1 MuTrig-FEE Install Status RIKEN/RBRC Itaru Nakagawa 1

2 MuTRIG-FEE Install (Station-1) Completed Oct. 27 2

3 Station-2&3 Installation Completed by Oct.29 3

4 ADTX Installation Check List Miscabling –Visible inspection   –Gap-by-Gap calibration logic/mask check  –ADTX Performance   –Dead (single) channel check  –Board ID check   –Slow control (threshould 10mV, 30mV)   –PROM erase and Download  –Efficiency   –Fake hit   –Timing   MuTR FEE Performance –Noise w/o HV   –HV upto 1500V (st-1), 50V (st-2&3) w/ Ar-CO 2 gas  –Minor Tweak of Cable to improve noise  –Noise w/ HV on  –Gap-by-Gap calibration  found one miscabling in St-1, Oct.5  –Gain  stereo ~ 1, non-stereo~0.9   LV –Miscabling  –LV measurement at Chassis with all other power on  4

5 Impact on MuTR Pedestal 5

6 MuTR Resolution vs. Noise Csplit = 100pF Csplit = 30pF w/o ADboard ○ Intrinsic 100um Achieved : 200 ~300um Pedestal RMS/MIP 6

7 MuTR Pedestal RMS Distribution before/after ADTX Install Typical Pedestal RMS Distribution of MuTR Strip Number Pedestal RMS 7

8 MuTR Pedestal Station-1 Run9 Present Oct.1 Oct.2 Oct.3 Oct.4 Oct.5 Oct.6 Oct.7 Oct.8 Gap-1Gap-2Gap-3 stereoNon-stereostereoNon-stereostereoNon-stereo 8

9 MuTR Pedestal Station-2 9

10 Station-3 Octant-2 Noise before after 10

11 Aluminum Foil Shield on Station-3 Chamber 11

12 Station-3 Aluminum Foil Effect w/o foil w/ foil 12

13 MuTrig Performance With Calibration Pulse Timing Efficiency Miscabling Check Logic Test Without Calibration Pulse Fake hit rates 13

14 ADTX Timing (Gap-1) Strip# 14

15 ADTX Efficiency (Gap-1) 1 1 1 Strip# 15 efficiency

16 ADTX Timing (Gap-2) 16

17 ADTX Efficiency (Gap-2) 17

18 ADTX Timing (Gap-3) 18

19 ADTX Efficiency (Gap-3) 19

20 Fake Hit Rate (Threshold=20mV) 20

21 21 LL1 Trigger Readiness Communication test  LL1 Board Production by end of October ADTX - MRG - LL1 - GL1 chain test this November. New high momentum trigger will be operated in Run10 for commissioning LL1 Board MuTRG-MRG Boards

22 DCM For Run10 Operation, 2 more FE3 were obtained from : 1.FOCAL 2.Colorado 22

23 Re-Capacitation Station-1 Station-2 23

24 Summary Installation to South Arm is completed. 24

25 Backup Slides 25