SPACE TELESCOPE SCIENCE INSTITUTE Operated for NASA by AURA Cosmic Origins Spectrograph HST Quarterly Review – Instrument Status Charles D. (Tony) Keyes 30 June 2003
2
HST Quarterly Review Page 2 of 10 Space Telescope Science Institute 30 June 2003 SI Status: COS COS Integrated SI Aft End and Vent Covers
3
HST Quarterly Review Page 3 of 10 Space Telescope Science Institute 30 June 2003 SI Status: COS STScI COS Program Activity SubprojectSTScI Activity Instrument Development IDT/STScI MOU I & T Ball (Thermal-Vac support) Commanding and Scheduling System OP-01 Ops bench testing Pipeline and Calibration keyword development pipeline development SM4 initial planning User Support COS ETCs Instr. Handbook development COS activities are a traditional-mode, new HST instrument development project coordinated with IDT led by PI Jim Green (Colorado) STScI supports COS science operations by leading development of “front- end” (operations) and “back-end” (OPUS/MAST/calibration) ground system and user support functions..
4
HST Quarterly Review Page 4 of 10 Space Telescope Science Institute 30 June 2003 SI Status: COS STScI Support of COS Thermal-Vacuum Testing COS Thermal-Vac at Ball: 25 June-10 August Per STScI/COS IDT MOU STScI will provide OPUS processing, conversion to FITS, and HDA-archival of all COS Thermal-Vac data Processed comprehensive bench test data suite delivered by IDT (including target acquisition!) Key MOU deliverable; output from all modes now tested in OPUS OPUS is ready All deliverables and mileposts of MOU now successfully completed
5
HST Quarterly Review Page 5 of 10 Space Telescope Science Institute 30 June 2003 SI Status: COS STScI Support of COS Thermal-Vacuum Testing (cont.) Active STScI Thermal-Vac requirements planning and participation Close coordination of planned STScI support activities with IDT All STScI IS supported the COS Pre-Environmental Review Calibration activity splinters with IDT at Ball MSRs and telecons Data transfer standards and procedures agreement with IDT; development and testing of data transfer process completed STScI IS shift schedules finalized STScI Instrument Scientists (Keyes, Sembach, Leitherer, Friedman, and Bohlin) will stand 6-day shifts during Thermal-Vac; Hartig will “float ”
6
HST Quarterly Review Page 6 of 10 Space Telescope Science Institute 30 June 2003 SI Status: COS STScI Ground Systems and User Support Activities STScI scheduling system Code development of all science and calibration exposure modes complete Bench testing of timing and commanding ongoing at Ball Flat field commanding updates; now in implementation testing Delivered updated COS mini-Handbook; additional post-Thermal-Vac updates planned in August and schedule coordinated Target Acquisition and Spectroscopic requirements ready for ATP/ETC implementation STScI post-SM4 data volume study (includes significant COS section) completed SMOV4 requirements planning: Special Commanding requirements definition Includes initial turn-on, anomalous recovery Calcos 1-d spectrum extraction and averaging routines tested COS Keyword Dictionary (adjunct to ICD-19) reviewed Testing of COS Phase II component of APT Supported STScI AAS COS display at Nashville meeting Supported COS Science Team meeting
7
HST Quarterly Review Page 7 of 10 Space Telescope Science Institute 30 June 2003 SI Status: COS COS Phase Development Plan (rev 8, 01/06/03) Phase 1 (1/1/00 – 6/30/00) 1.Macro Development 2.Reconfigurations Phase 2 (7/1/00 – 12/31/00) 3.NUV Timetag Mode + Darks 4.FUV Timetag Mode + Darks Phase 3 (1/1/01 – 6/30/01) 5.FUV & NUV Accumulation Science Exposures 6.FUV & NUV Target Acquisition Exposures 7.FUV & NUV Target Peakup Exposures Phase 4 (7/1/01 – 12/31/01) 8.Aperture Alignment Exposures 9.OSM1 Focus Alignment Exposures 10.OSM1 Rotation Alignment Exposures 11.OSM2 Rotation Alignment Exposures 12. FUV & NUV FP-Split Exposures Phase 5 (1/1/02 – 6/30/02) 13.FUV & NUV GO Wavelength Calibration Exposures 14.FUV & NUV Flat Field Lamp Calibration Exposures 15.FUV & NUV Automatic Wavelength Calibration Exposures 16.SAA Contours Phase 6 (7/1/02 – 12/31/02) 17.FUV & NUV BOP Target Screening Phase 7 (1/1/03 – 6/30/03) 18.FUV & NUV Flat Field Lamp Re-work 19.Coordinated Parallels Phase 8 (7/1/03 – 12/31/03) 20.OSM Heating Avoidance (if needed) 21.SMGT Preparations 22.SMOV Special Commanding 23.FUV & NUV Anomalous Recovery 24.FUV & NUV Initial Turn-on Phase 9 (1/1/04 – 6/30/04) 25.TRANS ovratalstart, ovratalend Phase 10 (7/1/04 – 12/31/04) 26.FUV & NUV Lifetime Adjustments