Status of the TileMuon Digitizer Board Victor Ferraz
2
TMDB Status PCB production already concluded Components assembling should start this week (depending on the delivered time) Most of the components are already in Brazil, but they are still stuck in the customs. The furnisher said that it should be delivered this week (not so sure) 2
3
Transition Board The layout of the transition board is concluded PCB production and assembling should start this week and be delivered on the next week 3
4
Summary The TMDB Print Circuit Board is ready. Assembling is waiting components Transition Board should start this week We are focused on the acquisition of components, production and assembling. After that, we will focus on developing the firmware Our current priority is to have the finished boards 4