Griffin-Spalding County Airport LPA Group Project Update Presented to September 28, 2009
2
Today’s Briefing AIP -28 – Project Update –Crack Seal, Rejuvenate, and Marking of Existing Airfield –Repackage West Taxiway Rehabilitation Project –Design Itinerant Apron Rehabilitation Environmental Study Update –Existing and New Airport
3
AIP-28 – PROJECT UPDATE Crack Seal, Rejuvenate and Marking –Entire Airfield Including Apron and Taxilanes –Scheduled to Start Construction Mid-October –Construction Duration Approx. 1 Month –Will Provide Extended Life to Existing Pavement –Will Give the Airport a Fresh Look
4
AIP-28 – PROJECT UPDATE
6
Repackage and Rebid West Taxiway Improvements Project –Last Year’s Project – Pavement Reconstruction –Anticipate Construction Next Summer (depends on State Funding) Rehabilitate Itinerant Apron Project –Overlay and Reconstruction of Terminal Area Apron –Anticipate Construction Next Summer (depends on State Funding)
7
ENVIRONMENTAL UPDATE Contracts Under GDOT Review –State Block Grant Requires GDOT to Review Contracts –Comments Expected Back This Week Once Contract Finalized, Study Should Take Approximately 1 Year to Complete