Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Similar presentations


Presentation on theme: "Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –"— Presentation transcript:

1 Elevating the Quality of Life in the District

2 Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE – AUGUST 2015 TO APRIL 2016  TIMELINE – EASTER BREAK 2016  TIMELINE – APRIL 2016 TO JULY 2016  ACCESS & FLOW  Foundation to Grade Building Permit  Building Permit  NEXT STEPS  18, Feb. to 3, Mar. Activities two week look ahead.  Construction Images of Courtyard & 1956 Building.  Construction Milestone.  Frequently Asked Questions.  Q & A Elevating the Quality of Life in the District

3 RULES OF THE ROAD  RESPECT EACH OTHER  CELLPHONES OFF OR ON VIBRATE  Q&A WILL BE TAKEN AT THE END OF THE PRESENTATION

4 Elevating the Quality of Life in the District

5 AFTER RENOVATION BEFORE RENOVATION

6 Elevating the Quality of Life in the District AFTER RENOVATION BEFORE RENOVATION

7 Elevating the Quality of Life in the District BEFORE RENOVATION AFTER RENOVATION

8 Elevating the Quality of Life in the District AFTER RENOVATION BEFORE RENOVATION

9 Elevating the Quality of Life in the District BEFORE RENOVATION AFTER RENOVATION

10 Elevating the Quality of Life in the District SECTIONS

11 Elevating the Quality of Life in the District

12

13 CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015

14 Elevating the Quality of Life in the District

15 CONSTRUCTION STRATEGY  TIMELINE – AUGUST 2015 TO APRIL 2016

16 Elevating the Quality of Life in the District

17 TIMELINE AUGUST 2015 – APRIL 2016 UNDER CONSTRUCTION EGRESS DURING CONSTRUCTION LOGISTICS AND PHASING PLAN ARE CONTINENT UPON OBTAINING PERMITS AND DOEE APPROVALS PER TURNER’S SCHEDULE

18 Elevating the Quality of Life in the District CONSTRUCTION STRATEGY  TIMELINE – EASTER BREAK 2016

19 Elevating the Quality of Life in the District TIMELINE EASTER BREAK 2016 UNDER CONSTRUCTION LOGISTICS AND PHASING PLAN ARE CONTINENT UPON OBTAINING PERMITS AND DOEE APPROVALS PER TURNER’S SCHEDULE

20 Relocation of IT Closet 1970 Building

21 Relocation of IT Closet 1970 Building STORAGE ROOMS SHEPHERD ELEMENTARY SCHOOL PHASE 2013-2016 Proposed Program Area per Area perRoom WORKROOM - 1 (First Floor Building 1931) 300 470 57% WORKROOM - 2 (First Floor Building 1970300 152 -49% TOTAL FOR WORKROOMS 600 622 4% STORAGE - 1 - BOOK STORAGE (Ground Floor) 400 433 8% STORAGE - 2 (First Floor Building 1970) 400 79 -80% SUPPLY STORAGE/RECEIVING (Ground Floor) 350 412 18% TOTAL FOR STORAGES 1,150 924 -20%

22 Relocation of IT Closet 1970 Building

23 Elevating the Quality of Life in the District CONSTRUCTION STRATEGY  TIMELINE – APRIL 2016 TO JULY 2016

24 Elevating the Quality of Life in the District

25 TIMELINE APRIL 2016 – JULY 2016 UNDER CONSTRUCTION EGRESS DURING CONSTRUCTION LOGISTICS AND PHASING PLAN ARE CONTINENT UPON OBTAINING PERMITS AND DOEE APPROVALS PER TURNER’S SCHEDULE

26 Elevating the Quality of Life in the District TWO CREPE MYRTLE TREES WILL BE RELOCATED 1 2

27 Excavation & Demo in Courtyard

28

29

30 Installation of Foundation System & Elevator Pit in Courtyard

31

32 Courtyard Retaining Wall Installation

33

34 Courtyard Concrete Slab Installation

35 Erection of Structural Steel in Cafeteria & Roof of 1956 Building

36 Erection of Structural Steel in Cafeteria & Sprinkler of 1956 Building

37 Erection of Structural Steel in the 1956 Building

38 Courtyard Concrete Slab Retaining Wall & Elevator Shaft Installation

39 1956 Building Addition Structural Steel Installation

40 1956 Building Addition Structural Steel, Framing Installation

41

42

43

44 1956 Building Addition Structural Steel Installation

45 Entrance Structural Steel Installation

46 Courtyard Structural Steel & Sprinkler Installation

47 1956 Building Addition Metal Deck Installation

48 1956 Building Addition Concrete Slab Installation

49 1956 Building Addition MEP Installation

50 1956 Building Addition Structural Steel Framing and MEP Installation

51 Courtyard Steel and Opening Installation

52

53

54 Playground Entrance Steel and Opening Installation

55 Elevating the Quality of Life in the District TWO CREPE MYRTLE TREES WILL BE RELOCATED 1 2

56 Infiltration System Impact Crepe Myrtle Trees in Images

57 Infiltration System Impact Crepe Myrtle Trees Relocated

58 Silver Maple Tree Impact Relocated Crepe Myrtle Tree

59 Elevating the Quality of Life in the District CONSTRUCTION MILESTONE  COMMENCEMENT OF CONCRETE WORK; OCTOBER  COMMENCEMENT OF ELEVATOR SHAFT; NOVEMBER  COMMENCEMENT OF COURTYARD STRUCTURAL STEEL; DECEMBER  JANUARY  COMMENCEMENT OF MECHANICAL, ELECTRCAL & PLUMBING WORK  INFILTRATION TRENCH INSTALLATION  SPRINKLER MAIN SERVICE LINE INSTALLATION PARKING AREA  CONCRETE SLAB ON DECK INSTALLATION  1956 ADDITION EXTERIOR FRAMING

60 Shepherd ES Logo in Courtyard & Mural

61 Frequently Asked Questions 1. Will the asphalt area on the playground be repaired or replaced? Answer:- The asphalt will be repaired 2. The Mural on the concrete wall will not be impacted by the construction Activities. 3. All Egress routes are accessible during Construction Per Building Codes. 4. Air monitoring scheduled to be performed once per month. 5. Memorial Gardens will be restored.

62 Elevating the Quality of Life in the District NEXT STEPS TWO WEEK LOOK AHEAD  EXCAVATION ON INFILTRATION TRENCH AT SOUTH SITE  EXCAVATION OF SPRINKLER MAIN LINE PARKING AREA  ERECTION OF STRUCTURAL STEEL IN COURTYARD AND 1956 BUILDING  INSTALLATION OF 1956 ADDITION EXTERIOR FRAMING  INTERIOR PARTITION INSTALLATION  MEP INSTALLATION

63 Kenneth Diggs DGS Associate Director DGS Government Affairs & Communications kenneth.diggs@dc.gov (202) 580-9361 Elevating the Quality of Life in the District


Download ppt "Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –"

Similar presentations


Ads by Google