MICE Project Progress Update Power Converters Rack housing MQ1 to MQ3 magnet power converters –Marshalling for all other quadrupole & dipole units –Houses controls VME crate & magnet ON lamp monitoring –Awaiting delivery of monitoring crate. Due end July-07 –Rack 95% complete –Wiring & Termination drawings complete –Electrical & controls checkout w/c 30-July-07
2
MICE Project Progress Update Decay Solenoid Solenoid power supply tested & ready for return to RAL –To be located on mezzanine floor –Mezzanine floor requires strengthening –Control interface requirements known –Drawings to be updated to show requirements
3
MICE Project Progress Update Cable Management Basic tray & trunking layout complete Drawing 204-70002 sheets 1 to 7 issued –Installation can now proceed Main MICE Hall cable routes & to LCR design complete Cable schedule complete for magnet power converters Mains distribution for power converters & LCR complete Mains distribution boards to be purchased & installed LCR tray work design complete –Rack support frames to be manufactured –Tray work to be installed –Raised floor to be installed Phase 2 electrical requirements under review –Detailed information for all systems required
4
MICE Project Progress Update Personnel Safety Rack Internal wiring 75% complete Terminals & relays installed Control crates in build UPS on order Testing at DL mid-August Delivery to RAL end August