Download presentation
Presentation is loading. Please wait.
Published byMercy Pierce Modified over 8 years ago
1
Frankfurt (Germany), 6-9 June 2011 Romanens – CH – S3 – 0220 Impact of Distributed Generation on Grid Protection BKW FMB Energie AG Switzerland Florian Romanens Paper n° 0220
2
Frankfurt (Germany), 6-9 June 2011 Content Introduction BKW FMB Energie AG and its grid Changes in existing distribution grids Some requirements considered by BKW Protection concept Short-circuits and earth-faults Frequency Conclusion
3
Frankfurt (Germany), 6-9 June 2011 Introduction BKW FMB Energie AG and its grid Swiss utility company based in Bern Generation, transport and distribution of electricity Grid: Transmission grid:380kV, 220kV Over-regional distribution grid:132kV, 50kV Regional distribution grid:16kV, 0.4kV Interconnected topology radial topology
4
Frankfurt (Germany), 6-9 June 2011 Introduction Changes in existing distribution grids Existing distribution grids are often built only for load flow DG can create a change in the power flow by BKW: - 16kV - star point isolated
5
Frankfurt (Germany), 6-9 June 2011 Some requirements considered by BKW DG-protection systems have to recognize: earth-f. and short-c. in case of fault on the DG-side quickly trip the DG-circuit breaker earth-f. and short-c. in case of fault in the grid normally allow sufficient time for the grid to clear the fault. If the fault is not cleared after a certain time, trip the DG-circuit breaker over / under frequency and over / under voltage have to stay connected if f>47.5Hz and U>80% Normally, a communication between substation and DG is used to realize an “intertrip” from the protection of the bay (in the substation) to the DG-circuit breaker
6
Frankfurt (Germany), 6-9 June 2011 Short-circuits and earth-faults Protection zones Each zone is defined by the CBs and CTs (beginning / end) Paper n°0220 shows the protection concept for each zone 16kV switchgear Line between substation and DG Other parts of the grid DG-zone
7
Frankfurt (Germany), 6-9 June 2011 Short-circuits and earth-faults Example: fault in the 16kV GIS in the substation GIS have a rated arcing duration of 1.0s Faults in the GIS have to be cleared within 1.0s On the BB: cleared by the reverse interlocking busbar prot. with special “BB- intertrip” Between CB and cable termination, the “intertrip” to the circuit breaker of the DG is used intertrip Simple over current functions are not appropriated
8
Frankfurt (Germany), 6-9 June 2011 Frequency Example with the frequency DG have to stay connected if f>47.5Hz & U>80% Important for the stability of the grid in case of a large disturbance Under Frequency Load Shedding (UFLS) If the load is bigger than the generation, the frequency will fall. In this case, a certain amount of load has to be shed, but the production has to stay connected to support the grid. generationload
9
Frankfurt (Germany), 6-9 June 2011 Conclusion DG are / will be connected to the distribution grid Due to DG, the power flow-direction can change Grid configuration has to take DG into account Especially protection concept have to be adapted for DG The sum of a lot of small generation units can impact on the stability and reliability of the grid Some requirements mentioned are difficult to fulfill. Therefore, the collaboration among the partners involved in projects with DG is very important
10
Frankfurt (Germany), 6-9 June 2011 Thank you for you attention!
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.