Presentation is loading. Please wait.

Presentation is loading. Please wait.

E. M. Hanna; 7/31/03 DXI Management Consulting 1 Resource Leveling.

Similar presentations


Presentation on theme: "E. M. Hanna; 7/31/03 DXI Management Consulting 1 Resource Leveling."— Presentation transcript:

1 E. M. Hanna; 7/31/03 DXI Management Consulting 1 Resource Leveling

2 E. M. Hanna; 7/31/03 DXI Management Consulting 2 Agenda  Importance of the Individual Project Plan  Importance of Resolving Resource Over-Allocations in All Project Plans  Identifying Resource Over-Allocations  Manual (On-demand) Leveling of Projects  Manual (On-demand) Leveling of Resources  Leveling Resources Across a Portfolio of Projects

3 E. M. Hanna; 7/31/03 DXI Management Consulting 3 Importance of the Individual Project Plan

4 E. M. Hanna; 7/31/03 DXI Management Consulting 4 The Building Blocks of EPM  The individual Project Plan is the building block from which the Enterprise Project Management environment is constructed.  The discipline of building sound Project Plans is critical to the success of EPM.  Resolving resource over-allocations is a critical part of the discipline of building sound Project Plans.

5 E. M. Hanna; 7/31/03 DXI Management Consulting 5 Basic Process for Creating a Project Plan

6 E. M. Hanna; 7/31/03 DXI Management Consulting 6 Importance of Resolving Resource Over-Allocations in all Project Plans

7 E. M. Hanna; 7/31/03 DXI Management Consulting 7 Over-Allocation of Resources  Over-Allocation of Resources exists when— Work [Scheduled] > Available Hours*  Usually caused by scheduling multiple assignments for a resource during a single time period (Note: EPM significantly intensifies this problem)  Project considers the Resource Calendar—but not other assignments—when scheduling new assignments *Available hours = Working Hours in Time Period X Resource Units

8 E. M. Hanna; 7/31/03 DXI Management Consulting 8 Impact of Over-Allocated Resources  If over-allocated resources exist in a schedule, the entire project schedule is untrustworthy and not suitable for use in managing the project.  If individual project plans are untrustworthy, all portfolio analysis becomes untrustworthy

9 E. M. Hanna; 7/31/03 DXI Management Consulting 9

10 E. M. Hanna; 7/31/03 DXI Management Consulting 10

11 E. M. Hanna; 7/31/03 DXI Management Consulting 11 Identifying Resource Over-Allocations

12 E. M. Hanna; 7/31/03 DXI Management Consulting 12

13 E. M. Hanna; 7/31/03 DXI Management Consulting 13

14 E. M. Hanna; 7/31/03 DXI Management Consulting 14

15 E. M. Hanna; 7/31/03 DXI Management Consulting 15

16 E. M. Hanna; 7/31/03 DXI Management Consulting 16 Approaches to Leveling  Project does the leveling Automatic leveling Manual (on demand) leveling  Entire project  Selected resources  Project Manager does the leveling Risk

17 E. M. Hanna; 7/31/03 DXI Management Consulting 17 Methods of Resolving Resource Over-Allocations  Delay a task  Split a task  Reduce a task’s duration  Change the resources assigned to the task  Assign more resources to the task  Replace an over- allocated resource with and under-allocated resource  Remove an over- allocated resource from a task  Add overtime Project Uses Only These Two

18 E. M. Hanna; 7/31/03 DXI Management Consulting 18 Manual (On-Demand) Leveling of an Entire Project

19 E. M. Hanna; 7/31/03 DXI Management Consulting 19

20 E. M. Hanna; 7/31/03 DXI Management Consulting 20

21 E. M. Hanna; 7/31/03 DXI Management Consulting 21 Manual (On-Demand) Leveling of a Single Resource

22 E. M. Hanna; 7/31/03 DXI Management Consulting 22

23 E. M. Hanna; 7/31/03 DXI Management Consulting 23

24 E. M. Hanna; 7/31/03 DXI Management Consulting 24 Leveling Resources Across a Portfolio of Projects

25 E. M. Hanna; 7/31/03 DXI Management Consulting 25

26 E. M. Hanna; 7/31/03 DXI Management Consulting 26

27 E. M. Hanna; 7/31/03 DXI Management Consulting 27

28 E. M. Hanna; 7/31/03 DXI Management Consulting 28

29 E. M. Hanna; 7/31/03 DXI Management Consulting 29

30 E. M. Hanna; 7/31/03 DXI Management Consulting 30

31 E. M. Hanna; 7/31/03 DXI Management Consulting 31

32 E. M. Hanna; 7/31/03 DXI Management Consulting 32

33 E. M. Hanna; 7/31/03 DXI Management Consulting 33 Recommendations About Leveling  Resource over-allocations must be addressed  A “Project Audit” should be conducted on project plans that are being published to the server. The audit should include a check for over-allocated resources.  Recommend—especially to naïve clients— that Project’s Automatic Leveling and Manual (On Demand) Leveling features not be used.

34 E. M. Hanna; 7/31/03 DXI Management Consulting 34 END


Download ppt "E. M. Hanna; 7/31/03 DXI Management Consulting 1 Resource Leveling."

Similar presentations


Ads by Google