INTEGRATED COASTAL ZONE MANAGEMENT PROJECT AT SAGAR ISLAND MONTHLY PROGRESS REPORT AS OF 31 st JANUARY, 2016 GHOSH, BOSE & ASSOCIATES ( P) Ltd, 8, HARRINGTON.

Similar presentations


Presentation on theme: "INTEGRATED COASTAL ZONE MANAGEMENT PROJECT AT SAGAR ISLAND MONTHLY PROGRESS REPORT AS OF 31 st JANUARY, 2016 GHOSH, BOSE & ASSOCIATES ( P) Ltd, 8, HARRINGTON."— Presentation transcript:

1 INTEGRATED COASTAL ZONE MANAGEMENT PROJECT AT SAGAR ISLAND MONTHLY PROGRESS REPORT AS OF 31 st JANUARY, 2016 GHOSH, BOSE & ASSOCIATES ( P) Ltd, 8, HARRINGTON MANSION 8, HO CHI MINH SARANI KOLKATA – 700071 SUNDARBAN INFRASTRUCTURE DEVELOPMENT CORPORATION LTD. (A State Government Company)

2 ACF With PMC: Hydea SpA - Ghosh Bose & Associates (P) Ltd JV ComponentName of Contractors Construction of Public Rain Shelter cum Nat Mandir & Public Rain Shelter cum Dala Arcade M/S. VIRAJ PROJECTS (I) PVT LTD Construction of ECO -, Beach Shelters and Drainage Construction of Leach Pit Based Toilets and Solid Waste Management Facility M/S N.K. BASU & COMPANY Construction of Bus Terminus

3 Package consisting of Civil, Sanitary & Plumbing, Electrical, and Other Allied Works Sl No.Name of WorkDate of IFB Pre bid Meeting Submission of Tender Issuance of LOA 1 Construction of Public Rain Shelter cum Nat Mandir & Public Rain Shelter cum Dala Arcade 30.06.201414.07.201431.07.201429.10.2014 2 Construction of ECO -, Beach Shelter and Drainage 30.06.201416.07.201431.07.201429.10.2014 3 Construction of Leach Pit Based Toilet and Solid Waste Management Facility 30.06.201415.07.201431.07.201429.10.2014 4 Construction of Bus Terminus 30.06.201416.07.201431.07.201429.10.2014

4 BRIEF DESCRIPTION AND LOCATION OF THE PROJECT Sl. No.Name of WorkBrief Description and Location of Site Name of the Contractor Value of Work Awarded Some Important Dates 1 Public Rain Shelter Cum Dala Arcade and Public Rain Shelter Cum Nat Mandir Nat Mandir – An Open Pavilion with domed roof having an area of 450 Sq m Location –As on faces the temple, on the right side of the paved approach, right in front of the temple. Dala Arcade – A shopping arcade having 124 Nos. 10’ X 10’ shops to accumulate the dala vendors. Location – On the left side of the paved approach as face towards the temple M/s Viraj Project (P) Ltd Rs 13.20 Core Letter of Acceptance Issued :- 20.10.2014 Contract Signed :- 30.12.2014 Proceed to Work Letter Issued on :- 27.01.2015 2Eco-, Beach Shelters and Drainage Eco-Camp – Consisting of Reception Centre, 20 Nos. small Eco-Huts, 10 Nos. Large tented Huts, Eating House & Toilet Blocks. Location – The Complex is located behind the temple complex between road no. 4 & 5. Beach Shelter – On the Beach overlook from the. M/s Viraj Project (P) Ltd Rs 9.11 Core 3 Leach Pit Based Toilet and Permanent & Temporary Composite Solid Waste Management Facilities 20 Nos. leach Pit Based Toilet Blocks comprising of 10 Nos. toilet in each block to be set up at 2 location, one near the exiting toilet right side of Road no. And another at the beach. 4 Nos. solid waste handling facilities shall be located at different locations covering the entire pilgrim area M/s N.K. Basu & Company Rs 2.12 Crore 4Bus Terminal.Bus Stand shall have Waiting Area,, Toilet Block and Tourist Information Centre & Transport Office Location – In the Road island at the confluence of Road No. 3,4&5 at the start of the Mela Ground M/s N.K. Basu & Company Rs 1.85 Crore

5 BRIEF SUMMARY OF THE PROJECT SL No. ContractorName of WorkContract PriceDate of LOA Date of Work Order Date of commencement as per W.O. 1 M/s Viraj Projects (I) Pvt. Ltd. Construction of Public Rain Shelter cum Nat Mandir & Public Rain Shelter cum Dala Arcade 132,839,162.0029.10.201427.01.2015 2 M/s Viraj Projects (I) Pvt. Ltd. Construction of ECO -, Beach Shelter and Drainage 91,779,042.9529.10.201427.01.2015 3 M/s N.K. Basu & Company Construction of Bus Terminius 18,517,073.9329.10.201427.01.2015 4 M/s N.K. Basu & Company Construction of Leach Pit Based Toilet and Solid Waste Management Facility 21,224,549.7529.10.201427.01.2015

6 AName of Contractor :- M/s Viraj Project (I) Pvt. Ltd. For Construction of Nat Mandir, Dala Arcade, Eco Camp Complex, Beach Shelter & Drainage Sl. No. Description As Per Contract Available at site Remarks 1M/Machine With Hopper 2 Nos. 2M/Machine without Hopper 3 Nos. 3Electric Vibrator 9 Nos. 3 Nos. 4Petrol Vibrator 3 Nos. 53.5 HP Pump 3 Nos. 61.5 HP Pump 1 No. 75 HP Pump1 No. 8Tulu Pump 2 Nos. 9Needle Shaft Pump 6 Nos. 10R/F Cutting Machine 3 Nos. LIST OF PLANT & MACHINERIES AT SITE

7 Sl. No. Description As Per Contract Available at site Remarks 11Grinding Cutting Machine 3 Nos. 12Compressive Testing Machine 1 No. 13D.G. Set 2 Nos. 14Sieve Analysis Set (For Fine Aggregate) 1 Set 15Sieve Analysis Set (For Course Aggregate) 1 Set 16Auto Level 2 Nos. 17Excavator /Back Loader2 Nos.1 No. On Hire Basis when required 18Truck/Tripper2 Nos.5 Nos. On Hire Basis when required 19Theodolite 1 No.

8 BName of Contractor :- M/s N.K. Basu & Company For Construction of Bus Terminal, Leach Pit Based Toilet & Solid Waste Management Facility Sl. No.Description As Per Contract Available at site Remarks 1M/Machine without Hopper2 Nos.1 No. 2Weight Batcher 1 No. 3Tully Pump 2 Nos. 43.5 H.P. Pump 1 No. 5Vibrator10 Nos.2 Nos. 6Earth Compacting Machine 1 No. 7Rod Cutting Machine 2 Nos. 8Excavator /Back Loader2 Nos.1 No. On Hire Basis when required 9 Truck/Tripper2 Nos.Nil On Hire Basis when required

9 SKILLED MAN POWER DEPLOYED AT SITE Name of Contractor: - M/s Viraj Project (I) Pvt. Ltd. Sl. No. DesignationNo. of Heads at Site 1Project Manager1 2Engineer (Degree)1 3Engineer (Diploma)2 4Supervisor6 5Electrician1 6Mechanic2 7Stores2 Name of Contractor :- M/s N.K. Basu & Associates Sl. No. DesignationNo. of Heads at Site 1Project Manager0 2Engineer (Degree)0 3Engineer (Diploma)0 4Supervisor 3 5Electrician 0 6Mechanic 0 7Stores 0

10 STATUS OF PHYSICAL PROGRESS AT SITE Name of Contractor: - M/s Viraj Project (I) pvt. Ltd. Name of Structure :- Public Rain Shelter Cum Nat Mandir Brief Description of Project as on 31stJanuary 2016 Foundation : - Completed. Filling below foundation (Yellow Sand) :- Completed. Back Filling by Excavated Earth :- Completed. Tie Beam :- Completed. Column up to Roof Beam Bottom :- Completed. Silver Sand Filling below Plinth :- Completed. Plain Cement Concrete below Floor :- Completed. Grade Slab :- 50 % Completed. Roof Beam & Dome Shuttering :- 50% Area Completed. Reinforcement Work for Roof :- 50% Area Completed. Roof & Dome Casting :- 1 st Dome 50% & 2 nd Dome 40%

11 Sl.No.DescriptionUnit Tender Quantity Tentative Revised Qty Executed Qty.Physical Progress Up to December In JanuaryCumulative Up to December In JanuaryCumulative 1Earth Work in ExcavationCum575900893.5920.00893.592 22.49%0.00%22.49% 2 Silver Sand Filling/ yellow sand filling Cum460410 407.7830.00407.783 3Plain Cement ConcreteCum18162.6160.0062.616 4 Reinforced Cement Concrete Cum255.3171.5370.00171.537 5Brick WorkCum175 128.0940.00128.094 6ReinforcementMt33 10.3340.0010.334 7Back FillingCum280780775.1380.00775.138 8PlasterCum3365 9ShutteringSqm1110 1019.2870.001019.287 10FlooringCum1905

12

13

14 Name of Contractor :- M/s Viraj Projects (I) Pvt. Ltd. Name of Structure :- Public Rain Shelter Cum Dala Arcade. Brief Description of the Project as on 31 st January 2016 Excavation :- 70% Completed. Filling Below Foundation ( Yellow Sand) :- 65% Completed. Column Foundation (Base Raft) :- 16 Nos.. Out of 22 Nos. Completed Column Casting 1 st Lift :-18 Nos.. Out of 28 Nos. Completed Column Casting 2 nd :- 12 Nos.. Out of 28 Nos. Completed Column Casting 3 rd :- 10 Nos. Out of 28 Nos. Completed Toilet Block Slab at (+)3.45 m Level :- 1 No. Out of 4 Nos. Completed Lintel Casting :- 40 % Complete Damp Proof Course Work :- 40 % Completed Base Raft for Brick Work :- 60% Complete Brick Work in Sub- Structure :- 60% Complete Brick Work in Super Structure :- 45% Complete Inside Shop Brick Work :- 5% Completed Silver Sand Filling (Below Floor) :- 25% Completed Grade Slab :- 20% Completed

15 Sl.No.DescriptionUnit Tender Quantity Tentative Revised Qty Executed Qty.Physical Progress Up to December In JanuaryCumulative Up to December In JanuaryCumulative 1Earth Work in ExcavationCum205047003130.5460 9.79%0.00%9.79% 2 Silver Sand Filling/ yellow sand filling Cum126740002856.2570 3Plain Cement ConcreteCum900146.4670 4 Reinforced Cement Concrete Cum1100426.2220 5Brick WorkCum1209.04545.5840 6ReinforcementMt15025.2230 7Back FillingCum750320.3030 8Anti Termite (Base & Wall)Sqm385056001557.4660 9Anti Termite (Below Floor)Sqm3300654.2860 10Damp Proof CourseSqm115.556.4130 11Earth DisposlCum53025002146.5050 12PlasterCum12650000 13ShutteringSqm7450877.9390 14FlooringCum6420

16

17

18

19 Name of Contractor :- M/s Viraj Project (I) Pvt. Ltd. Name of Project :- Eco-Camp Complex Brief Description of the Project as on 31 st January, 2016 Large Hut (10 Nos.) Excavation :- 7 Out of 10 Nos Hut Completed. Foundation :- 7 Out of 10 Nos Hut Completed. Column upto Plinth Level Slab :- 7 Out of 10 Nos Hut Complete. Casting of Plinth Slab :- 6 Out of 10 Nos Hut Completed. Column up to Eaves Beam Bottom :- 4 Out of 10 Nos Hut Completed. Casting of Eaves Beam :- 4 Out of 10 Nos Hut Completed. Small Hut (20 Nos.) Excavation :- 9 Out of 20 Nos Hut Completed. Foundation :- 9 Out of 20 Nos Hut Completed. Column upto Plinth Level Slab :- 9 Out of 20 Nos Hut Completed. Casting of Plinth Slab :- 2 Out of 20 Nos Hut Completed. Column up to Eaves Beam Bottom :- 1 Out of 20 Nos Hut Completed. Casting of Eaves Beam :- 1 Out of 20 Nos Hut Completed.

20 Eating House (1 No.) Excavation :- Completed. Foundation :- Completed. Column up to Plinth Level Slab :- Completed. Casting of Plinth Slab :- Completed. Column up to Eaves Beam Bottom :- Completed. Casting of Eaves Beam :- Completed. Toilet Block (2 Nos.) Excavation :- 2 Out of 2 Nos Block Completed. Plain Cement Concrete :- 2 Out of 2 Nos Block Completed. Yellow Sand Filling :- 2 Out of 2 Nos Block Completed. Brick Work Below Foundation :- 2 Out of 2 Nos Block Completed. Foundation :- 2 Out of 2 Nos Block Completed. Column up to Plinth Level Slab :- 2 Out of 2 Nos Block Completed. Tie-Beam :- 1 Out of 2 Nos Block Completed Reception Block (1 No.) Excavation :- Completed. Plain Cement Concrete :- Completed. Brick Wall below foundation :- Completed Yellow Sand Filling :- Completed. Foundation :- Complete. Pedestal upto Plinth Level Slab :- Complete

21 Sl.No.DescriptionUnit Tender Quantity Tentative Revised Qty Executed Qty.Physical Progress Up to December In JanuaryCumulative Up to December In JanuaryCumulative 1Earth Work in ExcavationCum60080004114.29325.264439.55 7.94% 1.236% 9.18% 2 Silver Sand Filling / Yellow Sand Filling Cum2631500840.1817.75857.93 3Plain Cement ConcreteCum11161.33213.16774.499 4 Reinforced Cement Concrete Cum344700317.81382.757400.57 5Brick WorkCum480.560.7936.2597.04 6ReinforcementMt406030.605.4436.04 7ShutteringSqm267843002128.07345.982474.05 8Back FillingCum51372001941.88 9FlooringCum1033

22

23

24 Name of Contractor :- M/s Viraj Project (I) Pvt. Ltd. Name of Project :- Drainage Brief Description of the Project as on 31 st January 2016 WORK NOT YET STARTED. Sl. No.Description of ItemsUnit Tender Qty. Executed Quantity% Physical Progress Up to Decembe r In JanuaryCumulative Up to Decembe r In JanuaryCumulative 1Earth Work in ExcavationCum 9818 000 0.00% 2 Silver Sand / Yellow Sand Filling Cum 2380 000 3Plain Cement ConcreteCum 000 4 Reinforced Cement Concrete Cum22.4000 5Brick WorkCum 1806 000 6ReinforcementMt 2.24 000 7PlasteringSq m 10413 000

25 Name of Contractor :- M/s Viraj Project (I) Pvt. Ltd. Name of Project :- Beach Shelter Brief Description of the Project as on 31 st January, 2016 WORK NOT YET STARTED. Sl. No.Description of ItemsUnit Tender Qty. Executed Quantity% Physical Progress Up to Decemb er In JanuaryCumulative Up to Decemb er In JanuaryCumulative 1 Earth Work in Excavation Cum000 0.00% 2 Silver Sand / Yellow Sand Filling Cum000 3Plain Cement ConcreteCum000 4 Reinforced Cement Concrete Cum000 5Brick WorkCum000 6PlasteringSq m000 7FlooringSq m000

26 Name of Contractor :- M/s N.K. Basu & Company. Name of Project :- Bus Terminal Brief Description of the Project as on 31 st January, 2016 Waiting Area. Foundation :- Completed. Column :- Completed up to 1 st Eaves Beam Top Tie Beam :- Completed. Eaves Beam :- Completed. Brick Work :- Stair Brick Work Completed. Back Filling :- Completed. Plastering work :- Completed. Grade Slab :- Completed. Food & Drink Facility. Foundation :- Completed. Column :- Completed. Tie Beam :- Completed. Eaves Beam :- Completed. Back Filing :- Completed. Brick Work :- Completed. Plastering work :- Completed Grade Slab :- Completed.

27 Toilet Block. Foundation :- Completed. Column :- Completed. Tie Beam :- Completed. Back Filing :- Completed. Lintel & Chajjah Casting :- Completed. Eaves Beam :- Completed. Brick Work :- Completed. Plastering :- Completed. Tourist & Information Office. Excavation :- Completed. Foundation :- Completed. Pedestal :- Completed. Back Filling :- Completed. Tie-Beam :- Completed. Column :- Completed up to Eaves Beam Bottom Septic Tank & Soak Pit :- Out of 2 Nos. 1 no. Completed.

28 Sl.No.DescriptionUnit Tender Quantity Tentative Revised Qty Executed Qty.Physical Progress Up to December In January Cumulativ e Up to December In JanuaryCumulative 1Earth Work in ExcavationCum18019001847.6750 19.99%0.00%19.99% 2Yelow Sand FillingCum 405404.2180 3Silver Sand FillingCum335 106.860 4Plain Cement ConcreteCum110 96.1440 5 Reinforced Cement Concrete Cum191300 261.8340 6Brick WorkCum170.75 105.9130 7ReinforcementMt29 13.6650 8ShutteringSqm1815 1277.920 9Back FillingCum12512751263.0960 10Septic Tank & Soak PitNos 2 101 11PlasterCum935 924.7190

29

30

31

32 Name of Contractor :- M/s N.K. Basu & Company. Name of Project :- Leach Pit Based Toilet Brief Description of the Project as on 31 st January 2016 Out of 20 Nos. Unit – Work is on Progress in 7 Nos. Unit. 5 Nos Block Completed up to Super Structure. 2 Nos Block Completed up to Sub Structure. Sl.No.DescriptionUnit Tender Quantity Tentative Revised Qty Executed Qty.Physical Progress Up to December In January Cumulativ e Up to December In JanuaryCumulative 1. Construction of temporary toilet blocks with Leach Pit based onsite treatment system - 10 toilet per unit Nos2061730%5%35%

33

34 Name of Contractor: - M/s N.K. Basu & Company Name of Structure: - Temporary & Permanent Composite Plant Brief Description of Status as of 31 st January 2016 Not Yet Started. Sl. No.Description of ItemsUnit Tender Qty. Executed Quantity% Physical Progress Up to Decem ber In January Cumulativ e Up to Decem ber In January Cumulativ e 1 Earth Work in Excavation Cum253000 0.00 % 2 Silver Sand / Yellow Sand Filling Cum115000 3 Plain Cement Concrete Cum473000 4 Reinforced Cement Concrete Cum181000 5Brick WorkCum20000 6PlasteringSqm243000

35 FINANCIAL PROGRESS AS OF 31 st January 2016 Sl. no.Name of ContractorName of JobContact Value Financial Progress Up to December In JanuaryCumulative 1M/s Viraj Project (P) Ltd. Construction of Rain Shelter cum Nat Mandir and Rain Shelter Cum Dala Arcade 132,839,162.0021.351%0.00%21.351% 2M/s Viraj Project (P) Ltd. Construction of Eco-, Beach Shelter & Drainage 91,779,042.9515.11%2.73%17.84% 3M/s N.K. Basu & Company Construction of Bus Terminal 18,517,073.9342.62%0.00%42.62% 4M/s N.K. Basu & Company Construction of Leach Pit Based Toilet & Temporary and permanent composite solid waste facility 21,224,549.757.25%2.74%9.99%

36 PAYMENT DETAILS Package -1: Construction of Public Rain Shelter cum Nat Mandir & Public Rain Shelter cum Dala Arcade Package -2: Construction of ECO - Camp Complex, Beach Shelter and Drainage Sl. No. RA Bill reference & DateDate of Certification Amount (Rs) Remarks 1. Mobilisation Advance 6.642 million 2.1 st RA Bill25/8/201591.94 Lac 3.2 nd RA Bill18/09/2015 22.63 Lac 4.3 rd RA Bill01/10/2015 44.93 Lac 5.4 th RA Bill18/12/2015 43.06 Lac 6.5 th RA Bill28/12/2015 33.09 Lac 7.6 th RA Bill13/01/2016 48.47 Lac Sl. No. RA Bill reference & DateDate of Certification Amount ( Rs) Remarks 1. Mobilisation Advance 4.589 million 2.1 st RA Bill25/8/201523.75 Lac 3.2 nd RA Bill18/09/2015 18.53 Lac 4.3 rd RA Bill01/10/2015 5.68 Lac 5.4 th RA Bill18/12/2015 25.32 Lac 6.5 th RA Bill28/12/2015 25.62 Lac 7.6 th RA Bill13/01/2016 26.34 Lac 8.7 th RA Bill01/02/2016 30.42 Lac

37 Package -3: Construction of Leach Pit Based Toilet and Solid Waste Management Facility Package -4: Construction of Bus Terminus Sl. No. RA Bill reference & Date Date of Certification Amount (Rs.)Remarks 1. Mobilisation Advance1.061 million 2.1 st RA Bill 23/01/2016 21.19 Lacs Sl. No. RA Bill reference & DateDate of CertificationAmount (Rs.)Remarks 1. Mobilisation Advance0.925 million 2.1 st RA Bill25/8/201523.90 Lac 3.2 nd RA Bill31/10/2015 15.77 Lac 4.3 rd RA Bill7/12/2015 31.29 Lac

38 SITE PROGRESS PHOTOGRAPH AS ON 31 st January 2016

39 BUS TERMINAL-TOILET BLOCK BUS TERMINAL-TOURIST & INFORMATION CENTRE BUS TERMINAL-WAITING AREABUS TERMINAL-FOOD & DRINK FACILITY

40 LEACH PIT BASED TOILET – IN ROAD NO. 1LEACH PIT BASED TOILET – IN ROAD NO. 5 ECO CAMP – LARGE HUT ECO CAMP – EATING HOUSE

41 ECO CAMP - SMALL HUTECO CAMP – TOILET BLOCK II ECO CAMP – RECEPTION PUBLIC RAIN SHELTER CUM DALA ARCADE

42 PUBLIC RAIN SHELTER CUM NAT MANDIR