www.P3forPA.com PennDOT CNG Fueling Stations for Public Transit Agencies Pennsylvania Department of Transportation A Public-Private Partnership (P3) Project
2
www.P3forPA.com 2 Scope of Project 26 Transit Agencies 29 Transit Agency Locations Construction of compressed natural gas (CNG) fueling stations Modifications to vehicle maintenance facilities Modifications to vehicle storage garages
3
www.P3forPA.com 3 Project Schedule Issuance of Final RFP– December 2015 Technical Proposals Submitted– January 14, 2016 Financial Proposals Due– February 4, 2016 Anticipated Announcement of Preferred Proposer– February 19, 2016 Commercial Close– 90 days after Announcement of Preferred Proposer
4
www.P3forPA.com 4 PennDOT BPT Team Bob Sharp, Division Chief rosharp@pa.gov rosharp@pa.gov 717-783-9461 Nick Baldwin, Program Coordinator nbaldwin@pa.gov nbaldwin@pa.gov 717-787-1209 Sam Plocinski, Program Coordinator splocinski@pa.gov splocinski@pa.gov 717-214-9757
5
www.P3forPA.com 5 Gannett Fleming Team Scott Zeevaart, Program Manager Scott Shriner, WO Manager/Asst Prog Mgr/Zone Construction Mgr Michael MacAllister, Zone Construction Mgr Brett Brenize, Zone Construction Manager
6
www.P3forPA.com 6 CDM Smith Team Timothy King, Senior Architect Matt Sickles, Senior Engineer Grant Holland, P3 Practitioner Ryan Mitchell, P3 Practitioner
7
www.P3forPA.com 7 Contact Information www.P3forPA.com Public-Private Partnerships (P3) Office Dale Witmer, Deputy Director (717) 705-4235 dalwitmer@pa.gov
8
www.P3forPA.com PennDOT CNG Fueling Stations for Public Transit Agencies Pennsylvania Department of Transportation A Public-Private Partnership (P3) Project