Grand Valley Metropolitan Council March 3, 2016 Erick Kind Region Engineer MDOT-Grand Region
2
Grand Region Boundary o October 1, 2015 o 13 Counties o o 1.5 Million People o 4300 lane miles
3
US-131 Southbound Weave/Merge Lane, Pavement & Bridge Repairs Project Summary Project will address road and bridge conditions, along congestion with CMAQ funding US-131 Concrete Pavement Repairs Pearl Street to Ann Street (Southbound) M-11 (28 th Street) to Wealthy Street (North and Southbound) Bridge Widening and Rehabilitation US-131 over Richmond Street and Indian Mill Creek (Southbound) Construct Southbound Weave/Merge Lane Connect Ann Street On-Ramp to Leonard Street Off-Ramp
4
US-131 Southbound Weave/Merge Lane, Pavement & Bridge Repairs Construction Cost: $7.8 Million Schedule: * Off line foundation work underway Project Description: Concrete Pavement Repairs Pearl to Ann Street (Southbound) Bridge Widening US-131 over Richmond and Indian Mill Creek. Weave/Merge Lane To Connect Ann to Leonard Traffic Volume: 53,000 South of Leonard (SB) 8% Commercial 48,000 Between Leonard/Ann (SB) LettingStartCompletion December 2015February 2016*October 2016
5
Local Agency Project Coordination
6
US-131 Traffic Control Plan (TCP) Maximize Work Zone Safety & Minimize Mobility Impacts Richmond Street Eastbound Directional Detour; Westbound maintained Maintain Two Lanes On US-131 Southbound – most weekdays Maintain One Lane On US-131 Southbound US-131 Southbound Traffic During Designated Night and Weekend Closures US-131 NB & SB: M-11 to Wealthy Street Night and Weekend lane closures PCMS and DMS Message boards will be utilized Lane Closure Updates, (List Serve, LCAR), Project Website http://www.michigan.gov/mdot/0,4616,7-151-9621_11008-372624--,00.html http://www.michigan.gov/mdot/0,4616,7-151-9621_11008-372624--,00.html
7
Project Traffic Control Summary All lanes on US-131 will be open until April 23 SB US-131 single lane closure beginning April 23 extending through September SB US-131 double lane closure on weeknight and weekends Richmond Street will be open to both directions of traffic until mid-March Richmond Street will be opened for SB-WB traffic. EB-NB traffic will be detoured starting mid-March
8
Ramp Closure Schedules The following ramps will be closed during different stages of the project TBD: Turner Avenue (just north of Ann Street) ramp to southbound US-131 Southbound US-131 ramp to Leonard Street Eastbound I-196 ramp to southbound US-131 Southbound US-131 ramp to Pearl Street
9
THANK YOU!