Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 1 Claude DEHAVAY - CERN/AB/CO/HT Installation Readiness Report - Controls
2
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 2 Presentation layout Our target schedule Which components and how far are we? Technical difficulties What we’ve learnt ? Enhancements Messages to the users Conclusions
3
3 Our target schedule The TS/IC Master schedule The HWC dates Plannings from users: - PO - Cryo - QPS - PIC - SU - BDI - RadMon From: Stephen Page 7-8 05/09/2005 8-1 05/12/2005 4-5 09/01/2006 3-4 05/06/2006 5-6 17/07/2006 6-7 18/09/2006 1-2 20/11/2006 2-3 15/01/2007
4
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 4 Presentation layout Our target schedule Which components and how far are we? Technical difficulties What we’ve learnt ? Enhancements Messages to the users Conclusions
5
5 AB/CO Components (1/2) For Hardware Commissioning: General services (Ethernet, Power network) WorldFip fieldbus Specific hardware designs, furniture, delivery for Timing, WorldFip, PIC. WorldFip gateways, Technical consoles, Remote reboot
6
6 AB/CO Components (2/2) For beam commissioning: LHC Beam Interlock (24 VME syst.) LHC RF (50 VME syst.) LHC Beam instrumentation (200 VME syst.) LHC Beam transfert (5 VME syst.)
7
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 7 Which components and how far are we ? Timing WorldFip gateways Remote reboot, technical consoles Powering Interlock Controller Cryo Control
8
LHC timing
9
Status of Timing installation (1/2) New designs Ordered (Units) Delivered VME Receiver modules for BDI crates32068% PCI Receiver modules for Gateways150100% GMT : FO driver and FO receiver25100% GMT : Cable driver & Cable receiver25100% Timing crates (Europa)20100%
10
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 10 Status of Timing installation (2/2) Cables and Optical fibers : DIC and installation on schedule Planning : Timing in place in November for PO - LHC MTG-> OK since june 2005 - Pt 8 -> Old HW until July 2005 - Pt 1 -> New HW on Week 25 - Pt 8-> New HW on Week 30 -> Installation is in progress according to the planning.
11
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 11 Which components and how far are we ? Timing WorldFip gateways Remote reboot, local stations Powering Interlock Controller Cryo Control
12
Node Tap FipDiag Gateway Passive component (Connector) Active component (User interface) Surface = SR Underground = UA, RR, Tunnel Cu/Cu Repeater Remote Reboot A segment in the WorldFip infrastructure Some figures 220 segments (7064 cables) 280 km 8000 nodes 4980 taps 7300 connectors Segment backbone Node
13
Surface = SR Underground = UA, RR, Tunnel Installation schedule for Power Converters Time Gateway Remote Reboot Tap Node 12674 1 : TS/EL Cables and Taps 2 : AB/CO/IS Elec.Qualif. 3 : IT/CS Ethernet/Fibers 4 : AB/CO/HTGateway 5 : TS/EL Power 6 : AB/PO Node interfaces 7 : TS/EL Drop cables 8 : AB/CO Final test FipDiag Cu/Cu Repeater 8 …… 3 ……55
14
14 WorldFip Gateways – Burn in
15
15 WorldFip Gateways – Installed
16
16 WFIP Gateways installation planning for Point1 QPS
17
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 17 Status of WFIP installation (1/3) LHC: All WorldFip cables are installed (except the drop cables for Power Converters & Point 7 Left) IP 8 (LSS8L, Arc 7-8, LSS8R, Arc 8-1): = 16% LHC 19 WorldFip gateways All gateways and taps are in place All backbones electrically qualified -> A 3 weeks job completed mid-may 2005
18
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 18 Status of WFIP installation (2/3) To be done for Point 8 (LSS8L, Arc 7-8, LSS8R, Arc 8-1): 1. Equipment interfaces and drop cables installation -> To be done by the Equipment groups and TS/EL -> during June 2005 for PO (LSS8L) 2. Installation of FipDiag and Repeaters 3. Final test of the complete segments (½ day per segment) -> June 30 th for PO (LSS8L)
19
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 19 Status of WFIP installation (3/3) Short term planning: All gateways for Point1-> July 4 th, 2005 QPS for Arc 8-1 (WFIP test)-> July 8 th, 2005 QPS for Arc 7-8 (WFIP test) -> September 1 st 2005 Cryo for Arc 8-1 (WFIP test) -> October 3 rd 2005
20
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 20 Which components and how far are we ? Timing WorldFip gateways Remote reboot, technical consoles Powering Interlock Controller Cryo Control
21
Remote reboot, Local stations (Pt8)
22
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 22 Which components and how far are we ? Timing WorldFip gateways Remote reboot, local stations Powering Interlock Controller Cryo Control
23
36 PICs for 28 Powering Subsectors, managing ~1600 electrical circuits, using more than 1000 cables, & handling ~2400 interlock signals LSS8L + Arc 7-8
24
PIC for A.L8for X.L8for M.L8 PIC Racks in UA83
25
25 PIC Planning 2 PICs are going to commissioned in Sep.05 2 others PICs for the Arc 7-8 in Dec.05: One more in UA83 One in UJ76. Radiation issues => system moved in TZ gallery? The units will be fully tested in the lab in August => dismounted and re-mounted in the undergrounded area by the interlock Team. For the time being, we are optimistic to be on time!
26
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 26 Which components and how far are we ? Timing WorldFip gateways Remote reboot, local stations Powering Interlock Controller Cryo Control
27
27 Cryo Control Architecture [Contribution : Ph.Gayet – AB/CO/IS] Similar architecture for: Refrigerators QRL -> Industrial technology (PLC and PVSS)
28
Local Cryogenic control room Central Cryogenic control room S7-400 as gateway S7-400 Siemens Quantum PCUs PROFIBUS DP networks (3) PROFIBUS PA networks WFIP Networks (4) WFIP Gateways Data server ET200 I/O for Valves & sensors CCC Hardware Architecture for Cryo (1/2) [Contribution : Ph.Gayet – AB/CO/IS] Local Cryogenic Control room
29
Local Cryogenic control room Central Cryogenic control room S7-400 as gateway S7-400 Siemens Quantum PCUs PROFIBUS DP networks (3) PROFIBUS PA networks WFIP Networks (4) WFIP Gateways Data server ET200 I/O for QV & sensors Hardware Architecture for QRL (2/2) CCC [Contribution : Ph.Gayet – AB/CO/IS] Local Cryogenic Control room Dedicated OWS/DS ACR responsibility QRL test setup ET200 I/O temperature sensors Until October 2005 for QRL tests Then WFIP for LSS8L test
30
30 Status of Hardware for QRL Infrastructure required for: 1) Cryo instrumentation tests for IP8: All done (arcs 7-8 and 8-1) 2) LSS8L tests in 2005 (Q4): To be done GW WFIP to provide (CO) -> Almost ready Profibus WFIP slave installation (ACR) Reconnection WFIP after QRL test (ACR) To requalify WFIP network (CO) -> see Short term planning
31
31 Status of Hardware for Cryo Plant 17 PLC installed, 3 PLC coming PVSS Data Server: - based on Windows XP for commissioning - migration to final Linux version foreseen this summer All PLC systems & components declared in AB/CO asset management system (ABCAM). OK with Cryo planning [Contribution : Ph.Gayet – AB/CO/IS]
32
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 32 Presentation layout Our target schedule Which components and how far are we? Technical difficulties What we’ve learnt ? Enhancements Messages to the users Conclusions
33
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 33 Technical difficulties (1/2) WorldFip : Synchro problem in the arbiter firmware -> Waiting for ALSTOM action (July !) Cryo controls: Necessity to qualify twice the fieldbus (Profibus to WorldFip) but only for IP8
34
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 34 ‘Technical’ difficulties (2/2) Problem of communication between people from different groups and/or departments probably due to ‘CEIWG replaced by NOTHING’ during 1 year! -> Better situation with the AB/CO periodical coordination meetings (twice a month). TS/EL : ‘Mise en service’ for outlets -> see Enhancements chapter
35
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 35 Presentation layout Our target schedule Which components and how far are we? Technical difficulties What we’ve learnt ? Enhancements Messages to the users Conclusions
36
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 36 What we’ve learnt (1/2) The functional test of the WorldFip infrastructure was not possible as foreseen The final tests are now organised in partnership with the equipment groups and TS/IC GatewayNodes Drop Cab. Final test
37
Scheduling of WFIP Final test Power converters QPS
38
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 38 What we’ve learnt (2/2) Thanks to the WFIP validation procedures and the Dry run PC short circuit tests: We know that the Controls infrastructure works fine. We are confident that we can operate the converters during the Short Circuit Tests. We are in phase and with the right speed with the installation schedule.
39
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 39 Presentation layout Our target schedule Which components and how far are we? Technical difficulties What we’ve learnt ? Enhancements Messages to the users Conclusions
40
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 40 Enhancement(s) Closer collaboration and better communication with TS/EL (see next slide)
41
Enhancements from TS/EL
42
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 42 Presentation layout Our target schedule Which components and how far are we? Technical difficulties What we’ve learnt ? Enhancements Messages to the users Conclusions
43
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 43 Messages in the bottle BDI : It’s time to organise the installation (assembly, configuration, test) for the 200 VME crates RF, PO, … : Please, request your WorldFip connection on time
44
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 44 Conclusions Installation : Point 8 is done & Point 1 is progressing well BUT we continue: To follow up the clock synchro problem on WorldFip firmware (AB/CO and ALSTOM) To keep close collaboration with other groups and the coordinators.
45
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 45 Contribution from AB/CO people especially from: R.Brun, Ph.Gayet, R.Lauckner, P.Le Roux, B.Puccio, M.Vanden Eynden, Z.Zaharieva, M.Zerlauth Thank you Comments or questions?