Preliminary Report on ERCOT Pilot Project for Fast Responding Regulation Service (FRRS) June 12th, 2013.

Similar presentations


Presentation on theme: "Preliminary Report on ERCOT Pilot Project for Fast Responding Regulation Service (FRRS) June 12th, 2013."— Presentation transcript:

1 Preliminary Report on ERCOT Pilot Project for Fast Responding Regulation Service (FRRS) June 12th, 2013

2 2 OUTLINE Summary of Findings Questions for PDCWG Conventional Regulation Deployment and Frequency FRRS Up and FRRS Down performance FRRS-Pilot Resource’s ability to respond to sudden large frequency deviation Measuring ERCOT deployed FRRS-up against rate of change of Frequency and Regulation-up deployment Stakeholder Review Process 6/12/2013 2 ERCOT

3 3 Summary of Findings Based on the first three months of observations; 1.The introduction of FRRS improves ERCOT’s ability to arrest frequency decay during unit trips. 2.FRRS Pilot Resources generally followed ERCOT FRRS deployments and responded automatically using local frequency detecting techniques. 3.When deployed, FRRS reduces the rate of change of frequency and regulation deployed to conventional Resources. 4.Observed lower quantities offered for FRRS-down and an overall lower performance for FRRS-down. 6/12/2013 3 ERCOT

4 4 Questions for the PDCWG 1.Can FRRS be part of Regulation Service? 2.If so, how much FRRS can participate in Regulation Service? 3.If so, are there any recommended changes to deployment logic of the pilot and what performance criteria are recommended 6/12/2013 4 ERCOT

5 5 Conventional Regulation deployment and Frequency 6/12/2013 5 ERCOT

6 6 Response from Conventional Resource 6/12/2013 6 ERCOT

7 7 Response from FRRS Resource 6/12/2013 7 ERCOT

8 8 Response from Conventional and FRRS Resources 6/12/2013 8 ERCOT

9 9 FRRS Performance 6/12/2013 9 ERCOT

10 10 05-22-2013 Frequency event 6/12/2013 10 ERCOT

11 11 03-30-2013 High Frequency Event 6/12/2013 60 Hz Frequency FRRS-Up Deployed FRRS Response 11 ERCOT

12 12 Frequency FRRS-Up Deployed FRRS Response Regulation Deployed Effect of FRRS-Up on Frequency and Reg-Up 6/12/2013 60 Hz 12 ERCOT

13 13 FRRS Impact on RoCoF 6/12/2013 13 ERCOT

14 14 FRRS Impact on Reg-Up Deployment 6/12/2013 14 ERCOT

15 15 Additional Analysis Underway Using KERMIT KERMIT is a Matlab/Simulink/Excel based platform used for simulating daily system operation with 1 second resolution. Capable of providing an assessment of a system’s ability to achieve adequate balancing and maintain system frequency Once the KERMIT model is calibrated and the deployment and un-deployment logic of FRRS are added, it can be used to study impacts of FRRS in the ERCOT system. 6/12/2013 15 ERCOT

16 16 Stakeholder Review Process ERCOT discussed progress of FRRS-pilot and some performance data with ETWG and PDCWG in March, April and May 2013 More discussions in June with the various subcommittees (ID options) TAC July 2 (Update on Pilot and outline options) BOD July 16 (Present update and options) 6/12/2013 16 ERCOT

17 17 Appendix 6/12/2013 17 ERCOT

18 18 Purpose of FRRS Pilot The pilot governing document states the purpose of the pilot project is to: 1.Determine whether FRRS can improve ERCOT’s ability to arrest frequency decay during unit trips 2.Determine the optimal means of deploying FRRS by testing various deployment methodologies 3.Determine whether FRRS can reduce the need for Regulation Service and thereby reduce total Ancillary Service costs 4.Assess the operational benefits and challenges of deploying FRRS 5.Provide data for ERCOT to determine the appropriate settlement treatment for Resources providing FRRS, including possible “pay-for- performance” methods such as those being developed in response to FERC Order 755. 6/12/2013 18 ERCOT

19 19 FRRS Pilot Overview FRRS pilot deployment obligations began on Feb. 25, 2013 at hour ending 11. When the pilot began, there were 32 MW FRRS UP and 30 MW FRRS DOWN qualified to participate. Additional 1 MW FRRS UP and DOWN began participating on Mar. 16, 2013. All the qualified resources completed the qualification tests. ERCOT has made FRRS parameter changes twice and more parameter changes are expected during the course of pilot 6/12/2013 19 ERCOT

20 20 Log of Parameter Changes 6/12/2013 20 ERCOT

21 21 Impact on Reg-up in Feb 2013 6/12/2013 21 ERCOT

22 22 April and May 2013 Performance 6/12/2013 April, 2013FRRS-UPFRRS-DOWN FRRS Resource A98.51%64.77% FRRS Resource B77.78%100.00% Total Average88.15%82.39% May 1 – May 20, 2013FRRS-UPFRRS-DOWN FRRS Resource A97.61%50.00% FRRS Resource B60.15%74.69% Total Average78.88%62.34% 22 ERCOT

23 23 Number of FRRS Deployments 6/12/2013 23 ERCOT 59.97 59.98 59.975

24 24 Determination of max FRRS-pilot participation 6/12/2013 24 ERCOT

25 25 May 2013 Regulation-Up Usage Vs Procurement 6/12/2013 25 ERCOT

26 26 FRRS-DN and FRRS-UP Payments 6/12/2013 26 ERCOT

27 27 OD 2-25-13 thru OD 5-20-13 Market Clearing Prices 6/12/2013 27 ERCOT

28 28 FRRS-DN Award Amounts 6/12/2013 28 ERCOT

29 29 FRRS-UP Award Amounts as of May 29 1100hrs

30 30 FRRS-DN Performance 6/12/2013 30 ERCOT

31 31 FRRS-Up Performance 6/12/2013 31 ERCOT

32 32 Performance Rate for First 13 Weeks 6/12/2013 32 ERCOT