1 MICE UK meeting at RAL 05 May 2005 Integrated Design & Safety Review Presented by
2
2 Work carried out so far: Design audits: Beam line & target (needs further revision) Fibre tracker (TRD to be modified to insert book marks) Cherenkov 2 (complete) Iron Shielding (TRD to be modified to insert bookmarks) Safety audits: Cherenkov 2 (Done) Iron Shielding (Done) Beam line & target (needs further revision)
3
3 Work expected to be done before the next MICE Collaboration Meeting: Design audits: Engineering infrastructures Safety audits: Engineering infrastructures Fibre trackers
4
4 Example of the work done so far: For the table summarising the work done to date, click: http://www.physics.ox.ac.uk/design/MICE/mice_design-safety_page.htm For the example on Cherenkov 2 Design audit, click: on the corresponding box in that table.