Kummer Student Design Center Construction
4
Kummer Student Design Center Construction Schedule Began construction in June 2010 Completion in December 2010
5
Indoor Practice Facility Construction Schedule Began construction in May 2010 Completion in September 2010
6
Indoor Practice Facility
7
Innovation Park Construction
8
Innovation Park Technology Development Center 10 th Street Construction Schedule Began construction in April 2010 Completion in November 2010