 15, 2011 HKS has data taken in 2005 (E01-011)
2 1/March/2015 日本物理学会大70回年次大会@早稲田大学 東大ICEPP 内山雄祐 他 MEG II collaboration.
Analysis strategy of high multiplicity data Toshiyuki Gogami 24/Feb/2011.
MEG positron spectrometer Oleg Kiselev, PSI on behalf of MEG collaboration.
1 W.Ootani ICEPP, University of Tokyo MEG experiment review meeting Feb , PSI W.Ootani ICEPP, University of Tokyo MEG experiment review meeting.
MICE Beam-line and Detectors Status Report 16 th October 2009 Chris Booth The University of Sheffield.
Karsten Büßer Beam Induced Backgrounds at TESLA for Different Mask Geometries with and w/o a 2*10 mrad Crossing Angle LCWS 2004 Paris April 19 th 2004.
SHMS Optics Studies Tanja Horn JLab JLab Hall C meeting 18 January 2008.
TWIST A Precision Measurement of Muon Decay at TRIUMF Peter Kitching TRIUMF/University of Alberta TWIST Collaboration Physics of TWIST Introduction to.
PSI July 2002MuEGamma Review Meeting1 Beam Line Status update 1.  E5 Test Beam Overview : Aims + RequirementsAims + Requirements Zone Layout + Measurement.
COBRA Magnet Status W. Ootani June 27th, 2006 MEG Review W. Ootani June 27th, 2006 MEG Review.
S. Kahn 5 June 2003NuFact03 Tetra Cooling RingPage 1 Tetra Cooling Ring Steve Kahn For V. Balbekov, R. Fernow, S. Kahn, R. Raja, Z. Usubov.
Peter-Raymond Kettle Tokyo - Topical Meeting, March Beam Monitoring Basis for Discussion only Beam Rate Beam Rate Beam Profile Beam Profile Beam.
1 HBD update Itzhak Tserruya DC Upgrades meeting, January 14, 2005 NIM paper II: Generic R&D ~ completed Full scale prototype construction Pending issues.
SksMinus status Hyperball collaboration meeting 2009/3/11 K. Shirotori.
Overview of Booster PIP II upgrades and plans C.Y. Tan for Proton Source group PIP II Collaboration Meeting 03 June 2014.
Geant4 Simulation of the Beam Line for the HARP Experiment M.Gostkin, A.Jemtchougov, E.Rogalev (JINR, Dubna)
Peter-Raymond Kettle MEG Review February BeamBeam LineLine StatusStatus.
Overview of the experiment Collaboration (about 30 physicists at this meeting) Budget Realistic schedule and general status (few words) of each sub-detector.
Magnetized hadronic calorimeter and muon veto for the K +   +  experiment L. DiLella, May 25, 2004 Purpose:  Provide pion – muon separation (muon veto)
COMET. μ-e conversion search from muonic aluminium J-PARC pulsed proton beam to produce pulsed muon beam Forbidden in the Standard Model  clue to the.
RF source, volume and caesiated extraction simulations (e-dump)
00 Cooler CSB Direct or Extra Photons in d+d  0 Andrew Bacher for the CSB Cooler Collaboration ECT Trento, June 2005.
P.-R. KettleMEG Review January MEG – Beam Line Studies Present Status & Overview since July 2002.
CBM-Meet, VECC July 21, Premomoy Ghosh CBM – MUCH Simulation for Low-mass Vector Meson Work done at GSI during June 2006.
J-PARC でのハイパー核ガンマ線分光実験用 散乱粒子磁気スペクトロメータ検出器の準備 状況 東北大理, 岐阜大教 A, KEK B 白鳥昂太郎, 田村裕和, 鵜養美冬 A, 石元茂 B, 大谷友和, 小池武志, 佐藤美沙子, 千賀信幸, 細見健二, 馬越, 三輪浩司, 山本剛史, 他 Hyperball-J.
The Luminosity Calorimeter Iftach Sadeh Tel Aviv University Desy ( On behalf of the FCAL collaboration ) June 11 th 2008.
Mu to e Meeting BNL, June 2006 Extinction requirement relaxation (Kevin O’Sullivan) Stopping Target Geometry (Cenap Ozben, David Morse) Yannis Semertzidis.
1 COBRA Magnet Status W.Ootani MEG Experiment Review Meeting, Jul W.Ootani MEG Experiment Review Meeting, Jul
Electron Spectrometer: Status July 14 Simon Jolly, Lawrence Deacon 1 st July 2014.
Xenon Delivery Japan 1 MCHF 575 kCHF granted Additional grant 656 kCHF Last 50l subject to negotiation.
A. Baldini PSI July 05 Overview of the experiment MEG is being built (Beam line, Magnet, LXe, DC, TC, Elect., Software) Delays in some items: O(months)
Status of physics analysis Fabrizio Cei On Behalf of the Physics Analysis Group PSI BVR presentation, February 9, /02/2015Fabrizio Cei1.
g beam test of the Liquid Xe calorimeter for the MEG experiment
Options and Recommendations for TL and Dumps
Target and Horn status report
ELENA Extra Low ENergy Antiproton Ring
K. Tilley, ISIS, Rutherford Appleton Laboratory, UK Introduction
Advanced Research Electron Accelerator Laboratory
GEANT Simulations and Track Reconstruction
(Beam) Commissioning Plan
IR Beam Transport Status
IR/MDI requirements for the EIC
Plans for future electron cooling needs PS BD/AC
Presentation transcript:

P.-R. KettleMEG-Review July MEG Beam Line Studies  E5 Z-Branch Collaborative Effort !!! Effort !!!  E5 Z-Branch Collaborative Effort !!! Effort !!!

P.-R. KettleMEG-Review July Topics to be Addressed Overview Overview Current Component Status Current Component Status Beam spot size Beam spot size Summary / Conclusions Summary / Conclusions Beam Line Commissioning Schedule Beam Line Commissioning Schedule Overview Overview Current Component Status Current Component Status Beam spot size Beam spot size Summary / Conclusions Summary / Conclusions Beam Line Commissioning Schedule Beam Line Commissioning Schedule

P.-R. KettleMEG-Review July Beam Line Overview Beam Line Objectives Couple ‘Z’-Branch elements in shielding to the detector i.e. COBRACouple ‘Z’-Branch elements in shielding to the detector i.e. COBRA Stop maximum number of μ + in thinnest target with minimal background contaminationStop maximum number of μ + in thinnest target with minimal background contamination  No Iron allowed in vicinity COBRA → Solenoid coupling  28 MeV/c surface μ + beam with high transmission efficiency → Rate  Reject beam e + background e + /μ + ~ 10 →Wien Filter  Small beam spot size at target in COBRA → careful optics + collimator system + solenoid  Thin slanted target min. thickness for  → 37 mg/cm 2 CH 2 Tg at 22  + degrader system → 37 mg/cm 2 CH 2 Tg at 22  + degrader system Beam Line Objectives Couple ‘Z’-Branch elements in shielding to the detector i.e. COBRACouple ‘Z’-Branch elements in shielding to the detector i.e. COBRA Stop maximum number of μ + in thinnest target with minimal background contaminationStop maximum number of μ + in thinnest target with minimal background contamination  No Iron allowed in vicinity COBRA → Solenoid coupling  28 MeV/c surface μ + beam with high transmission efficiency → Rate  Reject beam e + background e + /μ + ~ 10 →Wien Filter  Small beam spot size at target in COBRA → careful optics + collimator system + solenoid  Thin slanted target min. thickness for  → 37 mg/cm 2 CH 2 Tg at 22  + degrader system → 37 mg/cm 2 CH 2 Tg at 22  + degrader system  E5 Area

P.-R. KettleMEG-Review July Beam Line Overview Contd.  Triplet I  Wien Filter E^B Separator  Triplet II  Triplet I  Wien Filter E^B Separator  Triplet II  Collimator system  Beam Transport Solenoid BTS  Degrader + Collimator system  Target system + He-Bag System  Collimator system  Beam Transport Solenoid BTS  Degrader + Collimator system  Target system + He-Bag System

P.-R. KettleMEG-Review July Recap Previous Main Results Triplet 2 1 Solenoid WIEN Filter Colli. Trip. µ+µ+µ+µ+ e+e+e+e+ e+e+e+e+ µ+µ+µ+µ+ Integrated Rate After Separator 4cm 1800µA N µ ~9.4·10 7 µ + /s (1.7·10 8 µ+/s 6cm Tg.) N e /N µ > 9 N e ~ 8.7·10 8 e + /s Transmission Factors T Sep = (71±5)% T Colli = (90±5)% Integrated Rate After Separator 4cm 1800µA N µ ~9.4·10 7 µ + /s (1.7·10 8 µ+/s 6cm Tg.) N e /N µ > 9 N e ~ 8.7·10 8 e + /s Transmission Factors T Sep = (71±5)% T Colli = (90±5)% Integrated Rate 4cm 1800µA N µ ~1.3·10 8 µ + /s (2.3·10 8 µ+/s 6cm Tg.) Integrated Rate 4cm 1800µA N µ ~1.3·10 8 µ + /s (2.3·10 8 µ+/s 6cm Tg.) “Z-Branch” P cent =(28.2±0.1)MeV/c ΔP/P =(7.9±0.6)% FWHM P Beam =(28.2±0.9)MeV/c Consistent with TURTLE & P-Slit settings/Calib. P-Spectra:  -Kinematic Edge (29.79 MeV/c) P-Spectra:  -Kinematic Edge (29.79 MeV/c) Theoretical func. P 3.5 folded with Gaussian ΔP/P + Const. Cloud µ + contribution

P.-R. KettleMEG-Review July Previous Main Results contd… Integrated Rate After PSC Solenoid !!! 4cm 1800µA N µ ~6.1·10 7 µ + /s (1.1·10 8 µ+/s 6cm Tg.) Beam Spot: σ X ~ 5.3 mm σ Y ~ 6.5 mm Transmission Factor Solenoid T Sol = 71 % Integrated Rate After PSC Solenoid !!! 4cm 1800µA N µ ~6.1·10 7 µ + /s (1.1·10 8 µ+/s 6cm Tg.) Beam Spot: σ X ~ 5.3 mm σ Y ~ 6.5 mm Transmission Factor Solenoid T Sol = 71 % With larger Bore i.e. BTS T>71% Integrated Rate 4cm 1800µA N µ ~8.5·10 7 µ + /s (1.5·10 8 µ+/s 6cm Tg.) Integrated Rate 4cm 1800µA N µ ~8.5·10 7 µ + /s (1.5·10 8 µ+/s 6cm Tg.) Triplet 2 1 Solenoid WIEN Filter Colli. Trip. µ+µ+µ+µ+ e+e+e+e+ e+e+e+e+ µ+µ+µ+µ+ µ/e Separation 11.8cm 7.2σ !!! µ/e Separation 11.8cm 7.2σ !!!

P.-R. KettleMEG-Review July Degrader & Stopping Distribution Measurements µ+µ+µ+µ+ CH 2 Tg e+e+e+e+ Foils CH 2 at focus Michel Range Curve using NaI: Measurement  Simulation Fix Degrader 600 µ GEANT say 580µ Nearly all Stopped in 400µ R ~ 870 µ CH 2 Degrader Target AIR Target Thickness vs. NaI Rate VAC Target Gives R Mean = 1150µ Equiv GEANT + TRIM 88% STOP in 400µ Tg !!! Solenoid Fix Degrader Var. Tg 88% stopped in 400µ CH 2 Tg.

P.-R. KettleMEG-Review July Component Status Beam Line Commissioning Started – Beam Line Commissioning Started –   E5 Zone totally refurbished, primary installation work – Completed  LHe + LN 2 Transfer Lines to zone – Design close to finished ready for ordering Triplet I Separator II Triplet II BTS-Solenoid New Old + New New New New Old + New New New Completed Completed PSCPSC PSC shown here

P.-R. KettleMEG-Review July Current Component Status – Triplet I Triplet I: FINISHEDTriplet I: FINISHED - Constructed from QSB Quadrupole magnets μE4 Triplet I: FINISHEDTriplet I: FINISHED - Constructed from QSB Quadrupole magnets μE4 Shutdown2004 Shutdown 2004 Until May Until May May 2004 Planned Insertion Shutdown → Delay due to LEMs Beam → Delay due to LEMs Beam planned 5th-6th May planned 5th-6th May → Delay Magnet Group → Delay Magnet Group due to LEMs Beam due to LEMs Beam Planned 19th May… Ready but !!! → Crane Problem → Crane Problem shielding cannot be removed shielding cannot be removed FINAL Insertion 2nd June May 2004 June 2004

P.-R. KettleMEG-Review July Current Component Status – Separators Old Separator II Old Separator II - previously used vertical separator - previously used vertical separator defective most of last Test Beam 2003 defective most of last Test Beam 2003 June 2004 Repaired with new power supply June 2004 Repaired with new power supply → to be used Commissioning Phase I, → to be used Commissioning Phase I, successfully conditioned to 195 KV successfully conditioned to 195 KV → ONLY available until August 2004 for MEG → ONLY available until August 2004 for MEG New Vertical Separator New Vertical Separator approved for MEG approved for MEG Originally So-called copy of LEMs separator Originally So-called copy of LEMs separator modified design underway & HV-parts ordered modified design underway & HV-parts ordered or delivered or delivered V max 200 KV V max 200 KV D plates 18 cm D plates 18 cm L eff 70 cm L eff 70 cm  Expected End 2004 !!!  Expected End 2004 !!! Old Separator II Old Separator II - previously used vertical separator - previously used vertical separator defective most of last Test Beam 2003 defective most of last Test Beam 2003 June 2004 Repaired with new power supply June 2004 Repaired with new power supply → to be used Commissioning Phase I, → to be used Commissioning Phase I, successfully conditioned to 195 KV successfully conditioned to 195 KV → ONLY available until August 2004 for MEG → ONLY available until August 2004 for MEG New Vertical Separator New Vertical Separator approved for MEG approved for MEG Originally So-called copy of LEMs separator Originally So-called copy of LEMs separator modified design underway & HV-parts ordered modified design underway & HV-parts ordered or delivered or delivered V max 200 KV V max 200 KV D plates 18 cm D plates 18 cm L eff 70 cm L eff 70 cm  Expected End 2004 !!!  Expected End 2004 !!! V max 200 KV V max 200 KV D plates 18 cm L eff 70 cm

P.-R. KettleMEG-Review July Current Component Status – Triplet II Old Triplet II New Triplet II: Finished - LEMs magnets shorter version of old Triplet II using 3 QSK quadrupole magnets using 3 QSK quadrupole magnets …better …better New Triplet II: Finished - LEMs magnets shorter version of old Triplet II using 3 QSK quadrupole magnets using 3 QSK quadrupole magnets …better …better Presently in storage Presently in storage → will be implemented during → will be implemented during Phase I Commissioning 23rd June – Mid August 2004 Phase I Commissioning 23rd June – Mid August 2004

P.-R. KettleMEG-Review July Current Component Status – BTS Beam Transport Solenoid BTS: Beam Transport Solenoid BTS:  Design Problems SOLVED  Design Parameters submitted Novosibirsk (mid April) detailed design underway  Contract end June  Design, testing + manufacture 9 months (end March 2005)  Waiting for other tenders at present Beam Transport Solenoid BTS: Beam Transport Solenoid BTS:  Design Problems SOLVED  Design Parameters submitted Novosibirsk (mid April) detailed design underway  Contract end June  Design, testing + manufacture 9 months (end March 2005)  Waiting for other tenders at present BTS COBRA Full simulations performed with GEANT (from colli. System to target in COBRA) Part simulations done with Graphics TRANSPORT & TURTLE, ANSYS & TRACK → input measured beam phase space from test beam results → all major parameters studied Conclusion: beam spot-size   5mm at target not possible without loss of rate !!! beam spot-size   5mm at target not possible without loss of rate !!! Possible consequences for experiment? Possible consequences for experiment?Conclusion: beam spot-size   5mm at target not possible without loss of rate !!! beam spot-size   5mm at target not possible without loss of rate !!! Possible consequences for experiment? Possible consequences for experiment?

P.-R. KettleMEG-Review July BTS continued Sep Trip I Trip II ASC BTS COBRA X Y TRANSPORT Optics ( BTS COBRA optics only schematic here) Axial Field Coupling Centre COBRA → Centre BTS COBRA BTS Summed ++ Summed +- Various Excitations + Coupling Schemes tested SNM, DNM, Reversed Field, Compensation SNM, DNM, Reversed Field, Compensation so Final Solution → Maximum Flexibility so Final Solution → Maximum Flexibility Single Node Double Node

P.-R. KettleMEG-Review July Current Component Status – BTS cont. Summary of Main Results (same Polarity solenoids) Summary of Main Results (same Polarity solenoids) No Degrader, No vacuum Window, No He → spot-size  ~ 5mm No Degrader, No vacuum Window, No He → spot-size  ~ 5mm He Only → spot-size 25 % larger He Only → spot-size 25 % larger Full Degrader in BTS all materials → spot-size  ~ 15mm Full Degrader in BTS all materials → spot-size  ~ 15mm Degrader Intermediate focus inside COBRA → spot-size  ~ 10mm Degrader Intermediate focus inside COBRA → spot-size  ~ 10mm (potential background source) (potential background source) Split Degrader BTS + intermediate focus → spot-size  ~ 13mm Split Degrader BTS + intermediate focus → spot-size  ~ 13mm Beam-spot Size Beam-spot Size  Divergence & Multiple scattering + lever-arm IMPORTANT!!!  Divergence & Multiple scattering + lever-arm IMPORTANT!!!  He less important  He less important Radial + Axial Focussing Radial + Axial Focussing  depends on: Beam Divergence & Fringe Field of Solenoids  depends on: Beam Divergence & Fringe Field of Solenoids Radial component & hence focussing Enhanced by opposite polarity fields!!! BTS reverse polarity wrt Compensation Coils + COBRA BTS reverse polarity wrt Compensation Coils + COBRA  Spot-size reduced 30 % compared with same polarity !!!  Spot-size reduced 30 % compared with same polarity !!!

P.-R. KettleMEG-Review July Current Component Status – BTS cont. DNM Reverse Field Sol n BTS COBRA BTS COBRA  P ~ 6 MeV/c  P ~ 4 MeV/c Radial RadialFocussing Defocusing Like polarity Reverse polarity  10 mm

P.-R. KettleMEG-Review July Current Component Status – BTS cont. BTS Sol n : DNM Reversed Field DNM & SNM Like Polarity allowed by final Specs Degrader No loss 12% He loss 12% He loss 3% Decays 3% Decays Transmission Profile (no Target) BTS  TRANS  98% BTS-COBRA  TRANS = 85% Confirmed in Test Beam 88% µ + stopped in 400µ CH 2 Tg 88% µ + stopped in 400µ CH 2 Tg 86% He He 240µ CH 2 eq R stops = R µ ·  TRANS ·  STOP R µ = 8.5·10 7 µ + s -1 at 1.8 mA 4cm Tg  TRANS = 0.85,  STOPS = 0.88 R stops = R µ ·  TRANS ·  STOP R µ = 8.5·10 7 µ + s -1 at 1.8 mA 4cm Tg  TRANS = 0.85,  STOPS = 0.88 (Stop Rate) R Stops = 6.4·10 7 µ + s -1 at 1.8 mA 4cm Tg (want 2.5·10 7 s -1 for sensitivity) (1.1·10 8 µ + s -1 at 1.8 mA 6cm Tg (1.1·10 8 µ + s -1 at 1.8 mA 6cm Tg

P.-R. KettleMEG-Review July Current Component Status – BTS cont. Beam-spot Size Reduction Necessary? → 10 mm probably OK from TC, DC simulations Necessary? → 10 mm probably OK from TC, DC simulations Without rate-loss → very Difficult (sub-surface μ + ?) Without rate-loss → very Difficult (sub-surface μ + ?) Use Smaller Target → He Problem (240 μ CH 2 Eq.) missed μ + Stop at downstream end of Use Smaller Target → He Problem (240 μ CH 2 Eq.) missed μ + Stop at downstream end of COBRA e + background or annihilation 511 keV  s can one distinguish point-of-origin of background? If so maybe OK COBRA e + background or annihilation 511 keV  s can one distinguish point-of-origin of background? If so maybe OK  Conclusion: use collimators inside BTS to restrict divergence  Conclusion: use collimators inside BTS to restrict divergence  BTS specifications fixed won’t change Spot-size  Still time to optimize collimator/degrader layout

P.-R. KettleMEG-Review July Current Component Status – BTS cont. BTS Final Specifications Machine Drawings in preparation at Novosibirsk at Novosibirsk 2800 mm 380 mm 460 mm 300 mm 2630 mm

P.-R. KettleMEG-Review July Effect of Beam Spot Size Simulations by: Wataru Ootani & Hajime Nishiguchi

MEG-Review July P.-R. Kettle Beam Spot Size In the current design of the beam line, it is difficult to make the beam spot size smaller than 10mm( σ ) without loss of beam rate. Although, it is possible to make it smaller by using collimator, further beam tuning, etc., it is useful to look into the effect of large beam spot on detector performance.

MEG-Review July P.-R. Kettle Effect on Timing Counter

MEG-Review July P.-R. Kettle Hit Distribution TC geometry:  Larger acceptance to cover most of events: 22.5cm<z<125cm,  28.5cm<r<29.0cm for φ-counter, 29.5cm<r<31.5cm for z-counter Beam spot size:  σ=0.5, 1.0, 1.5, 2.0cm

MEG-Review July P.-R. Kettle Efficiency Timing counter acceptance:  26cm<z<125cm, 0°<φ<360° Drift chamber materials are not taken into account. ~3% difference

MEG-Review July P.-R. Kettle Michel Positron Hit Rate ~5% difference

MEG-Review July P.-R. Kettle Trigger Rate TC filtering with e-γ direction match in 1st level trigger Suppression factor (= Φe/ΔΦe)  Φe: TC total angular acceptance =150°  ΔΦe: angle range corresponding to calorimeter angle resolution ΔΦγ =7° φrange φrange(ΔΦγ =7°)

MEG-Review July P.-R. Kettle Trigger Rate, cont’d Suppression factor Trigger rate (assuming 20Hz at σ=0.5cm)

MEG-Review July P.-R. Kettle Impact Time Spread Correlation bw/ time and z of impact point Impact time spread Should be corrected with reconstructed track-length intrinsic

MEG-Review July P.-R. Kettle Effect on Drift Chamber

MEG-Review July P.-R. Kettle Signal Positron Bending Diameter Projected bending diameter of signal positron

MEG-Review July P.-R. Kettle Efficiency Loss

MEG-Review July P.-R. Kettle Trigger Rate Change of count rate in possible trigger window ( bending diameter ±1σ,±2σ,±3σ). this counting rate is raw rate summed over whole DC system and doesn’t contain other trigger requirements from TC and Xenon. If used as 2 nd -Level Trigger Trigger If used as 2 nd -Level Trigger Trigger

MEG-Review July P.-R. Kettle Spot-size Summary Effects of larger beam spot size on performances of timing counter and drift chamber were investigated. No serious effect was found on both detectors for 10mm beam spot size.

P.-R. KettleMEG-Review July Summary/Conclusions Main problem with BTS/COBRA coupling solved Main problem with BTS/COBRA coupling solved BTS Specification submitted to Novosibirsk (mid-April) expected End BTS Specification submitted to Novosibirsk (mid-April) expected End March 2005 March 2005 Spot-size at Target expected to be larger than Proposal now  10 mm Spot-size at Target expected to be larger than Proposal now  10 mm not thought to be major problem (simulations TC, DC) not thought to be major problem (simulations TC, DC) Expected Stop-rate R Stops = 6.4·10 7 µ + s -1 at 1.8 mA 4cm Tg Expected Stop-rate R Stops = 6.4·10 7 µ + s -1 at 1.8 mA 4cm Tg (1.1·10 8 µ + s -1 at 1.8 mA 6cm Tg) (1.1·10 8 µ + s -1 at 1.8 mA 6cm Tg) From background & sensitivity want (2.5·10 7 μ + s -1 ) Triplet I & II Finished Triplet I & II Finished Separator II ready for testing (new HV power supply) Separator II ready for testing (new HV power supply) New vertical Separator expected end 2004 New vertical Separator expected end 2004 Target + He Bag Design next Target + He Bag Design next Beam Line Commissioning Started, initial results reproduced so far!!! Beam Line Commissioning Started, initial results reproduced so far!!!  -beam will also be studied  -beam will also be studied Main problem with BTS/COBRA coupling solved Main problem with BTS/COBRA coupling solved BTS Specification submitted to Novosibirsk (mid-April) expected End BTS Specification submitted to Novosibirsk (mid-April) expected End March 2005 March 2005 Spot-size at Target expected to be larger than Proposal now  10 mm Spot-size at Target expected to be larger than Proposal now  10 mm not thought to be major problem (simulations TC, DC) not thought to be major problem (simulations TC, DC) Expected Stop-rate R Stops = 6.4·10 7 µ + s -1 at 1.8 mA 4cm Tg Expected Stop-rate R Stops = 6.4·10 7 µ + s -1 at 1.8 mA 4cm Tg (1.1·10 8 µ + s -1 at 1.8 mA 6cm Tg) (1.1·10 8 µ + s -1 at 1.8 mA 6cm Tg) From background & sensitivity want (2.5·10 7 μ + s -1 ) Triplet I & II Finished Triplet I & II Finished Separator II ready for testing (new HV power supply) Separator II ready for testing (new HV power supply) New vertical Separator expected end 2004 New vertical Separator expected end 2004 Target + He Bag Design next Target + He Bag Design next Beam Line Commissioning Started, initial results reproduced so far!!! Beam Line Commissioning Started, initial results reproduced so far!!!  -beam will also be studied  -beam will also be studied

P.-R. KettleMEG-Review July MEG Beam Commissioning Schedule MEG Beam Commissioning Schedule Part 1 Part 2 Part 3

P.-R. KettleMEG-Review July Schedule Beam Line Test Milestone AssemblyDesignManufactoring Studies Solenoid BTS Triplet I + II Target Part 1Part 2 New Separator Part 3 Beam Line Commissioning Sep+BTS+COBRACOBRA+Target GottaPrak.Gotta ? Studies Solenoid BTS Triplet I + II Target Part 1 New Separator Part 2 Beam Line Commissioning Pi beam? Platform