OVERVIEW  Review of completed projects  Update on large construction projects  Update on other miscellaneous projects.

Similar presentations


Presentation on theme: "OVERVIEW  Review of completed projects  Update on large construction projects  Update on other miscellaneous projects."— Presentation transcript:

1

2 OVERVIEW  Review of completed projects  Update on large construction projects  Update on other miscellaneous projects

3 COMPLETED PROJECTS  Athletic Complexes $12M  Mat-Su Day School $12.4M  Valley Pathways $22.5M  Big Lake ES Reno Ph I $2.2M  Houston/Palmer Jr MS Lockers $335K  Flooring Replacements Ph I $2M  Palmer HS Mechanical Upgrades $5.5M  Trapper Creek ES Roof $1M  Swanson ES Ext Upgrades $200K  Willow ES Roof $1.3M  Joe Redington Sr MS/HS $65M  CTHS Addition $16M  Houston HS Exterior Siding $600K  ADA Upgrades District Wide $1.5M  Washroom Upgrade District Wide $800K  Palmer HS, Palmer Jr MS, Cottonwood Creek ES, Pioneer Peak ES Roofs $3.8M

4 DENA’INA ES $26.5M  Design: Bettisworth North  Construction: FE Const.  44,224 SF  K through 5 school  Work started April 2015 Approx. 70% complete  On schedule to occupy 2016  Tour March 24, 9AM

5 DENA’INA ES Exterior Interior Second Floor

6 IDITAROD ES $25.2M  Design: MCG  Construction: Collins  50,605 SF replacement school. Pre-K thru 5  Work started May 2015, approx. 75% complete  On schedule to occupy 2016  Tour March 24, 11AM

7 IDITAROD ES Common Area Classroom

8 FRONTERAS CHARTER SCHOOL $6.9M  Contractor: Howdie Const.  Funded by USDA loan and $500K from MSB  Construction 55% complete  Access road from Seward Meridian is in place  Construction schedule is to occupy 2016

9 FRONTERAS CHARTER SCHOOL Framing Complete

10 ATHLETIC FIELD IMPROVEMENTS $6.4M  Play court upgrades at Finger Lake, Snowshoe, Larson, Glacier View and Houston High completed in 2014  All summer 2015 work completed with the exception of the Iditarod softball/baseball turf in-fields which are on weather hold until spring 2016

11 ADDITIONAL PROJECTS  Back-Up Generators, District Wide $2.6M - Design: AMC Engineering, 1oo% design - Wolverine Supply the low bidder - Contract includes base bid; Wasilla MS, Wasilla HS, Palmer HS -- Awarded alternates; Big Lake ES, Butte ES, Snowshoe ES, Willow ES and the Operations & Maintenance Building - Contract award approved March 1 by the assembly  Big Lake ES Renovation Ph II $800K, and ADA Parking Upgrades $200K - Flooring, washroom partitions, and parking lot are complete - Corridor lighting/ceiling contract approved by the assembly Jan 12 with work to start spring/summer 2016  District Wide HVAC Upgrades $7.1M - Design: PDC Engineers, Contractor: Wirtanen Construction - Scope includes upgrading building controls from pneumatic to direct digital controls and is approximately 65% complete - Work to continue into the 2017 school year with ph II advertised now

12 ADDITIONAL PROJECTS cont.  District Wide Energy Upgrades $3.1M (Gym Lighting and Windows) - New LED Gym lighting project is complete - Partial window replacements at 18 schools will be advertised this month for summer 2016 construction  Flooring Replacements $900K (2010 and 2011 flooring bond balances) - Poured rubber gym floors at Sherrod and Swanson are complete - Poured rubber gym floor at Pioneer Peak Elementary over spring break - Next phase includes carpet at Butte, Cottonwood, Finger Lake, Goose Bay, Sherrod, Swanson, Trapper Creek, and Willow Elementary Schools for a total of 108,000 SF of new carpet, currently advertised for bids  Roof Bond Balance $800K - Sutton ES reroof and Tanaina ES roof modifications closed Jan 2016 -- Contract to EP Roofing approved Feb 16 for summer 2016 completion

13 QUESTIONS