Bitter Creek Stream Restoration Preliminary Engineering Report Neighborhood Meeting
2
Project Orientation
3
Introductions Creek History Current Conditions & Proposed Solutions Question & Answer Meeting Agenda
4
Project Sponsor, Watershed Protection Department ◦ Janna Renfro (512) 974-3422 janna.renfro@austintexas.gov janna.renfro@austintexas.gov Design Engineers, CH2M Hill ◦ Heather Harris (512) 249-3327 heather.harris@ch2m.com heather.harris@ch2m.com Neighbors ◦ Name Location Introductions
5
Creek History – Before Development `
6
Creek History – 1970s `
7
Creek History – 1980s `
8
Project Study Area `
9
Project Areas (New Survey) = 311 Erosion Complaints 1 2
10
Project Area 1 Cover channel to… Discourage dumping Join stormdrains Improve safety Increase connectivity
11
Project Area 1 30’ Drainage Easement Threatened property Safety concerns Steep & eroding banks Minimal natural function Incised channel
12
Recommended Solution Raise Channel Bed (3 – 6 ft) Tiered Channel 2 ft pilot channel 4 ft floodplain bench 8 ft total depth Vegetated Banks Rock Bottom Continuous over ~600 ft Project Area 1 Existing 30’ Easement
13
Project Area 1
14
Project Areas = 311 Erosion Complaints 1 2
15
Transition 2 Recommended Solution Grade Control Structure(s) to make elevation change 1
16
Project Area 2 Wider channel Wider easements Some stable areas Isolated severe erosion spots
17
Project Area 2 Too wide Deflections Debris Trash Invasive vegetation
18
Project Area 2 Recommended Solution Clean up channel Provide defined flow path Passive restoration Improve quality of vegetation
19
Project Area 2 Recommended Solution Spot fixes for severely eroded banks
20
Project Area 2 Recommended Solution Spot fixes for side gully formations
21
Project Area 2 Recommended Solution Spot fixes for failing and eroded outfalls
22
Project Area 2 Recommended Solution Assess condition of existing projects
23
Project Areas = 311 Erosion Complaints 1 2
24
Project Area 3 Recommended Solution Evaluate improvements to enhance water quality downstream
25
Project Areas 1 2 1 2 Continuous, Engineered & Vegetated Channel Clean-up, Spot fixes, & Passive Restoration Pond Improvements for Water Quality