12/08/20111 PHENIX WEEKLY PLANNING 12/08/2011 Don Lynch.

Similar presentations


Presentation on theme: "12/08/20111 PHENIX WEEKLY PLANNING 12/08/2011 Don Lynch."— Presentation transcript:

1 12/08/20111 PHENIX WEEKLY PLANNING 12/08/2011 Don Lynch

2 12/08/20112 This Week Continue RPC1 N commissioning RPC1 S Installation Done, Begin RPC1 S commissioning Continue MuTr station 3 North Clamp-on re-capacitors in MMN FVTX rack assembly Done? Continue design and procurement for RPC3 shielding Remove hanging platform Done Reconfigure scaffold for RPC1S survey Done Move VTX/FVTX West to 1008 Done Install VTX/FVTX West Done Move VTX/FVTX East to 1008 Done Survey RPC1S Done Survey and align CM and beampipe Done Survey VTX/FVTX West Install FVTX racks Install VTX/FVTX West cables and services BBC South installation Done MPC South troubleshooting Install VTX/FVTX East Survey VTX/FVTX East Install VTX/FVTX East cables and services Continue prep of EC for roll in

3 12/08/20113 Next Week Complete Survey VTX/FVTX East and overall Continue RPC1 N & S commissioning Complete MuTr station 3 North Clamp-on re-capacitors in MMN Complete VTX/FVTX cabling & fiber installation Install new MPC racks Remove all scaffolding from IR Remove manlift and plates from IR Move MuID collars to IR Move 12 ton rolling cart to AH winter home Roll in EC Prep EC for run (platforms, ladder, dumb waiter, electric, fiber, gas

4 12/08/20114 2011 Shutdown CM alignment stopsDesign Done, Fabrication in Progress Reinstall BBC South12/7 MPC S troubleshooting12/8 Upgrade AH craneAfter 1/17/2012 RPC3 ShieldingLarge Blocks placed Rail extensions for garage in progress RPC HodoscopeMech Installation Done Cabling Prep for EC roll in EC prepDone Remove manlifts and plates12/14 Preposition MuID collars 12/14 reinstall MMS east vertical lampshadeDone CM alignment & BP Survey (Final after VTX/FVTX installed)12/8 MPC electronics rack upgrade installation12/14 Roll in EC12/15 Prep IR for run12/16 IR run prep, Pink/Blue/White sheets12/19-1/6/2012 New and upgraded full detector commissioningIn progress to 1/16/2012 Run 12 cooldown 1/17/2012 General Tasks

5 12/08/20115 VTX/FVTX Tasks 2011 Shutdown FVTX/VTX Chiller leak/contamination improvementsDone FVTX west assembly and QA testsDone FVTX west pre-surveyDone VTX pixel/strip pixel repairsDone VTX west re-assembly & QA testsDone FVTX east assembly and QA testsDone FVTX west integration with VTX west Done Move FVTX east to Chem labDone FVTX east pre-surveyDone VTX east reassembly and QA testsDone FVTX east integration with VTX east Done FVTX/VTX east half surveyDone FVTX/VTX west half surveyDone FVTX/VTX complete alignment survey in Chem. LabDone Install FVTX fibers from rack room thru AH/sill to CMDone Final FVTX/VTX QA tests and thermocouple wiring Done Move west FVTX+VTX half to 1008Done Move east FVTX+VTX half to 1008Done Install FVTX/VTX west detectors(mechanical)Done FVTX racks readyDone ? Survey FVTX/VTX west detectors(mechanical)12/8 Install FVTX racks on bridge12/8 FVTX/VTX west cable routing, plumbing, QA tests12/9 Install FVTX/VTX east detectors(mechanical)12/9 Survey FVTX/VTX east detectors(mechanical)12/9 FVTX/VTX east cable routing, plumbing, QA tests12/13 FVTX/VTX final electrical/fiber/plumbing/monitoring installation12/16

6 12/08/20116 Install and test RPC1 North including all cables and plumbingDone Build 1 new rack, upgrade existing RPC1 prototype rack and install on BridgeDone Move CM north to run positionDone Install scaffolding in station 1 southDone Modify BBCS cable routing Done Install RPC1 S Done RPC3 HV Distribution modifications, gas distribution Done modifications, PS calibration HV and services testing Remove hanging platformsDone RPC1 north and south commissioning In progress Remove all scaffolding 12/12 2011 Shutdown RPC Tasks

7 12/08/20117 Station 1 North Upgrade (remove, recapacitate, clean, reinstall)Done Station 2 North (north and south sides) and South (south side only) upgrade – remove dry air headers, modify headers, install terminator boards, reinstall modified headersDone MuTr North & South Station 3 Re-cap clamps Install work platforms (north and south for capacitor clamp installation to lower octants of station 3)Done Install new capacitor clamps in lower octants(South Done North In Progress) 7/25-12/21 Install new dry air manifolding to Cap clamp headers(South Done North In Progress) 11/21-12/21 Remove work platform & steps from MMSDone Re-install MMS east vertical lampshadeDone Remove work platforms from MMN12/21 MuTr Tasks 2011 Shutdown

8 12/08/20118 Electronics Group Tasks 2011 Shutdown MPC electronics replacement Build racks12/9 Install & wire racks 12/16 Test12/31 RPC hodoscope installation Run cables 12/31 Test12/31 RPC1 Wiring Install cablesDone TestDone Run 12 restoration of detectors EC rewire (power/cable/fiber)12/16 CM restore magnet power, cooling12/16 WC upgrades12/16 Pink/White/Blue Sheets1/6/12 VTX restoration Reinstall cables, fiber, cooling, monitoring12/12 FVTX installation and cabling Racks: assemble, test, install on bridge12/8 Fiber: install, terminate and connect12/13 LV sensor and wedge: fabricate, install, terminate and connect 12/13 Other ???1/17/2012

9 12/08/20119 Replace MuTr flowmeters (north and south) north done, south by - 12/31 Replace tygon lines (80 lines) from the cooling manifolds to the detector with 1/4" ID teflon tubing.Lines ready for installation Insulate whatever Big Wheel chiller lines in the IR that we can get to to reduce sweating in the IR. AH lines are done Build a system to clean the Novec during the run. In progress Pixel cooling upgrade for 10 º C without impacting strip-pixel cooling. Ready for installation Replace all cooling RTD transmitters Parts here ready for installation Upgrade Mutr, MuID and DC/PC computers in GMH by 12/15Done RPC station 1 gas panels: (north and south)Done RPC Station 1 supply lines and exhaust (connecting to existing lines).Done Plumbing new supply for R134A, incl. heat tape and insulation.Done MuID panel circulation. Class one div 2 fans. Design in progress? Dry air for Mutr HV work. (north and south)South done, North in progress Dry air filters to be replaced before run starts.Done Other??? 2011 Shutdown Miscellaneous Gas & Cooling System Tasks

10 12/08/201110 RPC1N RPC1S

11 12/08/201111

12 12/08/201112 VTX/FVTX

13 12/08/201113 Gas Mixing House East Annex for R134A bottles close to GMH.

14 12/08/201114 Station 2/3 S/N Access North Magnet Platform South Magnet Platform Out and Done

15 12/08/201115 MPC new electronics racks

16 12/08/201116 Roof leaks in utility bathroom at northwest corner behind tech offices, over door between rack room and assembly hall, over door between control room and elect. ass ’ y room, southeast corner of IR and laser room. Flooding in AH/ Driveway heaving Electronics test/assembly room- to-parking lot door (does not open/close/lock properly – needs to be replaced) Infrastructure Issues

17 12/08/201117 Safety, Security, Etc. From Ray Karol: Both north and south tunnels will be ODH1 at the start of run 12. Anyone needing access (e.g. RPC3’s) will need a film badge, ODH1 web training, ODH practical training, and physicals up to date. Per John Maraviglia of CAD: The practical training for ODH1 (which for most of us expires soon and will need to be retaken before run 12 cooldown in order to be able to access either the north or south tunnel and RPC3;’s) wil be given in Snyder Hall, building 911 on one of the following days: 12/8/11 (tomorrow) at 11:15 AM 12/911 (Friday) at 11:15 AM 12/16/11 (NextFriday) at 11:15 AM The class takes about a ½ hour. There will be additional classes scheduled in early January for those who can’t make these 3 sessions. PHENIX annual safety review 11/22/11 Rob, Paul, Steve and Don to prepare as usual. Mods to WC platforms: gates and railings plan needed

18 12/08/201118

19 12/08/201119

20 12/08/201120 Where To Find PHENIX Engineering Info Links for the weekly planning meeting slides, archives of past meeting slides,long term planning, pictures, videos and other technical info can be found on the PHENIX Engineering web site: http://www.phenix.bnl.gov/WWW/INTEGRATION/ME&Integration/DRL_SSint-page.htm