March 4, 2013 Photo by Martin Murphy. Shutdown 2012 Machine Status: Linac running with NTF Treatments, RFQ and Linac commissioning Booster beam commissioning.

Similar presentations


Presentation on theme: "March 4, 2013 Photo by Martin Murphy. Shutdown 2012 Machine Status: Linac running with NTF Treatments, RFQ and Linac commissioning Booster beam commissioning."— Presentation transcript:

1 March 4, 2013 Photo by Martin Murphy

2 Shutdown 2012 Machine Status: Linac running with NTF Treatments, RFQ and Linac commissioning Booster beam commissioning and studies TeV & Muon Rings – Partially available for tours with approval and appropriate training

3 Power Outages - Unplanned  Feeder 46B o Tuesday, January 29th  Isolated fault (Between F4 & P71)  Repairs pending

4 MSS Bypass Project - Completed  Booster  High Intensity Lab (HIL)  Neutrino Service Building 7 (NS7)  Proton Service Building 1 (PS1)  Neutrino Service Building 1 (NS1)

5 Power Outages – MSS Bypass Project  MS2 Oil Switch o February 25 th for ~ 2 weeks  Will be running house power off a generator (Until 3/8)  Impacts – MS2 Service Building and Adjacent Enclosure (M02)  MS1 Oil Switch o March 11 th for ~ 2 weeks (3/11 or 3/12 0800-1000)  Will be running house power off a generator  Impacts – MS1 Service Building and Adjacent Enclosure (M01)

6 Power Outages – Planned  WH8FC – Wilson Hall 8 th Floor Fiber Central Sunday, March 10 from 0600 – 1200 ○ Although this is a very local power outage, its effects are widespread and all networking in Wilson Hall will be offline including: Finance backup systems (5th floor) Remote Operating Center (ROC) Com Center 12th floor control room Service Desk Cardkey Access – works but no changes or updates ○ DOE Office CUB Minos/IF Underground networking FESS/WH building monitoring (16th floor) Several redundant Kerberos, Windows and Fermi domain controllers will also be down when WH8FC is powered off.

7 Shutdown 2012 Schedules and Links: Schedule can be accessed from the Operations Home Page - Schedules -> Operations Schedule Direct link to schedule - http://www-ad.fnal.gov/ops/schedule.html ANU - http://www-cons/http://www-cons/ Proton Source -http://www-ad.fnal.gov/proton/protonsched/shutdown2012.htm l


Download ppt "March 4, 2013 Photo by Martin Murphy. Shutdown 2012 Machine Status: Linac running with NTF Treatments, RFQ and Linac commissioning Booster beam commissioning."