GLAST LAT Project IFC Tour – Sep 5,2003 Larry Wai 1 GLAST Large Area Telescope: Integration and Facility Status Larry Wai SU-SLAC Integration and Facility Manager (within I&T) wai@slac.stanford.edu 650-926-3145 Gamma-ray Large Area Space Telescope
2
GLAST LAT Project IFC Tour – Sep 5,2003 Larry Wai 2 Tracker and Calorimeter Integration Tests AUG 22 -26 AUG 7 - 8 AUG 27 – SEP 2 SEP 2 SEP 17 - OCT 1 SEP 2 -16 (individual tests) SEP 2 -16 (Integrated script development) SEP 15-16 (integrated test) SEP 19 - OCT 9 OCT 2 - 6 SEP 1 DELAYED OCT 17 AUG 11 – SEP 1 CAL script migration
3
GLAST LAT Project IFC Tour – Sep 5,2003 Larry Wai 3 Step 1: Receiving and Post-Ship Tests
4
GLAST LAT Project IFC Tour – Sep 5,2003 Larry Wai 4 Step 2: TKR installation
5
GLAST LAT Project IFC Tour – Sep 5,2003 Larry Wai 5 Step 3: CAL Installation
6
GLAST LAT Project IFC Tour – Sep 5,2003 Larry Wai 6 Step 4: TKR/CAL Integration
7
GLAST LAT Project IFC Tour – Sep 5,2003 Larry Wai 7 Pedestal subtracted Integrated System - Preliminary Data Preliminary data
8
GLAST LAT Project IFC Tour – Sep 5,2003 Larry Wai 8 Building 33 LAT Operations Layout I&T FSW De-con I&T W/C AC ACD Project Stores Receiving Shop, Test Offices Meeting Area VDG Test Visitors & Mock-Up Service Corridor TKR CAL Mech ELX VDG Oven Hood T-Vac, Oven
9
GLAST LAT Project IFC Tour – Sep 5,2003 Larry Wai 9 Facility Monitoring System
10
GLAST LAT Project IFC Tour – Sep 5,2003 Larry Wai 10 Airborne Particulate Sensors
11
GLAST LAT Project IFC Tour – Sep 5,2003 Larry Wai 11 Cleanroom Status – “How Clean”
12
GLAST LAT Project IFC Tour – Sep 5,2003 Larry Wai 12 Cleanroom Status: Temperature/Humidity
13
GLAST LAT Project IFC Tour – Sep 5,2003 Larry Wai 13 Summary SLAC Building 33 Cleanroom Facility in operational mode TKR and CAL engineering models are now integrated as a system Basic functional tests completed Need to take more data (cosmics and Van Der Graaff) and do more tests to fully characterize integrated system Need to perform mechanical fit checks with TKR and CAL in engineering model grid Need to build LAT ground support equipment and associated LAT models to test “integrability” of entire system Need to obtain commitments from subsystems to provide manpower with expertise necessary to integrate LAT *and* within a tight schedule!