Download presentation
Presentation is loading. Please wait.
Published byChristiana Day Modified over 8 years ago
2
OVERVIEW Review of completed projects Update on large construction projects Update on other miscellaneous projects
3
COMPLETED PROJECTS Athletic Complexes $12M Mat-Su Day School $12.4M Valley Pathways $22.5M Big Lake ES Reno Ph I $2.2M Houston/Palmer Jr MS Lockers $335K Flooring Replacements Ph I $2M Palmer HS Mechanical Upgrades $5.5M Trapper Creek ES Roof $1M Swanson ES Ext Upgrades $200K Willow ES Roof $1.3M Joe Redington Sr MS/HS $65M CTHS Addition $16M Houston HS Exterior Siding $600K ADA Upgrades District Wide $1.5M Washroom Upgrade District Wide $800K Palmer HS, Palmer Jr MS, Cottonwood Creek ES, Pioneer Peak ES Roofs $3.8M
4
DENA’INA ES $26.5M Design: Bettisworth North Construction: FE Const. 44,224 SF K through 5 school Work started April 2015 Approx. 70% complete On schedule to occupy 2016 Tour March 24, 9AM
5
DENA’INA ES Exterior Interior Second Floor
6
IDITAROD ES $25.2M Design: MCG Construction: Collins 50,605 SF replacement school. Pre-K thru 5 Work started May 2015, approx. 75% complete On schedule to occupy 2016 Tour March 24, 11AM
7
IDITAROD ES Common Area Classroom
8
FRONTERAS CHARTER SCHOOL $6.9M Contractor: Howdie Const. Funded by USDA loan and $500K from MSB Construction 55% complete Access road from Seward Meridian is in place Construction schedule is to occupy 2016
9
FRONTERAS CHARTER SCHOOL Framing Complete
10
ATHLETIC FIELD IMPROVEMENTS $6.4M Play court upgrades at Finger Lake, Snowshoe, Larson, Glacier View and Houston High completed in 2014 All summer 2015 work completed with the exception of the Iditarod softball/baseball turf in-fields which are on weather hold until spring 2016
11
ADDITIONAL PROJECTS Back-Up Generators, District Wide $2.6M - Design: AMC Engineering, 1oo% design - Wolverine Supply the low bidder - Contract includes base bid; Wasilla MS, Wasilla HS, Palmer HS -- Awarded alternates; Big Lake ES, Butte ES, Snowshoe ES, Willow ES and the Operations & Maintenance Building - Contract award approved March 1 by the assembly Big Lake ES Renovation Ph II $800K, and ADA Parking Upgrades $200K - Flooring, washroom partitions, and parking lot are complete - Corridor lighting/ceiling contract approved by the assembly Jan 12 with work to start spring/summer 2016 District Wide HVAC Upgrades $7.1M - Design: PDC Engineers, Contractor: Wirtanen Construction - Scope includes upgrading building controls from pneumatic to direct digital controls and is approximately 65% complete - Work to continue into the 2017 school year with ph II advertised now
12
ADDITIONAL PROJECTS cont. District Wide Energy Upgrades $3.1M (Gym Lighting and Windows) - New LED Gym lighting project is complete - Partial window replacements at 18 schools will be advertised this month for summer 2016 construction Flooring Replacements $900K (2010 and 2011 flooring bond balances) - Poured rubber gym floors at Sherrod and Swanson are complete - Poured rubber gym floor at Pioneer Peak Elementary over spring break - Next phase includes carpet at Butte, Cottonwood, Finger Lake, Goose Bay, Sherrod, Swanson, Trapper Creek, and Willow Elementary Schools for a total of 108,000 SF of new carpet, currently advertised for bids Roof Bond Balance $800K - Sutton ES reroof and Tanaina ES roof modifications closed Jan 2016 -- Contract to EP Roofing approved Feb 16 for summer 2016 completion
13
QUESTIONS
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.