Set 7 due today Set 8 due April 18 C-3 due April 18 Exam May 7
2
Answers set 7: (1) Shortest Route L-P60=MIN L-S125
3
L B V S M P 60 10 50 55 15 20 125
4
Delete L-P, ADD PATHS FROM P L-S125 P-M (new) 60+10=70 =MIN P-V (new) 60+55=115
5
Delete P-M, add path from m P-V115=MIN L-S125 M-B (new) 70+50=120
6
Delete P-V, add path from V M-B120=MIN L-S125
7
Delete both M-B,V-B L-S125 L-P 60 L-P-M 70 L-P-V115 L-P-M-B120
8
Answer to (2) PERT
9
1 4 3 A B CD E F 2
10
ES AND EF ACTIVITYESEF A05 B08 C07 DEF (C)=77+2=9 EMAX[(EF(B), EF(D)]=9 9+3=12=MAX= E(x) F77+4=11
11
ANSWER TO (a) E(x)=12
12
LF,LS ACTIVITYLFLS AE(x)=12 B C D E F
13
LF,LS ACTIVITYLFLS A B C D EE(x)= 1212-3=9 FE(x)=1212-4=8
14
LF,LS ACTIVITYLFLS A B C DLS(E)=9 EE(x)=1212-3=9 FE(x)=1212-4=8
15
LF,LS ACTIVITYLFLS A B C DLS(E)=99-2=7 EE(x)=1212-3=9 FE(x)=1212-4=8
16
LF.LS ACTIVITYLFLS AE(x)=12 B CMIN[LS(D) LS(F)]= MIN(7,8)=7 DLS(E)=99-2=7 EE(x)=1212-3=9 FE(x)=1212-4=8
17
LF,LS ACTIVITYLFLS AE(x)=1212-5=7 BLS(E)=99-8=1 CMIN[LS(D) LS(F)]= MIN(7,8)=7 7-7=0 DLS(E)=99-2=7 EE(x)=1212-3=9 FE(x)=1212-4=8
18
LF,LS ACTIVITYLFLS AE(x)=1212-5=7 BLS(E)=99-8=1 CMIN[LS(D) LS(F)]= MIN(7,8)=7 7-7=0 DLS(E)=99-2=7 EE(x)=1212-3=9 FE(x)=1212-4=8
19
SLACK ACTIVITYLSESLS-ES A707 B101 C000 D770 E990 F871
20
ANSWER TO (b) CRITICAL PATH: C-D-E
24
NORMAL TABLE Kinderman Supplement, p 58 Row 1.0 Col.00
25
Z = 1.00 Z.00 … 1.0.84134
26
Answer to (c) P(finish project before deadline)=.84
27
Excel Class demo NOT same as assignment should be in memo format Describe critical activities in sentence