Programme Status ECTL AAB 15-16 February 2012
2
FACTS A mature approach: 2500 contributors Release process organises the delivery cycle ATM Engineering: System of Systems approach and link with Performance requirements Wide stakeholder support: 200 experts from Airspace Users International Validation Team of 65 staff representatives 7 National Authorities and EASA involved in the work 80 Military experts from 8 nations (through ECTL) Scientific Committee provides oversight on academic/long term research The SESAR family is enlarging
3
NEW SESAR ASSOCIATES Associate members Associate Partners 15 SMEs, 4 Research Centers, 18 Universities
4
MAIN ACHIEVEMENTS 1/3 22 Exercises of Release 1 completed out of 23 ACAS Improvement & Link with auto pilot Departure panel for small-medium size airports’ Controller Working Position: Single Remote tower operations Extended AMAN & integration with DMAN Full PRNAV in complex TMA Short Term ATCFM Measures live trial: -EUROCONTROL (CFMU),London, Maastricht, Reims FMPs, 11 aircraft operators -Measures implemented on OPS systems short time before take off: FL capping, route modifications First 4D Flight on 10/02/12!
5
MAIN ACHIEVEMENTS 2/3 Release 2 content defined: Airport safety & efficiency: detection of conflicting ATC clearances for Runway controller, routing of aircraft and vehicles through data link Trajectory management: synchronisation of airborne and ground flight profiles through i4D data exchange, improved ATC Trajectory prediction using AOC data ATC operations en-route: multi-sector planner tools, roles & responsibilities, streaming techniques using extended horizon of the arrival manager ATC operations airport: time Based Separation minima for tower Controllers, provision of ATC Services on a single airport from a single remote site Network Management: automation of slot swapping on CDM airports, improved ATFCM measures based on real time airspace use
6
MAIN ACHIEVEMENTS 3/3 Launch of WP 11.1 (Flight/Wing Operations Centres) technical activities Launch of the Master Plan update, with a view to finalise before summer 2012, for formal adoption (EU+ECTL) before end 2012 Long Term research activities are starting to deliver Launch of EU-US MoC activities
7
RESSOURCES The effort consumption is 10-15% below the plan, following the forecasted trend and reaching the “cruise level” in 2013-14 The SJU is constantly monitoring the situation with its partners, and systematically working on improvements and rationalisation
8
QUALITY Quality is ensured through SJU assessment of deliverables as well as through projects internal quality process Overall the quality is improving and the effort made by projects becomes visible during the gates
9
PROGRESS Some projects face difficulties in delivering timely results. The % complete continued to increase over 2011 Deliverables on the critical path (ops requirements) are systematically identified and project members are ‘assisted’ where required However Release 1 schedule was on track
10
RISKS The SWIM action plan is progressing slower than expected and SWIM prototyping and validation activities remain at risk Transversal activities need to find the proper balance between methodology and delivering results The number of validation activities identified for the 2013-2016 period is above the resources available (platforms, staffing…), hence the need for a more robust top down approach Critical dependencies need to be constantly monitored
11
FORECAST NEXT PERIOD Release 1 final report in April 2012 Release 2 activities delivery Demonstration activities (on-going call, deadline: 07 March 2012) start in summer 2012 Participation in ACARE (chairmanship of ‘Mobility’ working group) Further develop the interactions with EASA and National Authorities. Launch of work on integration of UAS in the SESAR concept of operations scenarios