Download presentation
Presentation is loading. Please wait.
Published byHope Cameron Modified over 8 years ago
1
Progress on Hydrogen R&D System Yury Ivanyushenkov on behalf of Elwyn Baynham, Tom Bradshaw, Mike Courthold Matthew Hills, Tony Jones MICE Collaboration Meeting, RAL, 15 June 2007
2
Scope Hydrogen R&D system specification Tender exercise Safety issues Next steps MICE Collaboration Meeting, RAL, 15 June 2007
3
Hydrogen R&D System Specification Specification document: - Describes MICE hydrogen R&D system ( P&ID implements recommendations by HAZOP study) - Specifies hydrogen gas panel assembly - Specifies test cryostat assembly - Defines scope of supply: a manufacturer supplies gas panel assembly and test cryostat but not a hydride bed, cryocooler, control system and ventilation system - Defines acceptance criteria MICE Collaboration Meeting, RAL, 15 June 2007
4
Hydrogen R&D System Layout MICE Collaboration Meeting, RAL, 15 June 2007 Hydrogen R&D System
5
Hydrogen R&D System P&ID MICE Collaboration Meeting, RAL, 15 June 2007 Hydrogen R&D System P&ID
6
Hydrogen R&D System Test Cryostat MICE Collaboration Meeting, RAL, 15 June 2007 Hydrogen R&D System Layout
7
Hydrogen R&D System Test Cryostat MICE Collaboration Meeting, RAL, 15 June 2007 Hydrogen R&D System Layout
8
Tender exercise MICE Collaboration Meeting, RAL, 15 June 2007 Tender for MICE R&D hydrogen system in May 07 Five companies were invited to participate Two companies responded with an offer Tender review on 04 June decided to accept an offer by AS Scientific Products LTD
9
Safety issues MICE Collaboration Meeting, RAL, 15 June 2007 Safety issues List of documents required by ISIS Safety Officer for the Operation Readiness Review
10
Next steps Next 3 months: Order hydrogen R&D system hardware Prepare control system specification document and start making control system (with Daresbury group) Prepare ventilation system specification document, get quotes, start building ventilation system (requires the mezzanine) Next 6 months: Install hydrogen R&D system in the MICE Hall and commission it with He Pass Operation Readiness Review Start working with hydrogen (possible conflicts with other activities in the MICE Hall) -> requires careful planning MICE Collaboration Meeting, RAL, 15 June 2007
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.