Injectors & LHC report K. Foraz on behalf of OSS members 01/08/2013LSC - K. Foraz1.

Similar presentations


Presentation on theme: "Injectors & LHC report K. Foraz on behalf of OSS members 01/08/2013LSC - K. Foraz1."— Presentation transcript:

1 Injectors & LHC report K. Foraz on behalf of OSS members 01/08/2013LSC - K. Foraz1

2 AD Removal of all the unused power supplies done Stochastic cooling amplifiers reconnected Vacuum work on UHM3107 and UVM3207 tanks delayed (tooling not ready) and postponed until week 33. Major ion pump change started More tests requested by vacuum on MTV screens (degasing issues) Girder line 7000: manufacturing drawings in progress. The 4 old magnets are removed BHN06: Waiting for other news from manufacturer 01/08/2013LSC - K. Foraz2 Girder line 7000 Stochastic cooling

3 LEIR Cabling campaign completed Optical fibbers installed Access system in progress Removal of ER.DHV12 magnet in progress General cleaning of LEIR area started, in collaboration with TSO. Future bake-out (sectors 1, 2 and 5): updated procedure was circulated. Most of activities on kickers were postponed 01/08/2013LSC - K. Foraz3 ER.DHV12 removal

4 PS Done – New crane PR275 has been commissioned In Progress – CV Consolidation program Some delay in the cabling part which will start next week – Septum 16 External Shielding - No work in August – Safety and Access System Installation is on progress EL campaign delayed PSB cabling campaign in PS (BTP transfer line) – Stopped by RP (dose higher than foreseen) – ALARA1  ALARA2, work will restart on Monday 01/08/2013LSC - K. Foraz4 New crane commissioned Ventilation installation Access system – new door BTP line cabling campaign

5 PSB In progress – On site preparations for the beam dump replacement project on schedule. New beam dump core delivered to CERN and is under preparation. Dismantlement of the BTM/BTY beam lines now complete. Final zone cleaning in preparation. EN-STI Successfully Injected foam to aid the cutting of the old beam pipe. Start of the beam dump removal procedure currently programmed Wednesday 07 th August. No general access to the PSB Machine during this period. – CV consolidation and maintenance of CV, kickers, Septa, vacuum beam instrumentation, Magnet and Beam stopper – AS45 lift replacement final commissioning 16 th Sept. Forecast – Replacement of all PSB ring 32A power sockets which are not protected by a differential – Integration testing of the new PPS (access) system Installation of the public address cables & infrastructure. – Replacement of the BI.SMH under preparation. Exchange work programed mid October. 01/08/2013LSC - K. Foraz5

6 SPS EL cabling works in progress – BA3 finished this week The preparation of LSS1 for the irradiated cable campaign is in progress: – 3 rd dump has been removed from LSS1+ and stored in ECX5 – Still on target to have the area clear for the beginning of September LSS1+ - 20% of orphan cables !! – (list from Wednesday in Indico – please check) Transformers – 4/8 in place in BA3 All other works progressing on schedule. 01/08/2013LSC - K. Foraz6

7 LHC - P1  P2 R2E – Pt1: – Left: demineralized water pipe installation finishing today. Chilled water pipe installation will follow – Right: Demineralized water pipe starting from next week LSS1: – PM15 lift broke down (generator) – back in service – Thermoswitch installation on DFBs finished – Cabling campaign is finished – Upgrade of collimator control system started – DQR-DQS upgrade in progress – Survey HLS maintenance in progress – DFBX -consolidation of current leads in progress Arc 12: – Exchange of cryo-magnets in progress ~65% 01/08/2013LSC - K. Foraz7 Demineralized water pipes – UJ14

8 LHC - P2  P3 Point 2 – Cabling finished – connectors in progress – Cooling tower maintenance in progress – Cryogenic maintenance in progress – DQR-DQS upgrade in progress Arc 23 – Cryogenics consolidation in progress – Magnet replacement in progress ~55% – W opening in progress ~41% LSS3 – Optical fibers work almost finished – From next week vacuum activities (B5L3, B5R3), new cable trays, walkway… 01/08/2013LSC - K. Foraz8 Next Friday AUG test @ P2 No access from mid arc 12 to mid arc 23 Walkway in LSS – ICL review next week

9 LHC - P3  P5 Arc 34 – QRL leak test in progress – compensator removal from Aug. 7 th (not as easy as the others…near Q6R3) – Magnet replacement in progress ~25% – Vacuum consolidation activities in progress LSS4 & P4 – Cabling in progress (Flexwell pulled in UX) – Water cooled cables consolidation in progress – ADT RF plant maintenance and upgrade – Cryogenic maintenance Arc 45 – Magnet replacement in progress ~25% – QRL Xrays in progress 01/08/2013LSC - K. Foraz9 Cryogenic maintenance Flowmeter replacement

10 LHC – P5  P6 LSS5 &P5: – HRL consolidation almost finished R2E – P5 – Drilling: 5 ducts (UJ56-tunnel) being drilled – Installation of the safe-room structure in progress – Chilled water pipes installation from next week Arc 56 – QRL compensator removed under analysis – SMACC DFBA in progress – some big delays announced to be analyzed – Xrays tonight M weld in progress (~45%) Vacuum leak test in progress LSS6 & P6 – MKD-MKB tests on going – Cryogenic maintenance 01/08/2013LSC - K. Foraz10 DFBAJ – clamp installation Additionnal valves on HRL

11 LHC – P6  P7 Arc 67 – SMACC in progress Resolder BB ~68% Shunt ~55% – DFBA consolidation – Vacuum insulation consolidation in progress R2E – P7: – TZ76 – vault painted – Installation of cable trays in progress – Smoke detector in RR being installed LSS7&P7 – Vacuum activities in progress: A6L7 (TCP), A5L7 (NC), IP7 (NC), A5R7 (NC), B5R7 (NC) – 13kA & 600A upgrade in progress 01/08/2013LSC - K. Foraz11

12 LHC - P7  P1 Arc 78 – SMACC M cut ~85% Desolder BB just started DFBA consolidation in progress LSS8 &P8 – DQR-DQS upgrade finished 01/08/2013LSC - K. Foraz12 Arc 81 -SMACC -DFBA consolidation in progress -W opening finished -DN200 installation finished -Cryo module consolidation in progress

13 General infrastructures The possibility of deploying Wi-Fi access points at each LHC pits (PAD – MAD on surface) is under study. A slight slowdown in the project of technical network renewal (due to vacation period) but still quite ahead of the schedule. Demineralised water production – work is finished !! 400kV & 66kV maintenance and consolidation – CERN ends end of July – But auto-transfer test postponed to end of August 01/08/2013LSC - K. Foraz13 Courtesy F. Chapron

14 Overall progress Injectors: on schedule, but to follow – CV cabling for PS ventilation – AD – BHN06 coil manufacturing LHC on schedule – R2E - On schedule – SMACC – to follow “OK for M line” welding DFBA schedule – Support from vacuum on surface – under analysis – overloaded !! General infrastructures: good progress Impact of summer holidays will be assessed in September (we can “feel” it already) Reminder - IPE 01/08/2013LSC - K. Foraz14