1 Week 1: Project Overview Customer: Debbie Conway Guide: Brian Thorn P09453

2 Team Members and Organization Fort Stanwix Energy Audit Project Manager (ISE): Kyle Mininni Assistant Lead (ME): Ryan Anderson ISE: Mauricio Pommier EE: Joanne Okvath Chief Engineer (ME): Rob Hudson

3 Project Description Project Background: Fort Stanwix National Monument (FSNM) is situated in Rome, New York. It was vital in the outcome of the French and Indian War and the American Revolution. The Fort consist of three primary energy use locations: the Willet Visitor Center, the Fort and a maintenance shed. The addition of the Willett Center has dramatically added to FSNM’s energy consumption. It is greater than original expectations and estimations, and currently accounts for 2/3rds of FSNM total energy cost. The team will be divided by traditional functional engineering roles. Problem Statement: The overall objective of this project is to identify short and long-term opportunities to reduce energy consumption and energy costs at the Fort Stanwix National Monument. Objectives/Scope: Conduct pre-assessment data collection Perform on-site energy assessment Develop energy savings opportunities Review Current electricity billing structure Indentify and evaluate alternative energy service companies (ESCOs) Implement a pilot renewable demonstration-scale energy project

4 Deliverable Status Week 1 (12/5): DeliverableStatus Needs assessment (preliminary)Complete – meet with customer 12/2 Project Overview PresentationComplete Project Plan elements (preliminary)Complete 1 page project summaryComplete Work breakdown structure w/ team rolesComplete – work not fully assigned 2 quarter schedule /milestonesComplete – altered given nature of P09453 Team norms/values & planComplete

5 Key Challenges Complex nature of current billing and energy usage Organizing and analyzing large amounts of data Large amount of potential variables affecting energy usage and consumption Energy saving opportunities budget constraint FSNM accessibility issues Lack of physical interface with customer