ACS news RF cabling campaign: DONE Final tests cavity tuning motor (ctrl): in progress recabling software upgrade Water cooling: ADT static pressure test: DONE re-installation of equipment (pressure valves etc): DONE procurement of demineralized water & final tests: wk9 Pending/ongoing: arc detector installation: in progress cavity racks installation (Daniel’s racks): in progress
2
ADT news RF cables: in progress Intlk&io tests: starting next week! Pending : MUX (Andy-Daniel) Define patch panels Install equipment Predrivers (Daniel) Rack cleaning
3
HV bunkers & power converters install flowmeters TS/CE: DONE (except 4 holes!) SC (Salomon): first visit: DONE next round: detailed inspection... inspection of AB/PO: not organized yet! Upgrade of electrical cells (TS/EL): cabling wk 9 – 11 (waiting for confirmation) New ICs: 1 week stop in 3 months Pending: Spare power converter to be re-cabled (AB/PO) HV limiter (automatic crowbar firing system): in progress
4
Faraday Cages Urgent: check RF connectors & cable calibration badly mounted connectors: problem fixed false floor: DONE Pending: Doors (contact & key)?
5
Platform HOM loads installation of cable trays (Nicou & FSU) Cryo: installation of ACS cav He press meas: wk7 (not finished) RF cables installation (Nicou&Co.) CavFWD cables CavRFL cables Arc detectors (C.Nicou) Pull cables + 1 additional cable (daniel) Install equipment Zone cleaning clean all zone after TS/CV chilled water installation: DONE
6
RUX45 WRL installation: in progress ACS Modules: in progress MC Couplers mount MC couplers mechanics (starts next wk) cable MC couplers connect to WG Install and cable Arc detectors CALIBRATE ANTENNA CABLES - Ph. B./JCP ?? Vacuum ctrl chassis: AT/VAC late: missing PLC chassis...in progress
7
RB’s ADT, APW Install amplifiers (Eric) cabling & cable testing: in progress Q7-Q9-ADT prepare and install patch panels (Eric): STARTED install ADT electrical distrib box (TS/El): ? water cooling connections (Eric): DONE replace/repair few RF cables check connection to earth
8
SR4 Install GPS antenna – in progress Produce DIC: DONE?? False floor Install chassis Cleaning (zone, racks) Ventilation upgrade (JCP)!!